Whitman County imposes wind energy moratorium as developer plans a 45-turbine project near Kamiak Butte

Whitman County imposes wind energy moratorium as developer plans a 45-turbine project near Kamiak Butte

Yahoo06-02-2025

Feb. 5—PULLMAN — The developer behind a wind farm project near Colfax says it has enough leases from landowners to move forward with 45 turbines, but plans to work with Whitman County as it writes new wind energy rules at the urging of upset neighbors.
Harvest Hills Wind project has faced significant outcry for its proximity to Kamiak Butte, a county park and National Natural Landmark. Opponents say it will ruin the landscape.
The county commission was about to vote on a cost reimbursement agreement with Harvest Hills early last month when instead, amid public pushback, the commission implemented a six-month moratorium to update the county ordinance.
Harvest Hills' 45 turbines would each be approximately 600 to 650 feet tall, lead developer Shane Roche said.
The configuration of each turbine has not been determined, but the project covers an area of private Palouse farmland between the towns of Colfax and Palouse, south of Palouse River and north and west of Kamiak Butte. While the project has enough leases to put up the turbines, it is not too late for interested landowners to join, Roche said.
Steelhead Americas, the North American development arm of Vestas, the world's largest wind turbine manufacturer, is developing the project. The turbine components are manufactured at Steelhead's plant in Denver. Steelhead plans to sell the project but will continue to service it.
Because the project is on private land and developed by private investors, it is not affected by President Donald Trump's executive order halting offshore wind and projects on federal land. That order stopped the Lava Ridge Wind Project near Twin Falls, Idaho, which some groups opposed for being near a historic site where Japanese Americans were incarcerated during World War II.
Roche noted that Trump also declared a national energy emergency in another order on his first day in office.
"We believe we are part of that solution," Roche said.
Wind is a quick and affordable way to meet growing demand, he said.
Harvest Hills is farther along than other projects in Eastern Washington and will be able to plug into the grid sooner, Roche said. Once construction begins, it is expected to finish in about a year.
Other companies are exploring wind projects in southern Spokane County, Lincoln County and Garfield County.
For comparison, Palouse Wind is an existing 105-megawatt facility that opened in 2012 in northern Whitman County with 58 turbines that are 426 feet tall. Vestas did not develop this project, but it used Vestas turbines. Palouse Wind sells its power to Avista Utilities.
Roche said Harvest Hills' turbines would be about 30% larger and require three times more spacing. The larger, more powerful turbines would generate 200 megawatts.
Roche said the moratorium gives Steelhead more time to work on the design phase. The company is focused on working with the county to develop the project while respecting property rights and benefiting the entire community, he said.
Despite pressure from residents to stop the project entirely, the county has to walk a fine line while writing a stricter ordinance.
Wind companies can choose to forgo the county permitting process and obtain a permit through the state's Energy Facility Site Evaluation Council or the Department of Ecology.
"I think it is better to have a county code and run under it rather than the state," County Commissioner Art Swannack said at a public hearing Monday in Colfax. "I still think the state will run over the top of us if the code does not follow what the courts say."
About three dozen people spoke at the hearing meant for the county to gather input on the ordinance.
Most opposed the development, and many asked for greater setback requirements not only from residences, but also from property lines.
Several homeowners complained that the county's zoning rules for building homes are extremely strict, yet the same rules would not apply to wind turbines, which are visually more intrusive.
Others asked the county to make a special industrial zone for wind projects, rather than allow them under general agricultural zoning.
The commissioners said they want to focus on updating decommissioning provisions.
"The planning commission is going to have to work on this, and I expect it won't be quick," Swannack said.
Harvest Hills hosted a moderated information session at Washington State University in Pullman on Tuesday where a panel of consultants discussed the project's economic, environmental and visual impacts.
Terry Wirkkala, senior project manager at ECOnorthwest, who studied the expected economic impacts of the project, said that it was expected to spend $158 million locally. The construction phase would involve 150 jobs, while the operational phase would employ five workers.
The project would generate an estimated $1.3 million a year in property tax for the county, Wirkkala said.
James Hanlon's reporting for The Spokesman-Review is funded in part by Report for America and by members of the Spokane community. This story can be republished by other organizations for free under a Creative Commons license. For more information on this, please contact our newspaper's managing editor.

Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Shoppers are wary of digital shelf labels, but a study found they don't lead to price surges
Shoppers are wary of digital shelf labels, but a study found they don't lead to price surges

Boston Globe

time2 hours ago

  • Boston Globe

Shoppers are wary of digital shelf labels, but a study found they don't lead to price surges

Social media is filled with warnings that grocers will use the technology to charge more for ice cream if it's hot outside, hike the price of umbrellas if it's raining or to gather information about customers. Advertisement Democratic US Senators Elizabeth Warren of Massachusetts and Bob Casey of Pennsylvania fired off a letter to Kroger last fall demanding to know whether it would use its electronic labels as part of a dynamic pricing strategy. Lawmakers in Rhode Island and Maine have introduced bills to limit the use of digital labels. In Arizona, Democratic state Representative Cesar Aguilar recently introduced a bill that would ban them altogether. A study published in late May found 'virtually no surge pricing' before or after electronic shelf labels were adopted. The study was authored by Ioannis Stamatopoulos of the University of Texas, Austin, Robert Evan Sanders of the University of California, San Diego and Robert Bray of Northwestern University The researchers looked at prices between 2019 and 2024 at an unnamed grocery chain that began using digital labels in October 2022. They found that temporary price increases affected 0.005 percent of products on any given day before electronic shelf labels were introduced, a share that increased by only 0.0006 percentage points after digital labels were installed. Advertisement The study also determined that discounts were slightly more common after digital labels were introduced. Economists have long wondered why grocery prices don't change more often, according to Stamatopoulos. If bananas are about to expire, for example, it makes sense to lower the price on them. He said the cost of having workers change prices by hand could be one issue. But there's another reason: Shoppers watch grocery prices closely, and stores don't want to risk angering them. 'Selling groceries is not selling a couch. It's not a one-time transaction and you will never see them again,' Stamatopoulos said. 'You want them coming to the store every week.' Electronic price labels aren't new. They've been in use for more than a decade at groceries in Europe and some US retailers, like Kohl's. But they've been slow to migrate to US grocery stores. Only around 5 percent to 10 percent of US supermarkets now have electronic labels, compared to 80 percent in Europe, said Amanda Oren, vice president of industry strategy for North American grocery at Relex Solutions, a technology company that helps retailers forecast demand. Oren said cost is one issue that has slowed the US rollout. The tiny screens cost between $5 and $20, Oren said, but every product a store sells needs one, and the average supermarket has 100,000 or more individual products. Advertisement Still, the US industry is charging ahead. Walmart, the nation's largest grocer and retailer, hopes to have digital price labels at 2,300 US stores by 2026. Kroger is expanding the use of digital labels this year after testing them at 20 stores. Whole Foods is testing the labels in nearly 50 stores. Companies say electronic price labels have tremendous advantages. Walmart says it used to take employees two days to change paper price labels on the 120,000 items it has in a typical store. With digital tags, it takes a few minutes. The labels can also be useful. Some have codes shoppers can scan to see recipes or nutrition information. Instacart has a system in thousands of US stores, including Aldi and Schnucks, that flashes a light on the digital tag when Instacart shoppers are nearby to help them find products. Ahold Delhaize's Albert Heijn supermarket chain in the Netherlands and Belgium has been testing an artificial intelligence-enabled tool since 2022 that marks down prices on its digital labels every 15 minutes for products nearing expiration. The system has reduced more than 250 tons of food waste annually, the company said. But Warren and Casey are skeptical. In their letter to Kroger, the US senators noted a partnership with Microsoft that planned to put cameras in grocery aisles and offer personalized deals to shoppers depending on their gender and age. In its response, Kroger said the prices shown on its digital labels were not connected to any sort of facial recognition technology. It also denied surging prices during periods of peak demand. 'Kroger's business model is built on a foundation of lowering prices to attract more customers,' the company said. Advertisement

Air Canada adds new flights to popular European destinations
Air Canada adds new flights to popular European destinations

Yahoo

time3 hours ago

  • Yahoo

Air Canada adds new flights to popular European destinations

Air Canada's inaugural flight from Montreal to Porto, Portugal, on June 4 has added to the air carrier's growing list of new and existing European destinations. 'We are delighted to be returning to Porto, marking our newest Europe route this summer and second destination in Portugal,' said Mark Galardo, executive vice–president and chief commercial officer and president, cargo. 'We design routes like this one to appeal to our customers throughout our North American network, with convenient travel options at our Montreal hub. A world heritage city and gateway to Portugal's northern region, Porto offers an array of history, culture, outdoor adventures and gastronomic experiences.' Air Canada's return to Porto complements its existing flights from Montreal and Toronto to Lisbon. Other new European routes announced for this summer include the launch of its Naples route in May and the return of the Ottawa to London LHR route in April. In addition, Air Canada recently launched its Toronto to Prague route, while the carrier's Montreal to Edinburgh route is set to launch at the end of the month. The Porto flights will be operated on Air Canada's Airbus 330-300. Customers can choose from three classes of service: economy, premium economy and Air Canada signature class, offering customers superior comfort and convenience in an exclusive cabin, with spacious lie-flat seating, personalized service, fine cuisine, extra baggage allowance and access to priority airport services.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into the world of global news and events? Download our app today from your preferred app store and start exploring.
app-storeplay-store