Uisce Éireann slammed for 'shifting deadlines' given to householders left without supply
HUNDREDS OF HOUSEHOLDS at a housing estate in Dublin were left without water over Easter after experiencing what one resident said was their seventh outage this year.
Homeowners at Dargle Wood in the Dublin suburb of Knocklyon have experienced dozens of outages since May 2022, according to the resident, as locals believe a new apartment development has put a strain on supply.
A water mains fault happened once again on the morning of Easter Sunday, and homes were left without any water until Tuesday evening despite initial alerts telling households that the outage would last no more than a few hours.
The resident who spoke to
The Journal
said that she was repeatedly assured by Uisce Éireann, the state's water provider, that crews were working to address the issue despite her claims that no one arrived to site until Tuesday.
A spokesperson for Uisce Éireann said that the estate in Knocklyon was impacted a a after a water mains pipe burst on Sunday morning and confirmed that a leak detection crew and repair team was not sent to the location until Tuesday.
The estimated restoration time continued to be updated to a later and later date during the outage.
Fianna Fáil TD John Lahart labelled the 'shifting deadlines' from the service as 'appalling'.
Advertisement
'In both service delivery and public communication, Uisce Éireann has fallen far short,' Lahart said.
'The lack of transparency and responsiveness shown to affected residents and their representatives is deeply troubling.'
'I want accountability'
Most residents had their water restored on Tuesday night but the homeowner we spoke to said because Uisce Éireann informed those at the estate that the outages would only last for a few hours, most households did not prepare for a prolonged period without water.
Uisce Éireann did not provide a reason why no repair teams were sent until Tuesday or why customers were told that the issue was being actively resolved.
A spokesperson said that some households were impacted by 'airlocks' – when air gets trapped in a high point of the system, preventing water flow- and that the service provider deployed plummers to those homes on Thursday.
The householder we spoke to moved into her home in south-west Dublin in 2021 and she estimates her there has been dozens of water outages since 2022.
Though estimated restoration times are usually very accurate and the longest period that families went without water was 24 hours, she said that continuous outages can be disruptive.
A theory among some residents is that the water supply was impacted after the development of a new apartment block near a number of housing estates in the area.
A spokesperson confirmed that there has been 'a number' of outages in the Knocklyon area this year due to old PVC pipes bursting, particularly in cold weather.
Readers like you are keeping these stories free for everyone...
A mix of advertising and supporting contributions helps keep paywalls away from valuable information like this article.
Over 5,000 readers like you have already stepped up and support us with a monthly payment or a once-off donation.
Learn More
Support The Journal

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Irish Independent
18 minutes ago
- Irish Independent
Traffic disruptions expected in busy Carlow town as ongoing works continue
The upgrade works, which are being carried out under Uisce Éireann's national Leakage Reduction Programme, involves the replacement of more than 2.1km of aging water mains which have been prone to bursts and high levels of leakage with new modern pipes, with 850 metres of mains replaced so far. Uisce Éireann say these upgrades will significantly reduce water loss, improve pressure, and enhance the overall resilience of the water network serving homes and businesses in the area. To date Uisce Éireann has completed all main laying works on N81 - Bridge Street, Market Square and Church St. Public side connection works on these streets is still ongoing and will continue until mid-summer. Upgrades on Upper Mill Street are now complete, with the old mains pipe scheduled for decommissioning shortly. Work on Old Chapel Lane is nearing completion, with crews set to move to Bishop Street, which will be closed until Friday, June 20. 'We are committed to delivering a more secure and reliable water supply to communities across Ireland,' said Dave Murphy, Programme Manager with Uisce Éireann. 'These ongoing works in Tullow Town are part of that effort, ensuring fewer disruptions, improved water quality, and a network that's fit for the future. "We're delighted with the progress made on this project and would like to thank the people of Tullow for their continued patience and support as these essential works continue. The project remains on track to be completed by September 2025'. The works are being carried on behalf of Uisce Éireann by Shareridge.


Irish Times
a day ago
- Irish Times
Ireland is like the paradox of Schrödinger's cat: a wet country that has too little water
Debates about whether we need 50,000 new houses a year, as the Government says, or 93,000, as some analysts say, are arguably pointless: neither total is possible as there simply isn't the water there to supply them, or to process their waste. Just 30,000 to 35,000 new houses can be supplied each year for the foreseeable future according to Uisce Éireann . Quite the gap. In 2013, Irish Water – as it was called – inherited a severely neglected water infrastructure system. The average age of a water pipe is about 75 years – double the European average – and leaky as a Government backbencher. At about 37 per cent, our water leakage levels are among the highest in western Europe due to these ageing underground pipes and a legacy of fragmented ownership of the network with historically variable levels of maintenance. Tralee alone loses 6.5 million litres a day in leaks, enough water for a town twice its size. Ireland also uses a lot of water compared to the rest of Europe, 1.7 billion litres daily, with domestic usage accounting for two-thirds of this and non-domestic consumers the balance. Uisce Éireann is expecting non-domestic demand in the Greater Dublin Area (GDA) to increase by 67 per cent by 2040. READ MORE As in housing, geography matters. While the west and south of the country has more rainfall and better water supplies, it is in the east of the country that demand is intensifying, exactly where rainfall is lower and river systems are smaller. About 80 per cent of our drinking water comes from rivers and lakes with the remainder from groundwater, mostly in rural areas. The GDA, with 40 per cent of the country's population, relies heavily on Vartry reservoir and the Liffey, the latter of which supplies 85 per cent of Dublin city's water. Such a narrow base of water supply means systemic vulnerability in case of drought or peak demand. At the same time, population growth means that domestic water demand across the country will increase by 26 per cent to 2044. [ Fixing 'known' water system issues will take until 2050 and cost up to €60bn, says Uisce Éireann ] In the east, the demand for drinking water will increase by 45 per cent to 800 million litres a day in the GDA by 2040, vastly exceeding current capacity. Two-thirds of towns and villages do not have the 'infrastructural headroom' to support new development without upgrades, which is essential for rural revitalisation. We also need to deal with wastewater. More than half of our wastewater treatment plants are not always compliant with their licences, and Ireland has been in continuous breach of various parts of the EU Urban Waste Water Treatment Directive for more than 30 years. In rural areas, more than half the septic tanks inspected last year failed. Just 1,390 of nearly 500,000 were tested, meaning significant risks for surface and groundwater quality. Various studies have noted evidence of faecal contamination in rural wells. There are solutions, the quickest of which is to change usage behaviour and the quickest way to do that is to charge for water. That didn't go down well the last time it was tried. Tánaiste Simon Harris recently promised the Government will not introduce water charges, although he also promised we'd complete 40,000 houses last year. The actual number of new homes completed was 30,330. There is a plan to charge for 'excess' water and wastewater usage (above 213,000 litres per average household annually), but there's no timeline or legislation yet for its introduction. Behavioural interventions like awareness campaigns are also useful: more nudge, less sludge. Better planning decisions about where new housing is allowed to integrate water supply and output also have a role. Rainwater and downpipe harvesting should be part of every new house. Fixing leaks and upgrading existing infrastructure are, however, key. Uisce Éireann spends €250 million a year reducing leaks from 46 per cent in 2018 and is aiming for 25 per cent by 2030. The proposed 170km Shannon pipeline to serve the east and midlands will take 350 million litres a day from the Parteen Basin near Birdhill, Co Tipperary. Without this pipeline, there will be no new housing or commercial water connections in the GDA, which will have significant implications for the national economy, the delivery of housing, social equality and sustainable patterns of development. [ Renters forking out €2,000 per month are paying the price for water charges debacle ] This will cost money, which goes to the heart of the issue: successive governments, all of which contained parties of the current Government, have repeatedly underfunded water infrastructure, exactly as they have housing, in both instances expecting the private sector to do the heavy lifting for them. Whereas expensive and volatile private sector reliance has grown exponentially in housing, no private sector involvement in water infrastructure has happened. Maybe no harm. Across the Irish Sea, privatisation of water in England has led to increased shareholder profits and directors' remuneration, and worse leakage and poorer quality water. In housing, ministers castigate local authorities for not doing enough at the same time as cutting funding. In water, there are announcements of increased funding, but as in housing, this is not always new funding, but recycled old funding. Indeed, Uisce Éireann's chairman recently accused the Government of allowing misleading messages of additional funding to permeate ' within Government circles, industry and the general public ', even though there was no additional funding (while politicians simultaneously blame Uisce Éireann for shortages). Pretend money – particularly annually allocated pretend money – won't solve our water supply issue. A wealthy but still penny-wise pound-foolish Government hasn't made the link between functioning infrastructure and housing output, and indeed climate. As a result, Ireland is now the geographical manifestation of Schrödinger's cat: a wet country that is at the same time lacking in water for new housing; a country with numerous energy-hungry data centres, but also a looming potential shortage of electricity for new houses; and more than 15,500 homeless in a country with over 160,000 vacant homes. You'd have to wonder whether anyone is in charge. Dr Lorcan Sirr is senior lecturer in housing at the Technological University Dublin

The Journal
a day ago
- The Journal
Here are the vacant and derelict buildings around Ireland that councils asked ABP to CPO in May
BOARDED-UP HOUSES and crumbling buildings are a common feature of towns and cities across Ireland. Derelict buildings contribute significantly to Ireland's housing crisis, and bringing them back into use is one of the Government's aims for addressing social housing shortfalls and to get more homes on the market. Under laws introduced in 1990, every local council keeps a Derelict Sites Register to encourage owners to bring vacant houses and land into use through the imposition of an annual levy of 7% of the property's market value, which applies until the site is no longer derelict. When someone objects to a local authority's attempt to obtain a property via the Compulsory Purchase Order process, the council can make an application to An Bord Pleanála to do so. The Housing Act also allows local authorities to acquire vacant homes via CPO, which they also must apply to do via An Bord Pleanála. The process is similar to making a planning application, and the board weighs up submissions from the council and the owner of the land before deciding whether a site can be subject to a CPO. The number of properties that councils try to CPO every month is relatively small. The Journal has been keeping track of the vacant and derelict properties that councils have sought to acquire, and previously wrote about how four local authorities applied to the board to CPO six different properties in April. Last month, three local authorities applied to the board to CPO three different properties around Ireland. 21 Keating Street, Dungarvan (Waterford) The front of Holly Tree House in 2009 Google Street View Google Street View Waterford City and County Council applied to have a derelict site, known as Holly Tree House on Keating Street in Dungarvan, vested on 23 May. The slender terraced house was last photographed on Google Street View in 2009, when it had a large tree in its front garden (possibly indicating where its name comes from). Advertisement There is little other information available about it online: no planning files are associated with the address (aside from attempts to CPO it) and it does not appear to have ever been listed for sale online. The case is due to be decided by An Bord Pleanála by 1 September. 83 Eastham Court, Bettystown (Meath) Google Street View Google Street View Meath County Council applied to acquire a vacant property at Eastham Court in Bettystown under the Housing Act on 8 May. The property, situated between two other houses, appears to be in good condition but does not have any occupiers or tenants known to the council . It is part of an estate that was built in the early 2000s. It has never been listed as sold on the Property Price Register and there are no planning applications associated with the property. The council issued a newspaper notice at the end of April, saying that it wanted to CPO the house and use it for social housing. An Bord Pleanála is due to decide the case by the end of October. Millbrook, Rathangan (Kildare) Google Street View Google Street View Kildare County Council applied to acquire a vacant property at Millbrook in Rathangan under the Housing Act on 26 May. The small cottage was deemed by the council in April to be 'unfit for human habitation' and incapable of being rendered fit for use at a 'reasonable expense'. The council also said at the time that any owners, occupiers or lessors of the property are not known. A planning application submitted in 2008, which was granted permission the following year, proposed demolishing the cottage and replacing it with a three-bedroom dormer and a four-bedroom bungalow on the site. The council's intended use for the property is not stated; however, under a renewal plan for Rathangan published last October , the local authority said it would seek to bring vacant buildings into use as housing and tourist accommodation, and incentivise the re-use of vacant buildings. Readers like you are keeping these stories free for everyone... A mix of advertising and supporting contributions helps keep paywalls away from valuable information like this article. Over 5,000 readers like you have already stepped up and support us with a monthly payment or a once-off donation. Learn More Support The Journal