‘Backups of epic proportions': Your comprehensive guide to Revive I-5 closures and traffic delays

‘Backups of epic proportions': Your comprehensive guide to Revive I-5 closures and traffic delays

Yahoo03-04-2025

This story was originally posted on MyNorthwest.com
Despite earlier claims from the Washington Department of Transportation (WSDOT), Revive I-5 is happening this summer, closing down significant stretches of the highway for four weeks, much to the chagrin of Seattle drivers and commuters.
The Revive I-5 campaign, Washington's effort to rehabilitate Interstate 5 (I-5), is set to improve the most vital sections of the major highway, section by section, between King and Snohomish counties. The prioritization of the sections is based on traffic volume and the present conditions of the roadway, with safety being the number one concern.
With heavy backups during rush hour traffic already too common, Seattleites are about to see backups of epic proportions once two of the four lanes close for a month on northbound I-5, beginning in late July.
The project had an original start date of March 2025, but in January, WSDOT announced that Revive I-5 was going to be postponed until next year due to an abrupt revelation that there weren't enough funds to start it.
While the massive highway overhaul is 'very' critical to the state's infrastructure, according to KIRO Newsradio traffic reporter Chris Sullivan, drivers felt a subtle sigh of relief, believing they had a little more time before significant lane closures and extensive backups. Unfortunately, that sinking feeling of looming traffic resurfaced this week when WSDOT announced they were going to start this project this summer after all.
How did WSDOT rebudget to continue Revive I-5?
'We had a budget set for the project, and when we established the budget, we thought the funding was sufficient,' WSDOT spokesperson Tom Pearce said. 'However, as we got into the project and worked with the contractor, they saw what the work was going to entail and they determined that we would need more money this year.'
'The Legislature will not set our budget until, of course, late in their session, but we needed to start the work before the session was finished if we were going to do the work in 2025,' Pearce added. 'In March 2025, it would have required starting before the necessary funds were fully committed from the Legislature.'
That explains why this project was initially delayed. So what changed?
'We reduced the scope of this project to focus on the Ship Canal Bridge,' Pearce explained. 'We changed the plans to align our construction spending with the available funding.'
Here's where Revive I-5 will start
This summer, with Revive I-5 back in action, WSDOT will begin working between Interstate 90 (I-90) and Ne45th Street across the Ship Canal Bridge—a vital connection between north and downtown Seattle, with 200,000 estimated daily commuters.
Recently, the Washington State Department of Transportation (WSDOT) finished the I-5 Duwamish River to S. Lucile Street section along Boeing Field into Tukwila. The next phase moves north, fixing concrete, potholes, and drainage systems along the Ship Canal Bridge.
What can drivers expect to see this summer?
'We will close northbound I-5 at I-90 from July 25-28,' Pearce told KIRO Newsradio. 'We're closed the entire weekend to allow our contractors to get out and set up a work zone that will keep the people working on I-5 safe, as we'll repave about 900 feet of the two left lanes of the Ship Canal Bridge.'
When the northbound freeway opens on July 28, the right two lanes will be open for travel, but the left two lanes will remain closed.
'We're going to have the express lanes open northbound 24/7 while we have the two left lanes closed off the main line,' Pearce stated. 'Once we finish our work on Aug. 22, we will have another full closure from Friday night, Aug. 22, to early Monday, Aug. 25, so that our contractor can go in, pick up the safety barrier that they've put up, restripe the freeway, and have all four lanes open on Monday morning.'
Lots of traffic congestion to go around
According to WSDOT, this will be a four-week preview of what people can expect for approximately nine months out of the year in 2026 and 2027. The traffic backups will be shared in both directions of I-5. Southbound drivers will also be without their morning express lanes, adding to an already tough commute into Seattle.
Over the course of this summer's one-month closure, Atkinson Construction will repair and resurface about 20% of the northbound Ship Canal Bridge, partially repair five expansion joints, and replace drainage.
Restarting this summer will keep the overall project on track and allow crews to gather critical data on the bridge's condition to better prepare for next year's phase.
What is WSDOT's plan for 2026?
Next year brings the World Cup to Seattle, adding further complications to the three-year highway revitalization.
'In 2026, we will close the two left lanes early in the year so that we can finish repaving and make any repairs we need,' Pearce said in anticipation of the World Cup. 'When we get to early June, when the World Cup is getting ready to fire up, we will pick up everything.'
King County officials claimed the World Cup would generate at least $929 million in revenue for the county, and create nearly 21,000 jobs. Organizers estimate that 750,000 people will visit Seattle during the three-week event.
'Once the World Cup is complete, our contractor will come back out in mid-July, and then they're going to close down the freeway again,' Pearce said. 'They will close the two right lanes of the northbound bridge so that they can work on those for several months. And then, come fall 2026, they will pick it up, and we will have everything open as we get into the winter.'
What's Revive I-5′s outlook in 2027?
In 2027, with the focus pivoting to southbound I-5, two lanes will be closed, and the other two lanes will remain open for several months. Once that work is done, WSDOT crews will flip their construction zone again, working on the previous two open lanes while opening up the recently completed lanes.
'We understand there's no good time to do this work. People are always going places. There are always events in the city,' Pearce said. 'We did the best we could to schedule this around things like the holidays, like Independence Day and Labor Day. Each of those (Ichiro) Hall of Fame weekends, we understand it is going to draw huge crowds to T-Mobile every night.'

Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Spokane County replaces aging aircraft with $3.4M helicopter upgrade
Spokane County replaces aging aircraft with $3.4M helicopter upgrade

Yahoo

timea day ago

  • Yahoo

Spokane County replaces aging aircraft with $3.4M helicopter upgrade

This story was originally published on The Spokane County Sheriff's Office (SCSO) unveiled its new $3.4 million Bell 505 helicopter at Felts Field Wednesday afternoon. The new helicopter will replace two 55-year-old aircraft that have been retired from the force after decades of service, according to the sheriff's office. Spokane Valley Police Chief Dave Ellis noted his admiration for the upgrade. 'Its advanced technology will improve our ability to combat rising auto thefts and conduct safer operations, including searches for missing children, Alzheimer's patie nts, and outdoor recreationists,' Ellis said, according to SCSD. The helicopter can reach a top speed of 125 knots per hour (kts) and a hover ceiling of 14,450 feet, according to BellFlight. SCSO fully equipped the helicopter with upgraded technology such as thermal imaging cameras and a live-stream video feed. The sheriff's office received a $500,000 grant from the U.S. Department of Justice, a $200,000 state grant for the thermal imaging cameras, $1.6 million from Spokane County, and raised money from the sale of an older SCSO helicopter, according to The Spokesman-Review. 'It's unbelievable how clear of an image they can get if they wanted to do surveillance over somebody that was a really bad guy. They could fly over at 7,000 feet and read the license plate,' John Preston, retired LAPD officer, said, according to The Spokesman-Review.

Toyota RAV4 Evolution: Every Generation From 1996 To The All-New 2026 Model
Toyota RAV4 Evolution: Every Generation From 1996 To The All-New 2026 Model

Miami Herald

time2 days ago

  • Miami Herald

Toyota RAV4 Evolution: Every Generation From 1996 To The All-New 2026 Model

The Toyota RAV4 has been a key proponent of the crossover craze since its arrival three decades ago. It offered all the benefits of a sedan, but with the extra ride height and superior dirt-road performance usually associated with true body-on-frame SUVs. With the sixth-generation RAV4 now revealed, we expect the RAV4 to retain its best-seller status for years to come. Here's a look at all generations of the RAV4, from the first one to the modern hybrid-only model. The first-gen Toyota RAV4 set the standard for future rivals like the Honda CR-V, Nissan Rogue, and Mazda CX-5. This RAV4's model years ran from 1996 to 2000 in the USA. The styling was cute and tough at the same time, and this early RAV4 was also available in sporty three-door form, or with a soft-top. Toyota kept things simple under the hood, relying on a 2.0-liter naturally-aspirated four-cylinder engine sending power to the front or all four wheels, with a choice of five-speed manual or four-speed automatic transmissions. A facelift for the 1998 model year introduced a few styling revisions, and Toyota even experimented with a fully electric version for the 2000 model year, but this only had an 88-mile range. Well over 50,000 first-gen RAV4s were sold in the United States in every year of production, confirming that this was the sort of car buyers were drawn to. So, when did the the RAV4 change its available body styles? It started here with a simplified lineup. Produced for the 2001 to 2005 model years, the XA20 RAV4 was once again available in three- and five-door form, but only the five-door body style made it to America. The styling was modernized, but retained a sporty look with well-executed rugged touches. Initially, Toyota stuck with the 2.0-liter four-pot, but a larger 2.4-liter engine with 161 horsepower debuted for the 2004 model year, somewhat addressing criticisms of the underpowered standard engine. That same model year, the RAV4 received a host of safety upgrades, including standard stability and traction control. A RAV4 EV was also available over this period, with a maximum range of 95 miles, but availability was extremely limited. A significant bump up in power coincided with the launch of the third-gen RAV4; this RAV4 generation's model years ran from 2006 to 2012. The big increase in power came despite fact that the design was softened to an extent that made this model appear a bit anonymous. The headlining engine was a 3.5-liter V6 producing 269 hp, far more than any previous RAV4. A more efficient 2.4L four-cylinder was standard. A manual gearbox was no longer available, but the V6 received a new five-speed automatic. The 2.4L model stuck with a four-speed auto. For the first time, the RAV4 EV cracked 100 miles on a full charge. This RAV4 was the first to lead all Toyota SUVs in terms of sales in the USA; over 170,000 units were sold in America for the first time in 2007, as the RAV4 continued to surge in popularity. On sale for the 2013 to 2018 model years, the XA40 featured a few noticeable styling changes not seen in previous generations of the RAV4: It had a rear liftgate instead of a rear door that opened to the side, while the spare wheel was no longer mounted at the back. A major change was the introduction of a hybrid model, which could return 34 mpg in city driving - a vast improvement over the standard, non-hybrid model. The unpopular V6 was dropped, but a new six-speed automatic was implemented for the standard four-cylinder engine. Inside, a more modern design was introduced, but Toyota got rid of the small, optional third seating row. The overall impact of these changes was tremendous, with the fourth-gen RAV4 topping 350,000 annual sales for the first time in 2016. As of this writing, the fifth-gen RAV4 is still on sale, but will be replaced after the 2025 model year. Introduced in 2018, this generation of the RAV4 was given a far more appealing look, with sharp, aggressive angles and beefy body cladding, all aimed at evoking the adventurous spirit of the original model. The unibody chassis improved in rigidity by 57 percent, creating a RAV4 that steered and drove with more sophistication than previous models. A new torque-vectoring four-wheel-drive system also debuted, with the ability to individually direct torque to each rear wheel, based on the driving scenario. Engine choices include a standard 2.5-liter four-cylinder, along with a hybrid version of the same engine. Non-hybrid models have an eight-speed automatic. The big news, however, was the arrival of the 2021 RAV4 Prime, a plug-in hybrid version with 302 hp and over 40 miles of all-electric range. It became the quickest RAV4 ever. In 2024, the RAV4 dethroned the Ford F-150 for the first time in decades, becoming the country's top-selling vehicle. That says all you need to know about the success of this RAV4 generation. Finally, we arrive at the all-new RAV4, revealed in the first half of 2025. Inside and out, it has a completely fresh look, with cleaner lines than the outgoing model. However, it remains similar in size. For this generation, Toyota has switched over to hybrid power exclusively, a smart move given the popularity of hybrid powertrains presently. The standard hybrid develops 226 hp (FWD) or 236 hp (AWD), while the plug-in hybrid produces a stout 320 hp. These are all improvements over the previous RAV4. Buyers looking for something with a sporting edge can opt for the new GR Sport trim, which is more than just a visual upgrade. It also features special tuning for improved handling and is exclusively offered with the 320-hp powertrain. This all-hybrid RAV4 is a far cry from the first-gen model, but it remains an irresistible mix of practicality, compact size, and some rugged capability. What is the most reliable year of the RAV4? Based on our research, the 2018 Toyota RAV4 has an impeccable reliability record, and is the most highly recommended RAV4 model year. What year did the RAV4's body change? The second-generation of the RAV4 to be sold in America did not have a three-door option. Other than that, the fifth-gen RAV4 marked a significant stylistic departure from conservative previous models. Will the RAV4 be redesigned in 2025? The sixth-gen, 2026 Toyota RAV4 has an all-new design and has already been revealed in 2025. The 2025 RAV4 forms part of the outgoing fifth generation. Is the Toyota RAV4 changing in 2026? The 2026 RAV4 has already been revealed and will go on sale later in 2025. What year is the 5th-gen RAV4? The fifth-gen RAV4 went on sale in late 2018 and is expected to go out of production later in 2025 to make way for the sixth-gen model. Copyright 2025 The Arena Group, Inc. All Rights Reserved.

Restoring access to this part of Mount Rainier could cost up to $785 million
Restoring access to this part of Mount Rainier could cost up to $785 million

Yahoo

time2 days ago

  • Yahoo

Restoring access to this part of Mount Rainier could cost up to $785 million

It has been over a month since the Washington State Department of Transportation permanently closed the state Route 165 Carbon River Fairfax Bridge — and now it wants to hear the public's thoughts on how to move forward. The 103-year-old, single-lane bridge was the only way for the public to access key areas of Mount Rainier National Park, such as Tolmie Peak, Mowich Lake and Spray Park, from state Route 165. WSDOT closed the bridge on April 22 due to safety risks. In an online open house for the public, WSDOT has identified seven potential projects. Each project has different cost estimates and time frames. The options are to: Maintain the permanent bridge closure. Replace the bridge at its current location. Replace the bridge north of its current location. Replace the bridge south of its current location. Realign state Route 165 and place a new bridge near Carbonado. Realign state Route 165 to connect with state Route 162 near Crocker. Realign state Route 165 east of Wilkeson and Carbonado. WSDOT does not currently have funding for any of the options; all of the agency's estimated time frames would start from whenever officials are able to identify funding. The first option would simply remove the existing bridge and not build a new one, according to the open house. 'The existing bridge would remain closed to all users with a dead end in Carbonado,' WSDOT wrote. 'With this no-build option, the bridge would be removed. This work would take about three years to complete once funding is received.' It would cost between $35 million and $50 million to remove the current bridge, WSDOT estimates. The second option would remove the existing bridge and build a new one in its place. WSDOT estimates that it would take six years to remove the current bridge and do design, permitting and construction for a new one. This would cost between $80 million and $130 million. WSDOT's third option would build a new 650-foot bridge north of its current location and realign half a mile of state Route 165. 'This alternative would take about six years from receiving funding and would include removal of the bridge, design, right-of-way, permitting, and construction,' WSDOT wrote. The cost would be between $60 million and $100 million. WSDOT's fourth option would build a new 650-foot bridge south of its current location and 'would require a minor realignment' of state Route 165. This project would take six years and cost between $60 million and $100 million. The fifth option would reroute state Route 165 to the south of Carbonado, starting by Wilkeson-Carbonado Road. 'A new bridge would be built spanning the Carbon River south of Carbonado,' WSDOT wrote. 'West of the Carbon River, the new alignment would follow Lilly Creek and reconnect to the existing SR 165 alignment near Lilly Creek Road East.' This option would take about five years and cost between $465 million and $785 million. WSDOT's sixth option would realign state Route 165 and connect it to state Route 162 near Crocker. This option would not require building a new bridge over the Carbon River. 'The new alignment would follow Lilly Creek and connect to the existing SR 165 alignment near Lilly Creek Road East,' WSDOT wrote. This would take about seven years and cost between $440 million and $735 million. The seventh and final alternative would realign state Route 165 east of Wilkeson and Carbonado. 'It would reconnect to the existing SR 165 south of the current Fairfax Bridge,' WSDOT wrote. 'It would upgrade 12 miles of road to highway standards and include a new or upgraded Kolisch Road bridge over the Carbon River.' Two new bridges would be required on Kolisch Road and Wilkeson Creek, WSDOT said. This would take about six years and cost between $375 million and $610 million. WSDOT is running its online open house until June 17. Residents can submit their feedback online until then at There is also an in-person open house on June 11 at Wilkeson Elementary School from 5:30 p.m. to 7:30 p.m. 'These are drop-in style events; you are welcome to come and go at your convenience,' WSDOT wrote. 'The content of the in-person open houses will be the same as this online format, but you will also be able to speak with the project team and ask questions.' The open house is part of WSDOT's $1.5 million planning study about the future of the bridge.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into the world of global news and events? Download our app today from your preferred app store and start exploring.
app-storeplay-store