Work on Sterling's $6M Second Street construction project rolls out next week
Apr. 9—STERLING — Sterling's Second Street road construction project, which will rebuild 10 blocks along Second Street from First Avenue to Route 2, is expected to start next week.
Sterling city officials held an open house Tuesday, April 8, to answer residents' questions about the project that will be completed by Gensini Excavating of Princeton at a price tag of $6.2 million.
"The whole road will be cored out," Gensini estimator Mike Garland said. "They're going to get new curbs and sidewalks on both sides. The driveways will be redone in those areas, and then, right away, new storm sewer system, and then a new asphalt road."
Engineer Kyle Lorenz of Willet Hofmann & Associates said the work will be completed in five phases and expects the project will be finished by June 2026.
"The first phase will be from Ninth Avenue to Broadway [Avenue], the end of it by the Dillon Home, and then from Ninth to Sixth Avenue, Sixth to Third [Avenue], and Third to Illinois 40," Lorenz said. "The fifth stage will probably be the pedestrian bridge."
The 160-foot pedestrian bridge will cross over Illinois 40 near the north side of the train tracks, extending behind the Plainwell Brass building and leading to a new multi-use bikeway path on East Second Street from First Avenue to Broadway Avenue.
The Sterling City Council approved a resolution in October authorizing Mayor Diana Merdian to enter into an agreement with the Illinois Department of Transportation and allocate $655,203 in local matching funds for the bikeway path's construction as part of the project.
City Manager Scott Schumard has said the majority of the bikeway path will be funded with IDOT's Illinois Transportation Enhancement Program grants. The ITEP grant will reimburse the city for 80% of the bikeway path construction and the city will be responsible for the remaining 20%.
Several Sterling residents living on Second Street, including Pam and Joe Machan, expressed concerns over the potential impact of the construction.
"One of our big concerns is being trapped in our driveways," Pam said. "Because when American Water did that street a couple of years ago, there was a four-hour period where we weren't told in advance that we could or could not leave, and that's what we want to avoid."
Garland assured the Machans they would be notified 24 hours in advance of any driveway work that might impact them.
ExpandAutoplay
Image 1 of 8
A rendering of Sterling's Second Street road construction project is shown during an open house on April 8, 2025. (Brandon Clark)
"If we're doing driveway replacements and we have to redo the concrete, yeah, we have to cut off access, but we'll let you know ahead of time so you can get your cars out of there, and park on a side street and then you can go back," Garland said. "Other than that, you're going to have access to your house at all times."
Garland said construction will generally occur Monday through Friday from 7:30 a.m. to 3:30 p.m., and Lorenz said crews will be out on Tuesday, April 15, performing water work site preparation.
"They're going to move some of the domestic vault belts," Lorenz said. "They're going to move some of them so that they're out of the way, and then they're also going to where we have conflicts with storm sewer, they're going to be lowering them."
The Second Street project was originally planned for last year but approval delays impacted the city's ability to schedule as much roadwork as it could have. Each year, the city sends a list of streets that need to be resurfaced and rebuilt to their engineers to prepare bids for the first half of the year.
Schumard said that by the time the city learned the Second Street project would likely be delayed until 2025, allowing them to add more roads to their list of projects, contractors responding to those bids were already booked and required the city to extend the project deadlines if the city wanted a lower price.
Although the city is responsible for 100% of the Second Street roadwork costs, Schumard said the majority of that project's cost already is in place by using a combination of motor fuel tax funds, the city's allotment of federal Surface Transportation Program funds and Sterling's local option sales tax.
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles
Yahoo
30-05-2025
- Yahoo
Darius Garland And Jarrett Allen Are No Longer Considered Untouchable By Cavaliers
Darius Garland And Jarrett Allen Are No Longer Considered Untouchable By Cavaliers originally appeared on Fadeaway World. The Cleveland Cavaliers are entering a pivotal offseason with serious questions surrounding two of their key players. According to Cavs insider Chris Fedor, Darius Garland and Jarrett Allen are no longer considered untouchable, a clear signal that Cleveland may be ready to shake things up after a disappointing postseason exit. Advertisement This is a stark departure from the franchise's previous stance. Garland and Allen were once viewed as integral building blocks. But after another early playoff flameout, the Cavaliers are acknowledging what's become obvious: the current core has hit its ceiling. Cleveland's regular season told a different story. They finished first in the Eastern Conference with a stellar 64–18 record, the second-best mark in franchise history behind only the 2016 championship team. However, injuries and underwhelming performances doomed their playoff run. Garland missed the first two games of their second-round series against the Indiana Pacers and looked out of rhythm upon returning. He averaged just 14 points on abysmal shooting splits and struggled to generate any offensive momentum. Jarrett Allen, meanwhile, was healthy but ineffective. Across Games 4 and 5, he totaled just 11 points and six rebounds, staggering numbers for a player expected to anchor the paint. Advertisement The Pacers outplayed the Cavaliers in every facet, handing Cleveland a humiliating 44-point deficit at one point in Game 4 and ultimately eliminating them in just five games. The playoff letdown has prompted Cleveland's front office to reconsider its trajectory. The Cavaliers are severely limited in flexibility due to salary cap constraints. They are currently operating above the second apron, which restricts their ability to sign free agents, aggregate salaries in trades, and even use their full mid-level exception. In short, the only way to truly retool the roster is to part with significant pieces, and that likely means moving either Garland, Allen, or both. Garland's playoff inconsistency is a growing concern. While the 24-year-old has shown flashes of brilliance in the regular season, his postseason track record leaves much to be desired. Advertisement His career playoff numbers pale in comparison to his regular season stats, particularly in scoring efficiency and decision-making under pressure. Despite his playmaking upside and youth, the Cavs may view him as a movable asset in pursuit of a better-fitting backcourt partner for Donovan Mitchell. Allen's durability and limitations have also drawn scrutiny. He missed most of the 2024 postseason due to a rib injury and was largely a non-factor this year against Indiana. While Allen remains one of the league's better rim protectors, his limited offensive game and struggles against physical playoff opponents have cast doubt on his long-term fit next to Mobley. The Cavaliers don't want to waste Mitchell's prime or Mobley's growth curve. With both stars viewed as foundational, it's clear the organization is ready to explore bold changes. Advertisement The Garland-Allen duo may have helped lift Cleveland out of its post-LeBron era, but if the Cavaliers want to be more than regular-season darlings, they might need to make some painful but necessary moves. Related: New Trade Idea Sends Four Players To The Lakers, Including Top Center From Eastern Powerhouse This story was originally reported by Fadeaway World on May 28, 2025, where it first appeared.
Yahoo
22-05-2025
- Yahoo
Illinois awards funding for Constitution Trail extension
BLOOMINGTON, Ill. (WMBD) — The state of Illinois announced on Wednesday that it awarded funding for a trail extension project in Bloomington. Gov. JB Pritzker and the Illinois Department of Transportation awarded $799,419 for the Constitution Trail Extension Project, according to information from IDOT. The project will expand the Constitution Trail from Lafayette Street to Hamilton Road with a 10-foot-wide asphalt multi-use path. Groundbreaking for Constitution Trail expansion at Heartland College The money for the project is part of $139.2 million that was awarded through the Illinois Transportation Enhancement Program, which is meant to expand local travel options and enhance quality of life in communities across the state. 'The Illinois Transportation Enhancement Program is a crucial part of Rebuild Illinois, helping make travel safer and more accessible in the communities that need it most,' Pritzker said. 'Today, I'm proud to announce the largest investment in the program's history, with more than $139 million going toward bike lanes, sidewalks, trails and other local improvements. This is just one part of the state's larger effort to reverse decades of disinvestment and create more connected communities.' A total of 66 projects were approved through the Illinois Transportation Enhancement Program. Copyright 2025 Nexstar Media, Inc. All rights reserved. This material may not be published, broadcast, rewritten, or redistributed.
Yahoo
22-05-2025
- Yahoo
Champaign Co. projects will receive part of $139M grant for Illinois transportation work
CHAMPAIGN, Ill. (WCIA) — Nearly $140 million in funding has been awarded to transportation projects around the state — including two projects in Champaign County that have been in the works for a while. On Wednesday, Governor JB Pritzker and the Illinois Department of Transportation announced that $139.2 million has been awarded through the Illinois Transportation Enhancement Program. The goal of the program is to expand local travel options and to enhance the quality of life in communities statewide, according to a news release from IDOT. City of Champaign could help renovation of downtown building $3 million will go toward Champaign's Kirby Avenue complete street project. Project engineers told WCIA last year that the project would include replacing the bridge and adding bike lanes and pedestrian upgrades to the Kirby Avenue overpass. WCIA previously reported that the complete street project was a part of the city's comprehensive plan. Officials said they hoped to begin construction in the spring of 2026. Savoy will receive $1.3 million to improve the Prairie Fields path. WCIA previously reported that the project would create multi-pathways and connect to other paths in Savoy. Pritzker said the Illinois Transportation Enhancement Program, which is a part of Rebuild Illinois, aims to help make travel safer and more accessible. 'Today, I'm proud to announce the largest investment in the program's history, with more than $139 million going toward bike lanes, sidewalks, trails and other local improvements,' Pritzker said. 'This is just one part of the state's larger effort to reverse decades of disinvestment and create more connected communities.' Bus stop near Market Place Mall could be looking at new routes IDOT received 233 applications for an estimated $383 million in funding. IDOT said the projects chosen are based on their readiness and connection to transportation networks, as well as their ability to secure public support and provide public benefits. Areas with higher need are given additional consideration. 'When people think about where they want to raise their families, it's projects like these that really move the needle,' State Senator Paul Faraci (D-Champaign) said. 'When communities have complete streets, sidewalks and bike paths they become places people want to live.' You can read more about the project and the project's recipients here. Copyright 2025 Nexstar Media, Inc. All rights reserved. This material may not be published, broadcast, rewritten, or redistributed.