Almost a decade gone, Metro Phase II of Bengaluru is still not on track
Bengaluru: Below par, underwhelming: That's the scorecard for Namma Metro' s Phase II pace of construction. Nearly 10 years after BMRCL began construction on Phase II, a substantial portion of the planned expansion remains incomplete.
Of the 75km of new lines planned, more than 40km is still not operational. Prolonged delays, coupled with other factors, led to a major cost overrun. The project's estimated cost ballooned from Rs 26,405 crore to Rs 40,614 crore — an increase of over Rs 14,000 crore.
In the same period, the traffic situation on the road got worse: In the absence of a robust public transport system, Bengaluru, which had 7.7 million vehicles in 2016, now has 12 million, adding to congestion.
And a likely silver bullet – which promises timely commuting, with less uncertainty – is missing.
The Phase II project, which received sanction in Feb 2014, involved extending the operational Purple and Green Lines in four directions for a total length of 35km, along with two new lines: Yellow Line from RV Road to Bommasandra (19km) and Pink Line from Kalena Agrahara to Nagawara (21km). BMRCL opened these extensions in phases.
The first stretch — Yelachenahalli to Silk Institute (6.29km) — was inaugurated in Jan 2021. The Mysuru Road-Kengeri section opened in Aug 2021, followed by the KR Pura-Whitefield stretch (13km) in March 2023. In Oct 2023, two sections — Baiyappanahalli-KR Pura (2.2km) and Kengeri-Challaghatta on Purple Line — were opened. The Green Line extension on Tumakuru Road from Nagasandra to Madavara (3km) opened in Nov 2024.
Regarding the new lines, although the Yellow Line is ready, a shortage of coaches delayed its operation. After missing several deadlines, BMRCL officials plan to open the line initially with just three trains. Pink Line, which includes a 13km tunnel network, has already been postponed to 2026.
Multiple factors contributed to delays in the project, including late land acquisition, delays in floating tenders, design changes, financial difficulties causing construction companies to halt work midway and the pandemic, resulting in poor project implementation.
For instance, the construction of a double-decker section on Yellow Line was never part of the original plan; the plan to build a double-decker from Ragigudda to Silk Board was added at a much later stage.
On the Pink Line, the elevated section from Kalena Agrahara to Swagath Cross Road (7km) saw a contractor abandon the project midway due to financial issues. After a long gap, BMRCL appointed a new contractor to continue the work.
It has been eight years, and the project is still under construction.
The delay in project execution, rising land acquisition costs, extension of the network by 3km, and construction of new depots all contributed to the steep rise in the project cost. Thursday, the state cabinet approved an increase of Rs 9,729 crore for the Phase II project.
It is reported that the state govt urged Union minister for housing and urban affairs, Manohar Lal Khattar, during his visit to Bengaluru, to approve the revised project cost and sanction Phase III of Namma Metro, extending from Sarjapur to Hebbal.
GFX
PHASE II
* SANCTIONED IN 2014
* LAUNCHED IN 2016
* WAS TO BE READY BY 2020
* LIKELY TO BE FULLY OPERATIONAL BY 2026
* 116km: Full operational length of phase II
*77km: Operational line as of today
* 8L: Ridership per day as of now
++++
Glitch disrupts services for 5 hours
Namma Metro services on Purple Line were disrupted for nearly five hours Friday morning due to a technical snag at the Whitefield (Kadugodi) station. BMRCL officials said operations between Hope Farm Channasandra and Whitefield stations were suspended from 5am to 9.55am.
However, there were no disruptions on the rest of the Purple Line between Challaghatta and Hope Farm Channasandra. The Green Line remained fully operational with no impact on its schedule.
——-
Early operations for UPSC exams
To assist aspirants appearing for the preliminary exams of the Union Public Service Commission scheduled for Sunday, BMRCL announced that Metro services will start an hour earlier that day. According to a release, train services will begin from terminal stations (Whitefield, Challaghatta, Madavara, and Silk Institute) at 6am, instead of the usual 7am on Sundays.
Get the latest lifestyle updates on Times of India, along with
Brother's Day wishes
,
messages
and quotes !

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Time of India
37 minutes ago
- Time of India
Long-pending central govt's infra projects in Belagavi back on track
Belagavi: Several long-pending central govt's infrastructure projects in and around Belagavi are finally gaining momentum after years of delay, primarily due to land acquisition hurdles. The breakthrough comes with the combined efforts of DC Mohammad Roshan and Belagavi MP Jagadish Shettar , who took these stalled projects as a top priority. Key among them is the much-awaited Belagavi-Dharwad railway line via Kittur, a 73-km project sanctioned in 2019 during the tenure of former MP and MoS for railways, the late Suresh Angadi. Despite funding from the Centre, the project was held up for years due to land-related issues. However, DC Roshan recently announced that land acquisition is now complete, and the work is expected to commence shortly. The Halaga-Macche bypass highway, a vital route connecting Pune-Bengaluru NH-4 and Belagavi-Goa national highway, sanctioned in 2009, also faced prolonged delay due to legal land disputes. With the district administration actively mediating and convincing landowners, the impasse has been resolved, and construction is underway. by Taboola by Taboola Sponsored Links Sponsored Links Promoted Links Promoted Links You May Like Use an AI Writing Tool That Actually Understands Your Voice Grammarly Install Now Undo Another major infrastructure project, the Belagavi Ring Road was sanctioned in 2018. The Rs 3,800 crore project to be executed in three phases, received Rs 1,622 crore for the first phase of 34 km. DC Roshan recently confirmed that 80% of the land acquisition is now complete. This ambitious project, sanctioned under the Bharatmala project, will help resolve the traffic congestion in Belagavi city. "Most of these projects were delayed despite being sanctioned, because of land-related issues. After I became MP, I prioritised these issues, met Union ministers, held review meetings with officials, and visited the sites. Today, we are seeing the results. I expect the required land to be fully acquired in the next 2-3 months and the tender process to begin within 5-6 months," said MP Jagadish Shettar. He credited DC Mohammad Roshan for playing a vital role in resolving bureaucratic and on-ground challenges related to land acquisition. In addition, Shettar informed that land acquisition for Belagavi-Hunagund-Raichur highway, a Rs 1,452 crore project, has also reached near completion. He further assured that the new terminal at Belagavi airport will be ready by March 2026, marking a step toward upgrading the facility to international standards.


Time of India
40 minutes ago
- Time of India
Mining industry seeks Rs 15,000 per kWh subsidy for electric trucks
The domestic mining industry has sought a Rs 10,000 to Rs 15,000 per kWh subsidy on electric Heavy Earth Moving Machinery (HEMM) to encourage their use. According to a report by the Federation of Indian Mineral Industries (FIMI), the upfront costs of electric trucks is a major entry barrier to their adoption. 'Electric trucks and other HEMMs are currently priced at nearly three times (3x) that of their diesel counterparts. Such price disparity discourages potential buyers,' a FIMI report said. The industry body report also recommended a 5% Goods and Services Tax rate on retrofit kits used to convert diesel trucks to electric. 'Retrofit kits currently do not have a dedicated classification. Instead, the individual components of these kits are taxed separately often at rates exceeding 18% which undermines the economic viability of retrofitting,' the report said.
&w=3840&q=100)

Business Standard
42 minutes ago
- Business Standard
TA Associates exits AU Small Finance Bank; sells 1.26% stake for ₹714 cr
Private equity firm TA Associates on Tuesday exited AU Small Finance Bank by selling its entire 1.26 per cent stake in the company for Rs 714 crore through an open market transaction. According to the bulk deal data available on the BSE, US-based TA Associates through its arm TA FDI Investors sold 93.90 lakh shares, amounting to a 1.26 per cent stake in Jaipur-based AU Small Finance Bank (AU SFB). The shares were disposed of at an average price of Rs 760.07 apiece, taking the deal value to Rs 713.78 crore. Details of the buyers of AU SFB's shares could not be ascertained on the BSE. Shares of AU Small Finance Bank fell 0.93 per cent to close at Rs 764.70 apiece on the BSE. In a separate block deal on the BSE, Morgan Stanley Asia (Singapore) sold 1.25 lakh shares of Bajaj Finserv for Rs 25 crore through an open market transaction. The shares were offloaded at an average price of Rs 1,983.8 apiece, taking the deal value to Rs 24.80 crore. These shares were acquired by Paris-based BNP Paribas through its affiliate BNP Paribas Financial Markets at the same price. The scrip of Bajaj Finserv slipped 0.92 per cent to settle at Rs 1998.35 apiece on the BSE.