PGCIL commissions Kathalguri-Namsai line ahead of schedule in Arunachal Pradesh
Itanagar: In a significant step toward strengthening the power network in Arunachal Pradesh, Power Grid Corporation of India Limited (
PGCIL
) has completed the 220 kV double circuit Kathalguri-Namsai transmission system five months before its scheduled deadline.
The line was energised late on Saturday night, a PGCIL statement said here on Monday.
The project, carried out under the Tariff-Based Competitive Bidding (TBCB) model, enhances the reliability of electricity supply across the region. Stretching 71 km, the new line connects the
Assam gas-based power plant operated by
NEEPCO
at Kathalguri to a modern 220 kV gas-insulated substation (GIS) at Namsai in Arunachal Pradesh.
A bay extension at the Kathalguri end has also been completed to improve system operations.
The infrastructure upgrade allows smoother power flow from the national grid into Arunachal Pradesh, while also improving voltage stability and providing critical system backup, essential for a dependable year-round electricity supply.
It is expected to significantly support the region's development initiatives, the statement said.
Arunachal Pradesh Deputy Chief Minister Chowna Mein praised the accomplishment.
"Kudos to PGCIL for their exemplary execution and unwavering commitment to the Northeast. This project is a cornerstone in our journey toward robust and reliable energy infrastructure," he said in a social media post.
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Time of India
an hour ago
- Time of India
Power Grid shares in focus on Rs 8.53 crore acquisition of MEL Power Transmission
Power Grid Corporation of India (Power Grid) will be in the spotlight on Thursday, June 5, after the company announced the acquisition of MEL Power Transmission Ltd (MPTL), a project-specific special purpose vehicle (SPV), under the Tariff-Based Competitive Bidding (TBCB) route. The acquisition transaction involved a 100% equity takeover of MPTL. Power Grid acquired the SPV for a total consideration of approximately Rs 8.53 crore. The acquisition cost also accounts for the assets and liabilities of MPTL as on the acquisition date. However, the final purchase consideration remains subject to adjustment based on MPTL's audited financials. The acquisition was completed on June 4. According to the regulatory filing, Power Grid acquired MPTL according to its selection as the successful bidder by the Bid Process Coordinator, PFC Consulting Ltd (PFCCL). The SPV was established for the implementation of the 'Transmission System for evacuation of power from Mahan Energen Limited Generating Station in Madhya Pradesh' on a build, own, operate, and transfer (BOOT) basis. The project's scope includes the development of a 400kV double-circuit (D/C) transmission line and the associated infrastructure at the Rewa (PG) substation, located in the state of Madhya Pradesh. MPTL was incorporated on November 19, 2024, by PFCCL and was created following the government's notification of the TBCB framework aimed at facilitating private sector participation and ensuring transparency in project allocation. Before this deal, neither Power Grid nor its promoter group held any interest in MPTL, the company informed. The shares of Power Grid closed flat at Rs 288.60 on the BSE on Wednesday. ( Disclaimer : Recommendations, suggestions, views and opinions given by the experts are their own. These do not represent the views of The Economic Times)


Economic Times
an hour ago
- Economic Times
Power Grid shares in focus on Rs 8.53 crore acquisition of MEL Power Transmission
Power Grid Corporation of India (Power Grid) will be in the spotlight on Thursday, June 5, after the company announced the acquisition of MEL Power Transmission Ltd (MPTL), a project-specific special purpose vehicle (SPV), under the Tariff-Based Competitive Bidding (TBCB) route. ADVERTISEMENT The acquisition transaction involved a 100% equity takeover of MPTL. Power Grid acquired the SPV for a total consideration of approximately Rs 8.53 crore. The acquisition cost also accounts for the assets and liabilities of MPTL as on the acquisition date. However, the final purchase consideration remains subject to adjustment based on MPTL's audited financials. The acquisition was completed on June to the regulatory filing, Power Grid acquired MPTL according to its selection as the successful bidder by the Bid Process Coordinator, PFC Consulting Ltd (PFCCL). The SPV was established for the implementation of the 'Transmission System for evacuation of power from Mahan Energen Limited Generating Station in Madhya Pradesh' on a build, own, operate, and transfer (BOOT) project's scope includes the development of a 400kV double-circuit (D/C) transmission line and the associated infrastructure at the Rewa (PG) substation, located in the state of Madhya Pradesh. ADVERTISEMENT MPTL was incorporated on November 19, 2024, by PFCCL and was created following the government's notification of the TBCB framework aimed at facilitating private sector participation and ensuring transparency in project allocation. Before this deal, neither Power Grid nor its promoter group held any interest in MPTL, the company informed. ADVERTISEMENT The shares of Power Grid closed flat at Rs 288.60 on the BSE on Wednesday. (Disclaimer: Recommendations, suggestions, views and opinions given by the experts are their own. These do not represent the views of The Economic Times) ADVERTISEMENT (You can now subscribe to our ETMarkets WhatsApp channel)


Time of India
an hour ago
- Time of India
REC shares in focus amid Rs 1.55 lakh cr fundraise plans, SPV strike off
Shares of REC Ltd are likely to be in focus on Thursday after the company's Board of Directors, in a meeting held on June 4, approved a Rs 1.55 lakh crore fundraising plan and the striking off of a project-specific subsidiary. Here are the details: Rs 1.55 lakh crore fundraising plan The board of REC on Wednesday gave a green signal to raise funds of up to Rs 1.55 lakh crore through the private placement of unsecured/secured non-convertible bonds or debentures. The fundraising is subject to shareholder approval at the upcoming Annual General Meeting (AGM) and will be executed in one or more tranches over a one-year period following the AGM resolution, pending approval from competent authorities. SPV strike-off: Rajgarh III Power Transmission Ltd Live Events In another key development, REC also approved the proposal to strike off Rajgarh III Power Transmission Ltd, a wholly owned subsidiary of REC Power Development and Consultancy Limited (RECPDCL). This SPV was originally created under the Tariff-Based Competitive Bidding (TBCB) mechanism to execute the 'Transmission system for Evacuation of Power from RE Projects in Rajgarh (1500 MW) SEZ in Madhya Pradesh - Phase III'. However, following a recommendation from the National Committee on Transmission (NCT) to merge the project with another transmission scheme, the Ministry of Power de-notified the project via an official communication dated March 18, 2025. In response, REC has decided to dissolve the SPV, subject to the necessary statutory and administrative approvals. Also read: Stock Radar: Bharat Forge stock showing signs of bottoming out after over 30% fall from highs; time to buy? REC share price performance As per the BSE Analytics data, REC's stock has declined 11.39% over the past 1 year. On a year-to-date (YTD) basis, the stock is down by 20.67%, while over the last 6 months, it has fallen by 26.25%. In contrast, the stock has gained 3.64% in the last 3 months, but recorded a 4.51% decline over the past 1 month. On Wednesday, the shares of REC closed flat at Rs 400.95 on the BSE. ( Disclaimer : Recommendations, suggestions, views and opinions given by the experts are their own. These do not represent the views of The Economic Times)