NextDecade Provides Second Quarter 2025 Business Update

NextDecade Provides Second Quarter 2025 Business Update

Business Wirea day ago
HOUSTON--(BUSINESS WIRE)--NextDecade Corporation (NextDecade or the Company) (NASDAQ: NEXT) today provided an update on developmental and strategic activities for the second quarter 2025 and early third quarter 2025.
'NextDecade continues to make significant progress constructing Phase 1 of Rio Grande LNG safely and developing expansion capacity at Rio Grande LNG. We recently completed the commercialization of Train 4, updated the engineering, procurement, and construction (EPC) contract for Train 4, signed our first long-term offtake agreement for Train 5, and signed the EPC contract for Train 5,' said Matt Schatzman, NextDecade's Chairman and Chief Executive Officer. 'Phase 1 remains on schedule and on budget, and we are progressing Trains 4 and 5 quickly toward final investment decisions (FIDs).'
'In April, we completed the commercialization of Train 4 with the announcement of 20-year LNG sale and purchase agreements (SPAs) with Aramco and TotalEnergies, which join ADNOC as the long-term customers supporting Train 4. In May, we announced a 2 million tonnes per annum (MTPA), 20-year LNG SPA with JERA, marking the first long-term SPA for Train 5 and serving as a testament to the strong demand we continue to see for offtake from the Rio Grande LNG Facility.'
'We are progressing the financing process for Train 4 and, subject to finalizing adequate financing, we expect to achieve a positive FID on Train 4 by mid-September 2025.'
'We continue to work on contracting an additional 2.5 MTPA under long-term SPAs to support a positive FID on Train 5. We have started the financing process for Train 5 and, subject to obtaining appropriate commercial support and financing, we are targeting FID of Train 5 in mid-September 2025.'
Significant Recent Developments
Construction
Under the EPC contracts with Bechtel Energy Inc. (Bechtel), Phase 1 progress is tracked for Train 1, Train 2, and the common facilities on a combined basis and Train 3 on a separate basis. As of June 2025:
The overall project completion percentage for Trains 1 and 2 and the common facilities of the Rio Grande LNG Facility was 48.3%, which is in line with the schedule under the EPC contract. Within this project completion percentage, engineering was 91.9% complete, procurement was 80.6% complete, and construction was 21.2% complete.
The overall project completion percentage for Train 3 of the Rio Grande LNG Facility was 22.7%, which is also in line with the schedule under the EPC contract. Within this project completion percentage, engineering was 55.7% complete, procurement was 45.5% complete, and construction was 2.2% complete.
Strategic and Commercial
In April 2025, the Company announced a 20-year LNG SPA with a subsidiary of Saudi Aramco (Aramco), pursuant to which the Aramco subsidiary will purchase 1.2 MTPA of LNG from Train 4 at the Rio Grande LNG Facility for 20 years, on a free on board (FOB) basis at a price indexed to Henry Hub, subject to a positive FID on Train 4.
In April 2025, the Company announced that TotalEnergies exercised its LNG purchase option with respect to Train 4 and the Company entered into a 20-year LNG SPA with TotalEnergies, pursuant to which TotalEnergies will purchase 1.5 MTPA of LNG from Train 4 at the Rio Grande LNG Facility for 20 years, on an FOB basis at a price indexed to Henry Hub, subject to a positive FID on Train 4. The Company believes sufficient long-term commercial agreements are now in place to support a positive FID on Train 4.
In May 2025, the Company announced a 20-year LNG SPA with JERA, pursuant to which JERA will purchase 2.0 MTPA of LNG from Train 5 at the Rio Grande LNG Facility for 20 years, on an FOB basis at a price indexed to Henry Hub, subject to a positive FID on Train 5.
In June 2025, the Company finalized a pricing refresh of the Company's lump-sum, turnkey EPC contract with Bechtel for the construction of Train 4 and related infrastructure and executed a lump-sum, turnkey EPC contract with Bechtel for the construction of Train 5 and related infrastructure. Pricing validity under the Train 4 and Train 5 EPC contracts extends through September 15, 2025.
Financial
In April 2025, Rio Grande LNG, LLC elected to terminate $250 million of commitments under its working capital facility due to a decrease in expected requirements for credit support during construction, which reduced the outstanding commitments under the working capital facility to $250 million and is expected to reduce related commitment fees by approximately $2 million annually.
In May 2025, the Company's wholly-owned subsidiary, Rio Grande LNG Super Holdings, LLC, entered into an amended credit agreement with the lender of its existing senior secured loan to increase the loan amount by $50 million to a total of $225 million initial principal. Incremental proceeds from the senior secured loan were disbursed at closing on May 14, 2025, and net proceeds will be used to fund working capital and general corporate purposes, including development expenses for expansion trains at the Rio Grande LNG Facility and specifically pre-FID expenses for Trains 4 and 5. Borrowings under the senior secured loan bear interest at 12.0%, with interest payable quarterly. Interest may be paid in-kind until March 31, 2027 and up to 50% in-kind thereafter. The senior secured loan matures December 31, 2030.
In conjunction with the closing of the May 2025 amendment to the senior secured loan, the Company issued warrants that are exercisable for an aggregate of approximately 2.0 million shares of NextDecade common stock to the lender of the senior secured loan. The warrants are exercisable for five years after the amendment date. The warrants are exercisable at $9.30 per share, which represented a 30% premium to the volume weighted average price for the 30 trading-day period immediately preceding the amendment date.
Regulatory
In July 2025, FERC issued a final SEIS for the first five liquefaction trains at the Rio Grande LNG Facility. Based on its published schedule, FERC anticipates issuing a final order on the remand by November 20, 2025.
Rio Grande LNG Facility
NextDecade is constructing and developing the Rio Grande LNG Facility on the north shore of the Brownsville Ship Channel in south Texas. The site is located on approximately 1,000 acres of land, which has been leased long-term and includes 15,000 feet of frontage on the Brownsville Ship Channel. The Company believes the site is advantaged due to its proximity to abundant natural gas resources in the Permian Basin and Eagle Ford Shale, access to an uncongested waterway for vessel loading, and location in a region that has historically been subject to fewer and less severe weather events relative to other locations along the U.S. Gulf Coast. The Rio Grande LNG Facility has been permitted by the FERC and authorized by the DOE to export up to 27 MTPA of LNG. Phase 1 at the Rio Grande LNG Facility is under construction, Train 4 has been commercialized and is being progressed toward FID, Train 5 is being commercialized and progressed toward FID, and the Company is developing and beginning the permitting process for Trains 6 through 8.
Phase 1 (Trains 1-3)
Phase 1 at the Rio Grande LNG Facility is under construction. Phase 1 includes three liquefaction trains with a total expected LNG production capacity of approximately 18 MTPA, two 180,000 cubic meter full containment LNG storage tanks, and two jetty berthing structures designed to load LNG carriers up to 216,000 cubic meters in capacity. Phase 1 also includes associated site infrastructure and common facilities including feed gas pretreatment facilities, electric and water utilities, two totally enclosed ground flares for the LNG tanks and marine facilities, two ground flares for the liquefaction trains, roads, levees surrounding the development area, and warehouses, administrative, operations control room, and maintenance buildings.
As of June 2025, progress on Trains 1 through 3 is in line with the schedule under the EPC contracts. During the second quarter 2025, the construction team continued piping fabrication, rebar installation, equipment setting and concrete placement, and structural steel erection in the areas of Trains 1, 2, and 3. The eighth wall lift was completed for Tank 1. Across the site, Bechtel also continued installing concrete foundations, instrument air receivers, floodgates, permanent fencing, temporary facilities, and other siteworks.
NextDecade holds equity interests in the Phase 1 joint venture that entitle it to receive up to 20.8% of the distributions of available cash during operations.
Final Investment Decision on Train 4
The Company has completed commercialization of Train 4 and has executed 20-year LNG SPAs totaling 4.6 MTPA of LNG with ADNOC, Aramco, and TotalEnergies in support of Train 4.
In June 2025, the Company finalized an EPC contract pricing refresh with Bechtel for Train 4 and related infrastructure. Pricing validity under the EPC contract for Train 4 extends through September 15, 2025.
The Company launched the financing process for Train 4 in June 2025 and expects to finance construction of Train 4 using a combination of debt and equity funding at the project level. The Company is in the process of entering into a term loan bank facility at Rio Grande LNG Train 4, LLC for the debt portion of the funding.
The Company's Phase 1 equity partners each have options to invest in Train 4 equity which, if exercised, would provide 60% of the equity funding required for Train 4. The Company expects the Phase 1 equity partners to exercise their options to participate in Train 4 equity.
NextDecade currently expects to fund 40% of the equity commitments for Train 4, and to have an initial economic interest of 40% in Train 4, which will increase to 60% after its equity partners achieve certain returns on their investments in Train 4. NextDecade is in the process of financing its equity capital for Train 4.
The Company expects to achieve a positive FID on Train 4 by mid-September 2025, subject to obtaining adequate financing.
Final Investment Decision on Train 5
The Company is also progressing Train 5 toward FID, and the commercialization process is underway for Train 5. In May 2025, the Company announced a 20-year LNG SPA with JERA for 2.0 MTPA of LNG in support of Train 5. The Company is targeting an additional 2.5 MTPA of long-term contracts to support a positive FID of Train 5.
In June 2025, the Company finalized an EPC contract with Bechtel for Train 5 and related infrastructure. Pricing validity under the EPC contract for Train 5 extends through September 15, 2025.
The Company began the financing process for Train 5 in the second quarter 2025 and expects to finance construction of Train 5 using a combination of debt and equity funding at the project level. The Company expects to enter into bank facilities at Rio Grande LNG Train 5, LLC for the debt portion of the funding. Certain of the Company's Phase 1 equity partners have options to invest in Train 5 equity, which if exercised, would provide 50% of the equity funding required for Train 5. Inclusive of these options, NextDecade currently expects to fund the balance of the equity commitments for Train 5, and to have an initial economic interest of up to 50% in Train 5, which will increase to up to 70% after its equity partners achieve certain returns on their investments in Train 5.
The Company continues to pursue financing for Train 5 and, subject to obtaining appropriate commercial support and financing, is targeting FID by mid-September 2025.
Development of Additional Liquefaction Capacity
The Company is developing and beginning the permitting process for additional liquefaction capacity at the Rio Grande LNG Facility site beyond Trains 1 through 5. Trains 6 through 8 are wholly owned by NextDecade and are cumulatively expected to increase the Company's total liquefaction capacity by approximately 18 MTPA once constructed and placed into operation.
Train 6 is being developed inside the existing levee at the Rio Grande LNG Facility site and adjacent to Trains 1 through 5. The Company expects to pre-file an application with FERC for Train 6 in 2025 and a full application with FERC in early 2026. The Company is evaluating multiple areas on the site for the development of Trains 7 and 8 and expects to provide an update on the expected permitting timeline for Trains 7 and 8 in 2025.
Investor Presentation
NextDecade has posted an updated investor presentation to its website concurrently with this release. A copy of this release and the investor presentation can be found on its website at www.investors.next-decade.com.
About NextDecade Corporation
NextDecade is committed to providing the world access to reliable, lower carbon energy. We are focused on delivering secure, low-cost, and sustainable energy solutions through the safe and efficient development and operation of natural gas liquefaction and carbon capture and storage infrastructure. Through our subsidiaries, we are developing and constructing the Rio Grande LNG natural gas liquefaction and export facility near Brownsville, Texas, with approximately 48 MTPA of potential liquefaction capacity currently under construction or in development. We are also developing a potential carbon capture and storage project at the facility that is expected to make meaningful impacts toward a lower carbon future. NextDecade's common stock is listed on the Nasdaq Stock Market under the symbol 'NEXT.' NextDecade is headquartered in Houston, Texas. For more information, please visit www.next-decade.com.
Forward-Looking Statements
This press release contains forward-looking statements within the meaning of U.S. federal securities laws. The words 'anticipate,' 'contemplate,' 'estimate,' 'expect,' 'project,' 'plan,' 'intend,' 'believe,' 'may,' 'might,' 'will,' 'would,' 'could,' 'should,' 'can have,' 'likely,' 'continue,' 'design,' 'assume,' 'budget,' 'guidance,' 'forecast,' and "target," and other words and terms of similar expressions are intended to identify forward-looking statements, and these statements may relate to the business of NextDecade and its subsidiaries. These statements have been based on assumptions and analysis made by NextDecade in light of current expectations, perceptions of historical trends, current conditions and projections about future events and trends and involve a number of known and unknown risks, which may cause actual results to differ materially from expectations expressed or implied in the forward-looking statements. Although NextDecade believes that the expectations reflected in these forward-looking statements are reasonable, it can give no assurance that the expectations will prove to be correct. NextDecade's actual results could differ materially from those anticipated in these forward-looking statements as a result of a variety of factors, including those discussed in NextDecade's periodic reports that are filed with and available from the Securities and Exchange Commission. The taking of a final investment decision on Trains 4 and 5 at the Rio Grande LNG Facility is subject to, among other things, maintaining requisite governmental approvals, entering into appropriate commercial arrangements, and obtaining adequate financing to construct each train and related infrastructure. Additionally, any development of additional expansion trains at the Rio Grande LNG Facility or CCS projects remains contingent upon receipt of requisite governmental approvals, execution of definitive commercial and financing agreements, securing all financing commitments and potential tax incentives, achieving other customary conditions and making a final investment decision to proceed. The forward-looking statements in this press release speak as of the date of this release. NextDecade may from time to time voluntarily update its prior forward-looking statements, however, it disclaims any commitment to do so except as required by securities laws.
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

O2Gold Provides Update on Quebec Aur Transaction; Upsizes Private Placement Financing
O2Gold Provides Update on Quebec Aur Transaction; Upsizes Private Placement Financing

Yahoo

time25 minutes ago

  • Yahoo

O2Gold Provides Update on Quebec Aur Transaction; Upsizes Private Placement Financing

NOT FOR DISTRIBUTION TO U.S. NEWS WIRE SERVICES OR FOR DISSEMINATION IN THE U.S. TORONTO, Aug. 07, 2025 (GLOBE NEWSWIRE) -- O2Gold Inc. (NEX:OTGO.H) ('O2Gold' or the 'Company') is pleased to provide an additional update on its pending acquisition of a gold mining exploration property in Quebec through the purchase of all of the issued and outstanding shares of Quebec Aur Ltd. (the 'Target') pursuant to a share exchange agreement entered into by the Company with the Target and its shareholders dated April 15, 2024, as amended November 14, 2024 (the 'Acquisition'). The Company has upsized the hard dollar portion of its previously announced non-brokered private placement financing (the 'Offering') from 14 million units to 18 million units (the 'Units'). Each Unit will continue to consist of one common share of the Company and one common share purchase warrant (each, a 'Warrant'), and the Units and 16 million common shares issued on a 'flow-through basis' pursuant to the Offering will each continue to be issued at a price of $0.05 per Unit and common share, respectively, for aggregate gross proceeds to the Company of $1.7 million. Each Warrant will continue to entitle the holder to acquire one additional common share of the Company at a price of $0.10 for a period of 24 months from issuance. The Company anticipates using the net proceeds of the hard dollar and flow-through portions of the Offering for general corporate purposes and to fund the phase one exploration expenses on the 9,000 hectare claim package that is the subject of the Acquisition, respectively. The parties continue to work diligently to complete the remaining legal formalities in relation to the Acquisition, which is now expected to close (along with the Offering) in late-2025, subject to the satisfaction or waiver of certain conditions. The Acquisition is more fully described in the Company's press releases dated April 15, 2024, April 23, 2024, April 24, 2024, May 30, 2024, and August 23, 2024, as well as the Company's management information circular (the 'Circular') which was mailed to shareholders of record as of August 26, 2024. Additional information respecting the Offering can be found in the Company's press release dated April 8, 2025. The press releases and Circular are available under O2Gold's profile on SEDAR+ at About O2Gold O2Gold is a mineral exploration company. For additional information, please contact: Scott Moore, Chief Executive OfficerPhone: (416) 861-1685Email: smoore@ Regulatory Statements This press release contains "forward-looking information" within the meaning of applicable Canadian securities legislation. Forward-looking information includes, but is not limited to, statements with respect to the Offering and Acquisition, including closing conditions and timing, and other matters related thereto. Generally, forward-looking information can be identified by the use of forward-looking terminology such as "plans", "expects" or "does not expect", "is expected", "budget", "scheduled", "estimates", "forecasts", "intends", "anticipates" or "does not anticipate", or "believes", or variations of such words and phrases or state that certain actions, events or results "may", "could", "would", "might" or "will be taken", "occur" or "be achieved". Forward-looking information is subject to known and unknown risks, uncertainties and other factors that may cause the actual results, level of activity, performance or achievements of the Company, as the case may be, to be materially different from those expressed or implied by such forward-looking information, including but not limited to: receipt of necessary approvals; general business, economic, competitive, political and social uncertainties; future mineral prices and market demand; accidents, labour disputes and shortages and other risks of the mining industry. Although the Company has attempted to identify important factors that could cause actual results to differ materially from those contained in forward-looking information, there may be other factors that cause results not to be as anticipated, estimated or intended. There can be no assurance that such information will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking information. The Company does not undertake to update any forward-looking information, except in accordance with applicable securities TSX VENTURE EXCHANGE NOR ITS REGULATION SERVICES PROVIDER (AS THAT TERM IS DEFINED IN THE POLICIES OF THE TSX VENTURE EXCHANGE) ACCEPTS RESPONSIBILITY FOR THE ADEQUACY OR ACCURACY OF THIS in to access your portfolio

Heartflow raises $316.7 million in US IPO as medtech listings attempt comeback
Heartflow raises $316.7 million in US IPO as medtech listings attempt comeback

Yahoo

time25 minutes ago

  • Yahoo

Heartflow raises $316.7 million in US IPO as medtech listings attempt comeback

By Ateev Bhandari and Pritam Biswas (Reuters) -Medical technology firm Heartflow said on Thursday it had raised $316.7 million in its U.S. initial public offering, setting the stage for its Nasdaq debut in another test of investor appetite for medical tech companies. The Mountain View, California-based company sold 16.67 million shares at $19 each, compared with a targeted range of $17 to $18 apiece. It upsized its offering and raised the proposed range earlier this week reflecting strong demand. The IPO valued the company at $1.54 billion. U.S. IPOs have picked up pace in a much-awaited recovery, as solid tech earnings and progress on trade deals have helped restore investor confidence. Strong recent debuts mark a reversal from early April, when uncertainty around U.S. President Donald Trump's tariffs paused dealmaking. Heartflow's stock will begin trading on the Nasdaq on Friday under the "HTFL" ticker symbol. The closing of the offering is expected on August 11. J.P. Morgan, Morgan Stanley and Piper Sandler are the lead underwriters for the offering. Following software firm Figma's blowout debut last week, analysts expect companies with a compelling growth story to be welcomed by the public markets. "We expect Heartflow to be well received at launch, especially following Figma's breakout success, which has helped reset sentiment toward high-growth names," IPOX CEO Josef Schuster said. Bain Capital-backed Heartflow leverages AI to create 3D models of the heart via a single specialized scan, improving detection and treatment of coronary artery disease (CAD). As AI gains widespread acceptance, companies embedding it into workflows for meaningful use cases are catching investor attention, with the technology powering gains across various Big Tech businesses. Heartflow's revenue grew 39% for the quarter ended March 31 from a year earlier. Its platform to detect CAD was used in 132,000 patients in 2024. Sign in to access your portfolio

ROSEN, TOP RANKED GLOBAL COUNSEL, Encourages Capricor Therapeutics, Inc. Investors to Secure Counsel Before Important Deadline in Securities Class Action
ROSEN, TOP RANKED GLOBAL COUNSEL, Encourages Capricor Therapeutics, Inc. Investors to Secure Counsel Before Important Deadline in Securities Class Action

Business Upturn

time27 minutes ago

  • Business Upturn

ROSEN, TOP RANKED GLOBAL COUNSEL, Encourages Capricor Therapeutics, Inc. Investors to Secure Counsel Before Important Deadline in Securities Class Action

NEW YORK, Aug. 07, 2025 (GLOBE NEWSWIRE) — WHY: Rosen Law Firm, a global investor rights law firm, reminds purchasers of securities of Capricor Therapeutics, Inc. (NASDAQ: CAPR) between October 9, 2024 and July 10, 2025, both dates inclusive (the 'Class Period'), of the important September 15, 2025 lead plaintiff deadline. SO WHAT: If you purchased Capricor securities during the Class Period you may be entitled to compensation without payment of any out of pocket fees or costs through a contingency fee arrangement. WHAT TO DO NEXT: To join the Capricor class action, go to or call Phillip Kim, Esq. at 866-767-3653 or email [email protected] for more information. A class action lawsuit has already been filed. If you wish to serve as lead plaintiff, you must move the Court no later than September 15, 2025. A lead plaintiff is a representative party acting on behalf of other class members in directing the litigation. WHY ROSEN LAW: We encourage investors to select qualified counsel with a track record of success in leadership roles. Often, firms issuing notices do not have comparable experience, resources, or any meaningful peer recognition. Many of these firms do not actually litigate securities class actions, but are merely middlemen that refer clients or partner with law firms that actually litigate the cases. Be wise in selecting counsel. The Rosen Law Firm represents investors throughout the globe, concentrating its practice in securities class actions and shareholder derivative litigation. Rosen Law Firm achieved the largest ever securities class action settlement against a Chinese Company at the time. Rosen Law Firm was Ranked No. 1 by ISS Securities Class Action Services for number of securities class action settlements in 2017. The firm has been ranked in the top 4 each year since 2013 and has recovered hundreds of millions of dollars for investors. In 2019 alone the firm secured over $438 million for investors. In 2020, founding partner Laurence Rosen was named by law360 as a Titan of Plaintiffs' Bar. Many of the firm's attorneys have been recognized by Lawdragon and Super Lawyers. DETAILS OF THE CASE: According to the lawsuit, throughout the Class Period, defendants provided investors with material information concerning deramiocel, Capricor's lead cell therapy candidate drug for the treatment of cardiomyopathy associated with Duchenne muscular dystrophy (DMD). Defendants' statements included, among other things, Capricor's ability to obtain a Biologics License Application (BLA) for deramiocel from the U.S. Food and Drug Administration (FDA). Further, defendants provided these overwhelmingly positive statements to investors while, at the same time, disseminating false and misleading statements and/or concealing material adverse facts concerning its four-year safety and efficacy data from its Phase 2 HOPE-2 trial study of deramiocel. The lawsuit alleges this caused shareholders to purchase Capricor's securities at artificially inflated prices. When the true details entered the market, the lawsuit claims that investors suffered damages. To join the Capricor class action, go to or call Phillip Kim, Esq. at 866-767-3653 or email [email protected] for more information. No Class Has Been Certified. Until a class is certified, you are not represented by counsel unless you retain one. You may select counsel of your choice. You may also remain an absent class member and do nothing at this point. An investor's ability to share in any potential future recovery is not dependent upon serving as lead plaintiff. Follow us for updates on LinkedIn: on Twitter: or on Facebook: Attorney Advertising. Prior results do not guarantee a similar outcome. ——————————- Contact Information: Laurence Rosen, Esq. Phillip Kim, Esq. The Rosen Law Firm, P.A. 275 Madison Avenue, 40th Floor New York, NY 10016 Tel: (212) 686-1060 Toll Free: (866) 767-3653 Fax: (212) 202-3827 [email protected]

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store