Auckland Rail Network Reopens After Successful Upgrades

Auckland Rail Network Reopens After Successful Upgrades

Scoop28-04-2025

Press Release – KiwiRail
2025's second Auckland rail closure draws region closer to CRL opening
Auckland rail services are back up and running as KiwiRail and its partners continue to deliver an ambitious work programme across the region including major infrastructure projects.
As passenger trains return to service today, Auckland's rapidly growing Franklin community will benefit from trains running twice as often at peak times. This is possible because of the huge progress made across the rail network during the April rail closure.
Teams undertook upgrade and renewal works at more than 80 sites across Auckland's rail network during the two-week closure. About 900 workers continued to deliver an ambitious programme including major infrastructure projects, as KiwiRail and Auckland Transport (AT) ready the rail network for the faster, more frequent train services the City Rail Link (CRL) will bring when it opens next year.
The rail elements of the Wiri to Quay Park (W2QP) Third Main project are now complete and entering the operational readiness phase. This critical project on the Southern Line separates passenger and freight trains on the busiest parts of the Auckland network.
'Despite some appalling weather, all projects we'd planned for the 16-day shutdown are now complete after KiwiRail teams successfully managed a large amount of work safely within tight deadlines,' says David Gordon, KiwiRail's Chief Capital Planning and Asset Development Officer. 'I'm really proud of our hard-working staff and contractors who gave up their Easter and Anzac breaks to make a big dent in the upgrade and renewal programme needed before the CRL can open.
'The Wiri to Quay Park project completion is a major mark of maturity for the Auckland rail network, keeping freight and commuters moving into the future. The Third Main Line, the newly triple-tracked section between Wiri and Westfield, provides a separate track for freight trains, meaning faster and more reliable transportation for KiwiRail's valued freight customers.
'This milestone follows the opening earlier this year of the Papakura to Pukekohe newly electrified section of the network, with a redeveloped train station at Pukekohe.'
KiwiRail also would like to take the opportunity to thank our freight customers for their understanding and cooperation with the use of roads to move their goods during the two-week rail closure.
The opening of the CRL next year will mean more trains on the network, doubling the number of Aucklanders who live within a 30-minute train journey to the central city and significantly cutting journey times. Ahead of this, an upgrade of priority areas, the construction and fit out of new stations, and the integration, testing and commissioning of new systems are required.
This has meant closing the entire rail network at its quietest times of usage – over public, school and university holidays. More closures will occur this year over long weekends, school holidays and the 2025-26 summer to progress more upgrade and renewals works, as well as three new train stations on the Southern line.
KiwiRail colleagues in the Link Alliance used the April closure to focus on completing works in the CRL tunnels and the connections to the rest of the railway.
Trains are now running down the CRL tunnels as part of a rigorous testing programme – covering everything from the infrastructure and rail systems interfaces, emergency procedures and scenarios, the stations and urban realm, and some simulated stress testing.
In this video, you can see a train travelling at full speed in the new 3.45km CRL tunnel in Auckland. This is described as 'line speed', which is 70kph. The video, which shows the perspective of the driver, is a rare glimpse of a train travelling in the tunnels that are 42m underground.
'We're really pleased with the amount of work achieved over the April rail closure, and seeing everything is on track for CRL's opening in 2026,' says Auckland Transport Director Public Transport and Active Modes Stacey van der Putten.
'We know every time the rail network closes it causes serious disruption for our customers, but with each day the network is closed we get a step closer to having the modern, fast, frequent and reliable rail network Aucklanders deserve.
'Following this closure we're also able to increase the frequency of trains to Pukekohe from today, with trains running to the city centre every ten minutes during peak times.
'I know it is inconvenient for people not to be able to catch the train, but AT and our partners at KiwiRail have a short time frame to deliver the necessary work to be ready in time for CRL opening.
'During the rail closure, we saw high uptake of our rail replacement buses and we're continuing to listen to customer feedback and make improvements where possible. The bus stop changes in west Auckland saw better rail bus reliability and we're currently investigating rail bus priority opportunities for future planned rail closures.
'These upgrades provide better experiences on our public transport network. Since Pukekohe Station reopened in February 2025, we're close to reaching the same amount of people using this station as in 2019, even as people continue to work from home more often. We're very pleased to see the high uptake.'
Other highlights of the April rail works include:
Completion of the construction of the Wiri to Quay Park (W2QP) Third Main Line, now ready for its operational readiness phase
Completion of Quay Park signals commissioning, successfully concluding all W2QP signalling works
Progressing the final stages of Rail Network Rebuild (RNR) focused on priority areas of the Southern Line, between Wiri and Papakura
The final stages of the Middlemore Station redevelopment
Ongoing work on the Western Power Feed in Glen Eden, which will add greater electricity capacity to the network in Auckland, boosting its resilience and allowing for future growth
Progressing construction of new train stations at Drury Central, Paerātā and Ngakoroa in South Auckland
Commissioning signalling at Quay Park
Building a third platform and additional tracks at Henderson Station, as well as continuing the upgrade of the lifts as part of AT's station improvements
Undertaking weather proofing maintenance at Newmarket Station
Soundproofing works at Waitematā (Britomart) Station
Maintenance work across Auckland, including replacing rails, turnouts, sleepers and ballast.
More information about the range of rail improvement work in Auckland is available at:
https://www.kiwirail.co.nz/our-network/our-regions/amp/
The Easter rail closure in stats:
More than 80 sites
More than 900 people
60% of Rail Network Rebuild Upgrades (RNR) delivered 24/7
RNR teams worked across about 31km of the network.
Excavated and replaced more than 2.4km of foundation and upgraded a similar amount of drainage
Excavated and replaced almost 13,000 tonnes of ballasted track (the rocks that the track sits on) between Wiri and Papakura.

Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Why drivers don't stop at train crossings
Why drivers don't stop at train crossings

RNZ News

time2 days ago

  • RNZ News

Why drivers don't stop at train crossings

Nearly half of motor vehicles fail to stop, or prepare to stop when approaching level crossings in research commissioned by Kiwirail. They were least likely to do so where there were just Give Way signs in place. The engineering and professional services consulting firm WSP observed more than 3600 drivers - 47 per cent failed to stop at crossings with Stop signs, or were ready to stop at Give Way signs. Earlier research had found more than half of the deaths in serious level crossing collisions over a ten-year period occurred at crossings with Stop or Give Way signs. There have been 25 collisions at crossings in the last two years. The report says 'Look for Trains' signs had significantly higher success getting drivers to stop and look - and a major recommendation of the review was to remove all Give Way signs for Stop signs. Paul Ashton is chief operations officer at Kiwirail. Photo: Supplied by Kiwirail

Skifields on schedule to open: CEO
Skifields on schedule to open: CEO

Otago Daily Times

time2 days ago

  • Otago Daily Times

Skifields on schedule to open: CEO

For once, it is white on time. Snowguns at Queenstown's Coronet Peak and The Remarkables skifields fired up last night, and they will keep cranking for as long as possible to bolster the natural snowfall arriving in a perfectly timed polar blast, ahead of the scheduled season opening on June 14. NZSki chief executive Paul Anderson expected up to 30cm of snow could be on the way, but more importantly, bitterly cold temperatures forecast would enable "solid snow-making" over the next five or six days which should mean Coronet could open top to bottom next week. "We are confident that we will be open on the 14th, as advertised." Mr Anderson said the plan was for both Queenstown skifields to open on the same day. "The reason we've done that, I noticed this last year, as soon as we opened, town got busy. "I think it's really important that we send a really strong signal to the market that Queenstown is open for business." He believed last month was "one of the most sudden shoulder seasons we've had for a few years", but questioned if it was just more noticeable because of the huge influx of people to the Wakatipu between Easter and Anzac Day. NZSki employs about 1300 people across its three mountains including Mt Hutt. Of those, 900 are in Queenstown. Mr Anderson said the company had a staff return rate of more than 50% and a record 6000-plus applications for about 600 remaining jobs. Accommodation-wise, some of the heat had been taken out of the market through a 90-bed CBD hostel, a new apartment development off Fryer St, comprising six two-bedroom units, and four or five houses NZSki owned near Gorge Rd, all of which were full. "Then you'll have staff that are returning that already know where they're going — they kind of work out their flats and flatting situations, year to year — so we're focused on the new people coming in." Transport to and from The Remarkables would be similar to last year. Those who did not have a full car would be in carpark 4 and get a shuttle "right up to the door" of the ski area, ensuring families and those with full cars got the closest parks. Cardrona Alpine Resort, owned by RealNZ, was also targeting a June 14 opening. Treble Cone has a tentative opening date of June 27.

Trains To Huapai Public Meeting
Trains To Huapai Public Meeting

Scoop

time3 days ago

  • Scoop

Trains To Huapai Public Meeting

Press Release – Public Transport Users Association Transport advocacy groups the Public Transport Users Association (PTUA) and Campaign for Better Transport (CBT) are hosting a public meeting to discuss Trains to Huapai at St Chad's Church, 7 Matua Rd, Huapai, at 1.30pm on Saturday 7 June 2025. Northwestern residents in urban Huapai-Kumeu and surrounds, arguably have the most stressful commute in the country, and inadequate public transport. The two-lane State Highway 16 has 16,000 more vehicles than the Waikato Expressway, 10,000 more than Transmission Gully and 12,000 more than the Puhoi to Warkworth motorway. Auckland Transport's 'solution' only offers a rapid busway in 10-20 years which will require the demolition of the Kumeu/Huapai central business the people need public transport now and rail is the best and easiest option which could be delivered in short order. Trains to Huapai services could use existing infrastructure. A crossing loop is available at Waitakere to run an hourly shuttle to Swanson and half hourly in the rush hour. The Waitakere tunnel is fit for electrification, hybrid-electric, or fully diesel trains. Three privately owned train sets are available for use. A four carriage train set could be provided for $150k within six months – so a rail service could be in place when the City Rail Link opens. A private investor is prepared to pay for the service for five years. KiwiRail initially said the cost for such a service was $145m. They now say it is now $20m. PTUA analysis says it could be done for $8.2m to $9.2m. So it's affordable, doable and timely to deliver comfortable, efficient and fast Train services to Huapai now. Campaigners have had the Trains to Huapai proposal blocked by Auckland Transport and more recently, by KiwiRail with a very 'can't do' attitude which they say 'is now bordering on ridiculous.' PTUA chair Niall Robertson says 'We believe that both AT and KiwiRail are reneging on their responsibilities to provide appropriate and needed transport services to the Northwestern community, especially as funding will be provided for five years from a private source with no need for ratepayer or taxpayer input.' CBT convener Jodi Johnston says, 'This is an innovative, novel solution to this problem at no cost to ratepayers or taxpayers which is being deliberately blocked by officials, despite support for the idea from both local and national politicians'. The PTUA and CBT urge Auckland Transport (AT) and KiwiRail to acknowledge the need for the service and for the politicians to deal with AT and KiwiRail and get things moving now! Guests invited to talk at the public meeting are: Greg Sayers, councillor for Rodney, Guy Wishart, local Rodney board member, Kerrin Leoni whau councillor and mayoral candidate, Niall Robertson, chair of the Public Transport Users Association, Jodi Johnston, convener of the Campaign for Better Transport. The MC will be Christine Rose, Local resident, past chair of the PTUA and past Auckland Regional Councillor. We have apologies from, The Honourable Chris Bishop, Minister of Transport, The Honourable Winston Peters, Minister of Rail, the Mayor of Auckland, Wayne Brown, the Honourable Chris Penk, Rodney-Mahurangi MP.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into the world of global news and events? Download our app today from your preferred app store and start exploring.
app-storeplay-store