Odisha: Breakthrough of final tunnel on Khurda Road-Balangir rail line achieved
Tunnel No 2 (T2), with a length of 1,775 metres with a 2-degree curve, has been constructed in a new technological method called New Austrian Tunnelling Method (NATM), the statement said.
The breakthrough, or 'daylighting', was successfully achieved on Friday, marking the completion of excavation work across all seven planned tunnels in this strategic railway corridor, it said.
Bhubaneswar, Jun 1 (PTI) The Khurda Road-Balangir new rail line project achieved a major milestone with the successful breakthrough of the final tunnel located between Buguda and Daspalla in Odisha's Nayagarh district, the East Coast Railway said in a statement.
The ECoR said that T2 is the second-longest tunnel in Nayagarh district. It was constructed using advanced technology and tunnelling methods to overcome the challenging Eastern Ghats, setting a new benchmark in infrastructure execution for Indian Railways.
With the completion of T2, the breakthrough of all seven tunnels in the 75-km stretch between Daspalla and Purunakatak has now been achieved, it said.
The total length of all seven tunnels is 12.76 km, of which three tunnels are located in Nayagarh district and the remaining four in Boudh district.
Construction of these tunnels involved tackling multiple complex challenges including highly variable soil and rock conditions and passing through wild zones, the statement added.
The new railway line project spans 301 km and significant portions of the project — Khurda Road to Daspalla (106 km) and Balangir to Purunakatak (120 km) have been completed while the remaining stretch of 75 km from Purunakatak to Adhenigarh is under progress, it said.
Completion of the final segment will establish seamless railway connectivity between eastern and western Odisha, bringing extensive benefits to both passenger and freight traffic.
Once fully operational, the railway line will reduce travel time between Bhubaneswar and Balangir, improve access to education, healthcare, and markets, stimulate trade and regional development, and support freight movement across Odisha and beyond, the statement added. PTI BBM BBM ACD
This report is auto-generated from PTI news service. ThePrint holds no responsibility for its content.

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Hindustan Times
12 minutes ago
- Hindustan Times
‘Defence may be the wrong word': Shashi Tharoor points at ‘China factor' in Pakistan conflict
Congress leader Shashi Tharoor said on Thursday that 81 percent of Pakistan's defence equipment comes from China, making the country an 'impossible factor' to ignore in the conflict with Islamabad. Tharoor, who is leading a parliamentary delegation to the US to expose Islamabad's nexus with terror after India's Operation Sindoor, said that New Delhi-Beijing relations were making good progress till last month's conflict with Pakistan. 'I'm not going to mince my words, but we are aware that China has immense stakes in Pakistan," PTI quoted Tharoor as telling the representatives of think tanks at the Indian Embassy in Washington DC. Tharoor pointed out that the largest single project under the Belt and Road Initiative (BRI) is the China-Pakistan Economic Corridor (CPEC), and that 81 percent of Pakistani defence equipment is from China. 'Defence may be the wrong word here. Offence in many ways……China is an absolutely impossible factor to ignore in what has been our confrontation with Pakistan,' Tharoor said. Shashi Tharoor told the gathering that India had seen good progress in its relationship with China after tensions since the 2020 Galwan Valley clashes. The Thiruvananthapuram MP added that during Operation Sindoor and the conflict with Pakistan, New Delhi saw a very different China in terms of its support for Islamabad, even on the UN Security Council. 'We have no illusions about what the challenges are in our neighbourhood, but I want to remind you all that India has consistently chosen a path of keeping open channels of communication, even with our adversaries. We have tried as much as possible to focus on development, on growth, on trade. Our trade with China is still at record levels. It's not that we are adopting a posture of hostility, but we would be naive not to be aware of these other currents around,' he said. The UN Security Council, on April 25, issued a press statement on the 'terrorist attack in Jammu and Kashmir' after the April 22 Pahalgam attack that killed 26 people, mostly tourists. The statement had condemned the attack in "the strongest terms' but did not mention The Resistance Front as Pakistan, which is a non-permanent member of the council, got it removed with China's help. 'The members of the Security Council underlined the need to hold perpetrators, organisers, financiers and sponsors of this reprehensible act of terrorism accountable and bring them to justice,' the press statement had said. Shashi Tharoor was asked about the Chinese military equipment that Pakistan used in the conflict during an earlier interaction at the Council on Foreign Relations. The delegation head said that when India saw what the Pakistanis were attempting to do using Chinese technology, for instance, the 'kill chain' that the Chinese specialise in, where the radar, GPS, planes and missiles are all linked together and they react instantly, 'we simply did things in a different way. Otherwise, we wouldn't have been able to hit' 11 Pakistani airfields, and "we wouldn't have been able to breach the Chinese-supplied air defences. 'So it's clear that assessments were taking place while the fighting was happening, and we were recalibrating our strategies in order to end as effectively as we were able to end,' Tharoor said.


Hindustan Times
2 hours ago
- Hindustan Times
Steep slopes, location access: How Chenab railway project team tackled construction challenges
Prime Minister Narendra Modi inaugurated the world's highest rail bridge, Chenab railway bridge, on Friday. Behind the bridge that offers connectivity of Kashmir to the rest of India, was a construction team that faced several challenges. One of the main obstacles that they dealt with was how to reach the location surrounded by the steep slopes of Himalayas. According to Afcons Infrastructure Limited, the company behind the making of the bridge, one of the key challenge was to access the bridge location and then to transport the equipments and construction material there. Initially they made use of mules and horses but over time temporary roads were made to access the site, said a spokesperson of the company. An 11- km road was constructed on the North side of the river bank and similarly a 12 km road was created on the South side. Executive Vice Chairman of Afcons, Krishnamurthy Subramanian highlighted the Chenab bridge as a marvel of engineering and told PTI that it is a 'symbol of India's resolve to conquer most formidable challenges with ingenuity and courage.' To make this project a reality, the company used world's tallest crossbar cable cranes and specialised heavy machinery as tools. Further, consolidation grouting was used to make the arch foundation of the slopes of Himalayas sturdy. According to the company, cantilever techniques was used for the erection of the arch from both sides. One of the key moment of triumph came when ' a single majestic arch approaching steadily from both banks met at the crown," in April 2021, said the company. To construct a viaduct, a structure designed to make roads and railways over rivers, was also a unique challenge. The company spokes person said, "There were multiple transition areas. Keeping this in mind, the launching sequence was meticulously planned in four sections," the spokesperson. Also read: Chenab Rail Bridge to bring Delhi and Kashmir closer | Why is it important Meanwhile the managing director of Afcons emphasised the importance of this project for the company saying, "For Afcons, it represents our unwavering commitment to nation-building and our ability to reimagine infrastructure in the toughest terrains.' He further said that this bridge will inspire generations of engineers about the power of Indian engineering. Another key milestone was that for the first time in the Indian Railways' history, a laboratory accredited by the National Accreditation Board for Testing and Calibration (NABL) was set up to ensure the quality of the project. (With PTI Inputs)


New Indian Express
2 hours ago
- New Indian Express
Chenab bridge: How project team navigated through steep slopes on horses and mules
KATRA: To realise the vision of travelling from "Kashmir to Kanyakumari" by rail, the project team behind the construction of the Chenab bridge faced several challenges. Among them was how to reach the location surrounded by the steep slopes of the Himalayas. The team had only one option -- horses and mules. According to Afcons Infrastructure Limited, the top infrastructure company that constructed the bridge, one of the main and earliest challenges was access to the bridge location, to transport equipment and construction materials. "Initially, mules and horses were used by the project team to reach the location. Slowly over a period, temporary roads were created and access was made available to the site," a spokesperson from the company said. Prime Minister Narendra Modi on Friday inaugurated the iconic Chenab Bridge, Anji Rail Bridge and Udhampur-Srinagar-Baramulla Rail Link project and flagged off Vande Bharat trains, connecting Katra to Srinagar. The spokesperson added that eventually, on the North side of the river bank, an 11-km road was constructed and a 12-km road on the South side. Krishnamurthy Subramanian, Executive Vice Chairman, Afcons, said the Chenab Railway Bridge is more than just a marvel of engineering. "It is a symbol of India's resolve to conquer the most formidable challenges with ingenuity and courage," he told PTI. The company used the world's tallest crossbar cable cranes and specialised heavy machinery as tools for this ambitious project. "The ancient and steep slopes of the Himalayas were tamed using massive consolidation grouting, making them sturdy for the colossal arch foundations," the company said, highlighting challenges it faced. "With the foundations set, the erection of the arch from both sides was planned by the cantilever construction technique. The first big moment of triumph came on April 5, 2021, when a single majestic arch approaching steadily from both banks met at the crown," it added. "The viaduct construction was another unique challenge. There were multiple transition areas. Keeping this in mind, the launching sequence was meticulously planned in four sections," the spokesperson said. Giridhar Rajagopalan, Deputy Managing Director, Afcons, told PTI that for the first time in Indian Railways, incremental launching was done on a transition curve and a longitudinal gradient, both occurring at the same location, for the deck launching of the viaduct portion of the Chenab Bridge. S Paramasivan, Managing Director, Afcons, "For Afcons, it represents our unwavering commitment to nation-building and our ability to reimagine infrastructure in the toughest terrains. This bridge will inspire generations of engineers and stands as a tribute to the power of Indian engineering and teamwork." For the first time in the Indian Railways' history, a laboratory accredited by the National Accreditation Board for Testing and Calibration (NABL) was set up to ensure that quality was being monitored at every stage of the project. Situated at a height of 359 metres above the river, the Chenab bridge is 35 metres higher than the iconic Eiffel Tower in Paris and the world's highest railway bridge over the Chenab river. After inaugurating the Chenab bridge, PM Modi walked on it holding the Tricolour high. He travelled in a rail engine coach to reach the spot.