All 592 suspender ropes at the George Washington Bridge are now replaced

All 592 suspender ropes at the George Washington Bridge are now replaced

Yahoo07-03-2025

All of the George Washington Bridge's original suspender ropes have been replaced, the Port Authority of New York and New Jersey announced on Thursday. This marks the completion of a seven-year effort and a major milestone in a comprehensive $2 billion rehabilitation project of the almost 100-year-old bridge.
Over the last seven years, Port Authority crews have worked to replace each of the bridge's 592 suspender ropes. To accomplish this, crews secured temporary ropes at each panel point across the bridge as well as the adjacent panel points to support the bridge's weight at that location, the Port Authority said. They then disconnected and removed the original ropes. After that, crews installed and secured the new ropes to the span's girders, finally disconnecting the temporary ropes.
The suspender ropes range in length from 38 feet to 674 feet, with the longest near the bridge's two towers and the shortest at the center of the span, according to Port Authority.
Though traffic was allowed to continue flowing throughout the duration of this project, one sidewalk was closed at a time to allow work crews to access the ropes. This also enabled the agency to completely rebuild both of the span's shared use sidewalks.
The completely rebuilt north sidewalk reopened after every suspender rope on that side of the bridge was replaced with the south sidewalk closing in February 2023. Now that the suspender rope project is complete, the Port Authority expects to complete work on the south sidewalk and reopen the path in 2026. Once the south sidewalk's construction is done, pedestrians will have dedicated use of it while bicyclists will exclusively use the north sidewalk.
The bridge's main cables were also rehabilitated as part of this project with 26,474 compacted wires within each cable being recoated and rewrapped. A new elastomeric wrap was added along with a new dehumidification system to extend the lifespan of the main cables. According to Port Authority, if the main cable wires from all four cables were laid end to end it would be long enough to wrap around the Earth four times.
"Replacing all 592 suspender ropes on the George Washington Bridge is a remarkable feat of engineering as we work to rehabilitate and renew nearly every major component of the world's busiest bridge," said Port Authority Chairman Kevin O'Toole. "Over seven years, our teams diligently planned and worked with precision and perseverance to ensure the bridge remains safe and reliable for millions who depend on it for work, commuting or travel."
He continued, "As the bridge nears its centennial, we're proud to help preserve its legacy as an engineering marvel while securing its future for decades to come."
This work is all part of a $2 billion project known as the Restoring the George program. This program is described by Port Authority as "one of the most ambitious renewal projects among the Port Authority legacy infrastructure and most comprehensive rehabilitation since the bridge opened 94 years ago."
This program touches nearly every major component of the bridge, addressing wear and tear from the approximately 100 million vehicles that cross it each year.
Multiple projects under this program have already been completed with several ongoing or remaining such as the rehabilitation of the Center Avenue and Lemoine Avenue bridges, the rehabilitation of lower-level steel, paint removal and replacement of movable maintenance platforms, among other things.
The full program is expected to be completed in 2030.
This article originally appeared on NorthJersey.com: George Washington Bridge restoration project reaches milestone

Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Toddler rescued from luggage conveyor belt at Newark Liberty International Airport
Toddler rescued from luggage conveyor belt at Newark Liberty International Airport

Yahoo

time7 days ago

  • Yahoo

Toddler rescued from luggage conveyor belt at Newark Liberty International Airport

The Brief A toddler climbed onto a luggage conveyor belt at Newark airport last week. Port Authority officers rescued the child, who was headed for an X-ray machine. The toddler was saved without any injury. NEWARK, N.J. - Officers are being praised for saving the life of a young child after some terrifying moments unfolded at an airport in New Jersey last week. What we know A toddler wandered onto a luggage conveyor belt in Terminal A at Newark Liberty International Airport on Wednesday evening. Officials say the young child was headed for an X-ray machine, but was rescued by Port Authority officers just minutes later. The child was found uninjured in the checked baggage room on the lower level, according to who says the child's mother was at the JetBlue ticketing counter on the departures level. The Port Authority says the child's family is "grateful" for the outcome. What they're saying "The cops, realizing the danger the child was in, without hesitation, entered the conveyor system and, after about four minutes, located the child who was headed for an x-ray machine," the Port Authority Police Benevolent Association Inc said in an Instagram post. The Source Information from this article was sourced from the Port Authority Police Benevolent Association Inc and

Newark Airport to open its shuttered runway Monday, 13 days ahead of schedule
Newark Airport to open its shuttered runway Monday, 13 days ahead of schedule

Yahoo

time01-06-2025

  • Yahoo

Newark Airport to open its shuttered runway Monday, 13 days ahead of schedule

Newark Liberty International Airport on Monday will reopen a closed runway that has contributed to weeks of delays and chaos at the travel hub. Transportation Secretary Sean Duffy will lead a news conference from the airport Monday to mark the runway's reopening. Runway 4L-22R — which is 11,000 feet long — has been undergoing 'planned rehabilitation' after showing 'significant signs of wear' and has now been deemed safe and up to the Federal Aviation Administration's standards, according to a release from the Port Authority of New York and New Jersey, which operates Newark Airport. It had last been rehabilitated in 2014, and runways are typically updated about every 10 years, the statement said. According to the release, the $121 million project began in early March and was set to be finished on June 15. The project included 'milling and paving the runway surface, updating lighting, improving airfield signs with LED lighting, installing new underground electrical infrastructure, and implementing drainage improvements.' Before it was fully shut down on April 15, the runway was closed on nights and weekends to accommodate the construction schedule. To ensure the runway is fully revamped by the end of the year, the Port Authority said it will continue to close on weeknights and again on weekends at the end of the year. However, Monday's reopening will allow 'regular runway operations to resume,' the statement said. During runway 4L-22R's planned future closures, two other runways at the airport will remain fully operational. 'As we approach the busy summer travel season, this key milestone puts us on a path to further reducing congestion, enhancing safety, and ensuring a seamless travel experience,' Duffy said in the Port Authority statement. 'With the runway completed, we'll continue our work to harden the telecoms infrastructure and improving the staffing pipeline for the airspace.' The planned runway construction was not the only reason passengers flying in and out of Newark have faced delays and cancelations this spring. Air traffic controllers serving the airport have experienced a number of communications blackouts while directing planes in the area in recent months due to equipment failures, prompting the FAA on May 20 to reduce the number of flights to and from Newark until the planned runway construction was complete. 'Our goal is to relieve the substantial inconvenience to the traveling public from excessive flight delays due to construction, staffing challenges, and recent equipment issues, which magnify as they spread through the National Airspace System,' acting FAA Administrator Chris Rocheleau said at the time of the announcement. This article was originally published on

Colossal closures could challenge drivers this weekend in and around Seattle
Colossal closures could challenge drivers this weekend in and around Seattle

Yahoo

time01-06-2025

  • Yahoo

Colossal closures could challenge drivers this weekend in and around Seattle

This story was originally published on The busy construction season is upon us and this weekend drivers will be tested with three major closures between Everett, Seattle, and near North Bend. The Washington State Department of Transportation (WSDOT) is in the middle of repairing and repaving the network of bridges between Everett and Marysville, including the Snohomish River Bridge, the Steamboat Slough Bridge, and the Ebey Slough Bridge. This weekend work moves to the Steamboat Slough Bridge in the southbound direction. Originally built in 1927, this section of bridge will undergo rehabilitation work on the end lift upper wheels and the movable span, which have deteriorated over the years from the marine environment. Other preservation work involves seismic retrofitting, repaving and replacing panels on the bridge deck, and a fresh coat of protective paint. This project will close State Route 529 (SR 529) southbound between the Ebey Slough and Steamboat Slough beginning Friday, May 30th at 11 p.m. through Tuesday, June 3rd at 11 p.m. During this closure drivers can only access Smith Island via northbound SR 529, but can leave the island via north and south SR 529. WSDOT plans a similar closure next weekend between Friday, June 6th and Tuesday, June 10th. This weekend's scheduled closure at the Ballard Bridge has been postponed, but the Seattle Department of Transportation (SDOT) will still close the Leary Way Bridge at the north end of the Ballard Bridge. People driving south on 15th Ave NW will need to travel down to Leary Way NW, then use the on-ramp to access the Ballard Bridge. People traveling north from Interbay via the Ballard Bridge will need to exit down to Leary Way NW using the off-ramp to continue into Ballard. SDOT suggests to take the Aurora Bridge as a detour route to avoid increased traffic. There is a weekend closure on the Ballard Bridge scheduled for next weekend. WSDOT is moving forward on the behemoth Interstate 90/State Route 18 Interchange Improvements project through early Wednesday morning. Both directions of State Route 18 (SR 18)will close under the I-90 bridges from 9 p.m. Thursday, May 29, to 5 a.m. Wednesday, June 4, for construction of the diverging diamond interchange. People can detour using eastbound and westbound I-90 and using adjacent interchanges to loop around — exit 20 (High Point Way) or exit 22 (Preston-Fall City) to the west of SR 18 and exit 27 (Southeast North Bend Way) to the east of SR 18. Additionally, SR 18 will be reduced to a single lane with flaggers and pilot vehicles alternating traffic from 9 p.m. Sunday, June 1, to 5 a.m. Monday, June 2, near the Raging River and Deep Creek bridges to shift eastbound SR 18 traffic onto the new bridges.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into the world of global news and events? Download our app today from your preferred app store and start exploring.
app-storeplay-store