logo
Construction continues on O-Train East extension, with no timeline for opening to passengers

Construction continues on O-Train East extension, with no timeline for opening to passengers

CTV News2 days ago

An O-Train on Line 1 is seen in this undated image. (CTV News Ottawa)
Construction and train testing continues on the new O-Train eastern extension into Orléans, but there is still no word on when passengers will be riding the rails.
A report for the June 12 Transit Committee meeting provides an update on construction on Stage 2 of the light rail transit system, which includes extending O-Train Line 1 from Blair Station to Trim Station.
'In the east, final construction activities and train testing are well underway and nearing completion,' says the report, submitted by Transit Services general manager Renee Amilcar.
'Remaining major fleet activities include software upgrades and operator training. Communication rooms and the setup of system parameters, to ensure devices such as switches and cameras function as required, is now complete at all stations in the east. Communication systems testing continues.'
Amilcar says the commissioning of the communication-based train control system is 'well advanced with multiple trains continuing to run in loops.'
'Boundary testing between stage 1 and Stage 2 territories has been completed.
OC Transpo has already said O-Train Line 1 service will be affected on the weekends of July 5 and 26 for Stage 2 Integration work, and there will be additional impacts on Line 1 through the summer as testing and commissioning progresses on the eastern extension.
Amilcar says operator training on Stage 2 East is expected to begin in late July, which will lead to the certification of the required number of personnel to support trial running on the O-Train line.
The report says there is several things to do before opening the eastern extension of O-Train Line 1 to customers, with the 'path to revenue service' including testing and commissioning, substantial completion, trial running and final safety approval.
After the contractor achieves substantial completion, the city will begin trial running on the east extension and the existing Stage 1. Amilcar says trial running will 'exercise and evaluate the performance' of the system's infrastructure, vehicles, operating and maintenance personnel and operating procedures. There will be a 21-day Trial Running period before launch.
The report does not mention a timeline for opening the O-Train East Extension, but Amilcar has previously mentioned the fall for opening to passengers.
Convent Glen Station
An overhead view of the new Convent Glen Station on the O-Train east extension. (OC Transpo/report)
Here is a look at some of the items to be completed, according to the report.
System installation, integration, testing and commissioning
'Significant work is currently underway to integrate communication systems for the east extension with the existing live systems on Line 1,' Amilcar said.
'Testing of systems began in a lab environment and will be migrated to a production environment over the next several weeks. This iterative and complex integration process will be phased and carefully coordinated to minimize customer impact.'
Amilcar says the majority of the system integration work will be conducted during overnight hours, but there may be some closures on the O-Train line.
Operations and maintenance readiness
Amilcar says 'work is progressing' on the training program, staffing and recruitment and maintenance readiness.
The hiring of new Electric Rail Operators and the familiarization training is underway, and training on Stage 2 is expected to begin in late July.
Line 1 East Stations
Amilcar says occupancy permits for the stations are expected over the summer.
'Station occupancy for the east stations is nearly complete with deficiency closeout, building code service reviews, and occupancy permits expected in Q3 2025.'
Work outside the 'guideway'
Amilcar says work 'outside the guide' required for substantial completion is currently underway, including grading, drainage, headwall installation, slope finishing, top-lift paving, guardrail installation and landscaping along Highway 174.
That work is expected to be completed this spring.
The second phase, following Substantial Completion' includes slope finishing, top-lifting paving, guardrail installation and landscaping.
Once the eastern extension opens, Line 1 will stretch 25 kilometres between Tunney's Pasture and Trim Station.
The western extension from Tunney's Pasture to Moodie Drive and Algonquin College is scheduled to open in 2027.

Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Justice department cutting up to 264 jobs as it faces ‘budgetary pressures'
Justice department cutting up to 264 jobs as it faces ‘budgetary pressures'

CTV News

time33 minutes ago

  • CTV News

Justice department cutting up to 264 jobs as it faces ‘budgetary pressures'

The Canadian flag flies on the Peace Tower of Parliament Hill as pedestrians make their way along Sparks Street Mall in Ottawa on Nov. 9, 2021. THE CANADIAN PRESS/Sean Kilpatrick OTTAWA — The federal department of justice is set to lay off up to 264 employees as it navigates what it calls 'significant budgetary pressures.' Ian McLeod, a spokesperson for the department, says in an email that the department is taking 'difficult but necessary' steps to manage available resources, given ongoing budget pressures that 'can no longer be sustained.' He says 264 positions in the department 'may no longer be required' and that the employees in those roles were notified this week. McLeod says the department has implemented 'several measures' aimed at addressing budgetary pressures over the past year, including staffing restrictions. The number of federal public service jobs dropped by almost 10,000 in the last year, marking the first decrease since 2015. As of March 31, 357,965 people were working for the Government of Canada, down from 367,772 in 2024. Between 2024 and 2025, the justice department lost 29 workers, going from 5,637 to 5,608 employees. Hundreds of workers in other federal organizations — like the Canada Revenue Agency, Employment and Social Development Canada and Immigration, Refugees and Citizenship Canada — also have been laid off recently. Prime Minister Mark Carney has vowed to cap, not cut, the federal public service. He also has promised to launch a 'comprehensive' review of government spending with the aim of increasing its productivity. This report by The Canadian Press was first published June 6, 2026. Catherine Morrison, The Canadian Press

Shovels hit the ground on new village near beachfront in Wasaga Beach
Shovels hit the ground on new village near beachfront in Wasaga Beach

CTV News

timean hour ago

  • CTV News

Shovels hit the ground on new village near beachfront in Wasaga Beach

Architect's drawings of 'The Breakers' Village, Phase One fronting 1st Street near Beach Area 1, which is expected to be completed this summer. (The Town of Wasaga Beach) Shovels hit the ground Friday in Wasaga Beach as construction started on phase one of the new commercial and residential village near Beach Area 1. Back in May, Sunray Group CEO, Ray Gupta, joined Mayor Brian Smith to announce the $45 million premium Marriott hotel set to anchor the new beachfront. These residential and commercial spaces will house new shops and cafes and complement the premium Marriot Hotel, restaurants and other amenities being built by Sunray Group in early 2026. 'Today, (Friday) we are putting shovels in the ground on a high quality, mixed-used village right here along 1st Street near Beach Drive. Stonebridge will build a diverse range of residential and commercial spaces that will house new shops and cafes, which will support year-round economic activity near Beach Area 1 and Beach Area 2. This will complement the premium Marriot Hotel, shops, restaurants and other amenities being built by Sunray Group,' said Mayor Brian Smith. 'This is all part of the Town's plans to reimagine our main beachfront and commercial area – to build Destination Wasaga – and reinvent our community as a thriving, four-season destination.' In November of last year, Stonebridge Building Group was awarded a contract by the town to design and develop a 5.18 acre portion of property near Beach Area 1 between 1st Street and 3rd Street. Sunray Group Sunray Group unveiled that it will build a premium Marriott Hotel in Wasaga Beach on Beach Drive at Beach Area 1 on May 21, 2025. (Supplied) 'Stonebridge understands the significance of this project for Wasaga Beach, and we're invested in the community's success,' said Mark Crowe, President of Stonebridge Building Group. 'Our team is proud to help build a vibrant, year-round village near the beachfront that will support local businesses and help reinvent Wasaga Beach as a thriving, four-season destination.' The village near Beach Area 1 will include open spaces, a public park, public art and a focus on live-work town homes with ground floor commercial space. In total, the project will include over 150 residential units and 31 commercial units. Phase 1 of the construction project includes 26 residential units and five commercial units. According to the town, this five-phase project is anticipated to be completed over the next three years. Stonebridge Building Group says they will pay for demolition costs related to this project. It is also working with the town on redesigning 1st Street. Back in May, Sunray Group said they planned to build a 120-room Marriott hotel in phase one of what will be a four-phase project near the town's beachfront. To learn more about the Marriot Hotel, click here. Related Articles

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into the world of global news and events? Download our app today from your preferred app store and start exploring.
app-storeplay-store