Phase 3 of Kennedy Expressway work is on schedule, but has drivers frustrated

Phase 3 of Kennedy Expressway work is on schedule, but has drivers frustrated

CBS News02-05-2025

Kennedy Expressway construction work has been back in action this spring, and some commuters are fit to be tied.
"A parking lot," one wrote on the Illinois Department of Transportation Facebook page on the Kennedy Construction Project.
"Will this be completed by 2035?" another wrote.
"Total BS," wrote a third.
If there is any good news for drivers, IDOT said it is on track to finish the final phase of the project before Thanksgiving — not Thanksgiving 2035, but Thanksgiving this year, 2025. That is the very timeline they had in the beginning.
But for drivers, that does not make taking the Kennedy any quicker in the meantime.
Drivers moving only inches is the headache many are experiencing on the inbound lanes of the Kennedy. The two left lanes have been closed since March, so drivers can only take the two right lanes to O'Hare International Airport, and the express lanes to the Edens Expressway, from the Loop.
"It makes me question living in Chicago," said Katie Conklin.
Conklin is a frequent flyer on I-90, spending two hours a day in traffic. It is in that time she asks a question many might have when she doesn't actually see any work actively going on.
"Are there people working?" she said. "Because I need to make myself feel better about living through this, and making sure that there's an end."
Jon Schumacher of the Illinois Department of Transportation said contractors have indeed been hitting the dates. While it might not always look like it, Schumacher said there are 75 workers putting in 10-hour shifts each day.
"You definitely don't see everybody, because there is a substantial amount of work going on beneath the structures as well," he said.
Schumacher said IDOT is currently repairing concrete piers and beams beneath bridges. But its crews are also repaving the interstate.
Under the Kennedy pavement, workers are replacing joints and bridge deck overlays, which IDOT said are toward the end of their lifespan.
This is the third phase of the Kennedy reconstruction project, and it is already 10% to 20% complete.
"Just to extend the life of the bridges another 20 to 30 years," Schumacher said.
Schumacher added that if there is any silver lining, in a couple of months, drivers to O'Hare will be able to take the express lanes.
"At some point here later this summer, we're going to be opening that ramp back up to the local lanes, so we're going to see probably a little more equalization between the locals and the reversible lanes," he said.
As for drivers like Conklin, she said at this point, she has been at the same point before during earlier phases of the Kennedy project.
"I'm telling myself, like, I can make it through the last phase. I did it all three years. So this is it, right?" she said. "Like I've got seven months to go."
IDOT also said there will be ramp closures likely coming after July. The department said it will give out dates and locations before that happens.

Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Kennedy Expressway Ohio Street ramp opening delayed when car drives onto fresh concrete
Kennedy Expressway Ohio Street ramp opening delayed when car drives onto fresh concrete

CBS News

time16 hours ago

  • CBS News

Kennedy Expressway Ohio Street ramp opening delayed when car drives onto fresh concrete

The Illinois Department of Transportation said the reopening of the Ohio Street ramp on the Kennedy Expressway has been delayed. IDOT said a car drove into the work zone and onto freshly poured concrete, damaging the concrete and pushing back the reopening of the outbound ramp by about a week. The third and final phase of the Kennedy Construction Project began in March. While this phase is running ahead of schedule by about a month, according to officials, the whole project isn't set to be completed until Thanksgiving. On June 5, the Division Street and Ontario Street on-ramps to the outbound Kennedy closed for about two weeks. On Monday, June 9, the outbound Kennedy off-ramps North and Fullerton avenues will close for about two weeks. The Ogden Avenue on-ramp to the outbound Kennedy is currently closed, as is the on-ramp at Armitage Avenue. They are expected to reopen the week of June 9. The Ohio Street ramp was also on track to reopen next week until the concrete was damaged. "Reminder: Follow posted signs and stay alert in work zones—your attention keeps everyone safe," IDOT wrote on their social media.

Schumacher's 2001 Grand Prix-winning Ferrari sold for £13.43m
Schumacher's 2001 Grand Prix-winning Ferrari sold for £13.43m

Yahoo

time24-05-2025

  • Yahoo

Schumacher's 2001 Grand Prix-winning Ferrari sold for £13.43m

The Ferrari driven to victory by Formula One legend Michael Schumacher at the 2001 Monaco Grand Prix has been sold for 15.98m euros (£13.43m) at auction. He also raced in the F2001 to win the Hungarian Grand Prix and clinch the fourth of his seven world titles in that year. The car was sold by RM Sotheby's before qualifying for this year's Monaco Grand Prix and became the most expensive car driven by the German, 56, to be sold at auction. It was also the fourth most expensive F1 car ever sold - the world record was set in February when a Mercedes 'streamliner' raced by Sir Stirling Moss and Juan Manuel Fangio went for £42.75m. Previously, the most paid for a car driven by Schumacher was the £9.75m bid for his F2003 back in 2002. Ferrari will hope to emulate Schumacher's 2001 success in Monte Carlo with Charles Leclerc second, behind McLaren's Lando Norris, on the grid for Sunday's race. Mercedes raced by Moss and Fangio sells for record £42.75m

I-57 road work set to start in Iroquois Co.
I-57 road work set to start in Iroquois Co.

Yahoo

time23-05-2025

  • Yahoo

I-57 road work set to start in Iroquois Co.

IROQUOIS COUNTY, Ill. (WCIA) — The Illinois Department of Transportation announced on Thursday that construction on Interstate 57 is set to begin in Iroquois County next week. The construction on I-57 will start on Wednesday, May 28. The nearly five-mile work zone will span from a half mile north of the Illinois 116 interchange at exit 293 to two miles north of the Clifton interchange at exit 297. Central Illinois lanes remaining closed for Memorial Day: The work will mill and resurface the road, including the Clifton interchange ramps. One lane of traffic will be open in each direction during the $9.8 million project, which is expected to be finished in September. Drivers should expect delays and allow extra time for trips through this area and be prepared for slow and stopped traffic. In order to avoid the work area, when possible, motorists should consider the use of alternate routes. Drivers are also encouraged to pay close attention to changed conditions and signs in the work zones, obey the posted speed limits, refrain from using mobile devices and be alert for workers and equipment. Copyright 2025 Nexstar Media, Inc. All rights reserved. This material may not be published, broadcast, rewritten, or redistributed.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into the world of global news and events? Download our app today from your preferred app store and start exploring.
app-storeplay-store