logo
Shannon LNG power plant project stalled by legal challenge

Shannon LNG power plant project stalled by legal challenge

Friends of the Irish Environment (FIE) asked the High Court to allow a judicial review of An Bord Pleanála's decision to grant permission for the project
The environmental group argues that the greenhouse gas emissions that would result from the gas-powered electricity generation plant have been undercounted.
It says if the plant goes ahead, the electricity sector will breach the emissions threshold legally set for it.
It also says An Bord Pleanála, by granting planning permission, failed in its responsibilities under Section 15 of the Climate Act which requires that public bodies act in accordance with the Climate Action Plan.
Judge Richard Humphreys granted the group's request for leave for a judicial review and listed the case for a fortnight's time.
Shannon LNG has been trying to build a liquefied natural gas (LNG) terminal and regassification plant on the Co Kerry coast for almost 20 years and is involved in a protracted planning and legal battle over the project.
However, last March it received permission for a separate but related electricity generation plant on the same site.
The plant, which would be one of the country's biggest, would burn high-emissions conventional fossil fuel gas to generate electricity.
It would also have the option of burning even more emission-intensive LNG if the import terminal and regassification plant receive permission.
Opponents argue that approving the power plant will make it harder to refuse the LNG facilities and create a 'lock-in' effect, embedding LNG in the country's energy supply for the long term.
ADVERTISEMENT
Shannon LNG argues the power plant is necessary because of the growing demand for electricity in the country.
It argues shipping LNG into Ireland is necessary because most of the country's supply of conventional fossil gas comes from an undersea pipe from the UK which could be vulnerable to disruption.
The Government supports that view and earlier this year lifted a ban on LNG importation.
In papers lodged to the court, FIE said there were critical failures in the environmental impact statement submitted by Shannon LNG in its planning application.
Paul Price, adjunct professor at Dublin City University, said the method the company used to calculate the likely greenhouse gas emissions was incorrect and the emissions were 'significantly underestimated'.
The group argues that new power plants that would generate more than 3 gigawatts (GW) of electricity were already awaiting construction – more than the 2GW the Government said was needed to meet electricity demand to the end of the decade.
"Even on the developer's emissions calculations (which significantly underestimate greenhouse gas emissions) this single power station would on its own account for one-third own of all budgeted emissions from the entire electricity sector in 2030,' it argues.
'Nowhere does the Inspector [of An Bord Pleanála] explain how this could possibly be compliant with the relevant carbon budgets and sectorial emissions ceilings.'
The matter back in court on May 26th.

Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Revealed: How much RZLT have local authorities paid to date?
Revealed: How much RZLT have local authorities paid to date?

Agriland

time16 hours ago

  • Agriland

Revealed: How much RZLT have local authorities paid to date?

Local authorities have paid out more than €11 million to date in Residential Zoned Land Tax (RZLT) payments to Revenue, according to new figures provided to Independent senator, Victor Boyhan. RZLT applies to land that is included on an annually revised map published by a local authority and that is not a residential property. The self-assessed annual tax is based on the valuation of a relevant site and is calculated at 3% of the market value of the relevant site. The figures were provided to Senator Boyhan by the County and City Management Association (CCMA) which is the representative body for the chief executives of Ireland's 31 local authorities. According to the senator the figures provided by CCMA 'are a revelation in themselves'. He added: 'Central government have empowered Revenue through legislation to pursue our councils to cough-up and pay RZLT, at a time when many councils are struggling financially to provide services and the administrative burden of preparing RZLT return simply does not make sense. 'It raises questions about the governments real commitment to divest more powers and functions form central government to local government'. RZLT According to the figures Dublin City Council has had the highest RZLT bill so far while Leitrim County Council has had the lowest. Source: CCMA Senator Boyhan told Agriland that it is his view that RZLT is 'penalising councils' but he can also understands why council chief executives might be slow to criticise government policy. Today (Friday, June 6) he called for all councils 'to be reimbursed for RZLT paid to date'. Senator Boyhan added: 'I know there are thousands of new homes at various stages in the pipeline either via An Bord Pleanála or councils that have been granted planning permission and have never been commenced and that's where the government needs to focus its energies on if wants to accelerate new housing delivery. 'I too know that An Bord Pleanála have a very large caseload of planning applications for new homes on their desk which they are currently unable to process due to staff shortages. 'So new home proposals are stuck in certain parts of the planning process, the promise rapid roll out of the New Planning Act just hasn't happened, despite the all the political promises.' He believes that its time for companies and organisations that hold full planning permission for housing development to 'use it or loss it' . 'That will flush out real housing opportunities and deliver new homes, that's the sort of proactive policy I want to see the government pursue rather than also targeting agricultural land in active use,' he added. The senator is also urging farm representative bodies to continue to campaign to encourage the government to 'exclude RZLT on land in active farm use and production'.

Developer lodges plans for second Wicklow solar farm with 40-year lifespan
Developer lodges plans for second Wicklow solar farm with 40-year lifespan

Irish Independent

time2 days ago

  • Irish Independent

Developer lodges plans for second Wicklow solar farm with 40-year lifespan

Located in the townland of Ballymoney, just off the M11, the proposed development is the second planned by BNRG Ballymoney Limited, which received consent for a solar farm (covering up to 9.8-hectares) on a neighbouring 19-hectare site in 2019, despite two submissions raising concerns around privacy, biodiversity and visual impact, before being approved by An Bord Pleanála in 2020 after a third party appeal. BNRG Ballymoney Limited's latest application proposes to construct PV panels mounted on metal support structures arranged in rows running east to west, covering a total area of 31.6 sqm, along with a battery energy storage system (BESS), with access provided via the neighbouring, approved solar farm. As revealed in a search of Wicklow County Council (WCC) and An Bord Pleanála planning portals by Neo Environmental, acting on behalf of BNRG Ballymoney Limited, '10 solar farms are consented within a 5km radius of the application site'. The solar farm, battery energy storage system BESS and main infrastructure, including inverter stations, MV stations, new access tracks, underground cabling, a temporary construction compound and a substation, will occupy five fields of agricultural land currently being used for arable farming, with perimeter fencing surrounding it, 16 CCTV cameras and access gates. In Neo Environmental Ltd's planning statement, a consultant noted that, overall, the proposed footprint constitutes a 'relatively small percentage of the total area of the application site', with 16,687.5 sqm allocated for infrastructure (c. 6.14pc of the site area). Commenting on the proposed 40-year lifespan of the development, the consultant noted that WCC would appreciate from their experience with renewable energy projects that developers have 'historically used an operational period of approximately 30 years when seeking planning consent for such schemes'. 'These timescales were initially led by manufacturing guidelines and were originally based upon the expected lifespan of the infrastructure incorporated within the proposals,' they wrote. 'However, by virtue of technological advancements and industry experience, evidence now indicates that the expected operational lifespan of modern solar PV technology significantly exceeds the previously estimated 30 years. 'The proposed layout and design is considered to strike an optimum balance between clean energy production and all environmental and technical considerations.' A decision is due on the application by July 9, with public submissions accepted by Wicklow County Council until June 18.

Plans lodged for 666 homes, crèche and new Wicklow bridge
Plans lodged for 666 homes, crèche and new Wicklow bridge

Irish Independent

time3 days ago

  • Irish Independent

Plans lodged for 666 homes, crèche and new Wicklow bridge

Lodged by Certain Assets of Dawnhill and Windhill Limited, the proposed development will see the demolition of three structures on a 25.07-acre site in Kilbride to make way for 578 semi-detached and terraced houses, comprising 100 two-beds, 317 three-beds, and 161 four-beds, along with 88 apartments and duplex apartments in a mix of 24 one-beds, 51 two-beds and 13 three-beds. The c. 2335 sqm 'local centre' will feature a c.1,095 sqm crèche with an outdoor play area, three community/medical units, and three retail units. Building heights within the development will range from one to five storeys, with all residential units having associated private open space facing north, south, east and west. A new public boardwalk/bridge for pedestrians and cyclists from the development across Arklow marsh and the Avoca River to the Arklow Riverwalk is also proposed, with the bridge element across the Avoca River constructed atop the concrete columns (debris traps) permitted as part of the Arklow Flood Relief Scheme. Forming part of the designated Kilbride Action Area Plan, the development will include streets, pedestrian/cycle links, open spaces/parks (with play areas) and will see the closures of two existing entrances onto the Kilbride Road, along with amendments to the permitted open spaces and access road granted as part of an adjacent 86-home development by Certain Assets of Dawnhill and Windhill Limited, which was conditionally granted by An Bord Pleanála last year after a third-party appeal. Adding to the wave of developments in the works on the back of the completion of Arklow's Wastewater Treatment Plant, Certain Assets of Dawnhill and Windhill Limited's latest application has been welcomed by Wicklow-Wexford TD Brian Brennan as a 'potentially game-changing residential development for Kilbride in Arklow'. 'This is exactly the boost that Arklow needs, however, we must ensure that this, and any other projects for the town provides all the infrastructural requirements in terms of roads, access, traffic management and also the facilities to meet the needs of the growing population, from schools, sports and leisure facilities, provisions for entertainment and community spaces,' he said. 'We need to start to make serious progress on a second bridge in Arklow and the development of a third link road to the M11. 'Arklow has been waiting for many years for these types of developments, and now that the time has come, we must ensure that we do it properly, giving people the proper facilities to live and work in our town.' Wicklow County Council will make a decision on the application by July 17. Public submissions can made until June 26.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into the world of global news and events? Download our app today from your preferred app store and start exploring.
app-storeplay-store