India's power transmission body flags regulatory hurdles in equipment procurement
India's
power transmission sector
is facing acute supply-side bottlenecks, especially in procuring High Voltage Direct Current (HVDC) equipment critical for carrying renewable energy over long distances, raising concerns over the country's ability to meet its 2030 renewable energy targets.
The Electric Power Transmission Association (EPTA) has urged the Power Ministry to provide a level-playing field in
procurement
policies, highlighting a regulatory mismatch that allows renewable energy (RE) developers to bypass subcontracting restrictions, while transmission companies remain bound by them.
by Taboola
by Taboola
Sponsored Links
Sponsored Links
Promoted Links
Promoted Links
You May Like
Villas Prices In Dubai Might Be More Affordable Than You Think
Villas In Dubai | Search Ads
Get Quote
Undo
The association has called for a temporary exemption from these restrictions until December 2030, to help transmission developers procure key HVDC components without delay.
'This mismatch between generation and transmission is hurting the overall power sector and delaying addition of capacity,' said an official from a leading transmission company, reported PTI. According to the official, while RE projects are built in 12–18 months, transmission lines often take 3–4 years, and HVDC systems even longer.
Live Events
Also Read:
Adani to announce ₹20,000 crore investments in North East
The issue stems from restrictions on suppliers and subcontractors from countries sharing land borders with India, particularly China, which is a major source of HVDC equipment. Although these curbs apply to central ministries, autonomous bodies, and public-private partnership (PPP) projects, they also extend to transmission developers operating under the fully privately funded Build-Own-Operate-Transfer (BOOT) model, leaving them similarly affected.
The EPTA noted that renewable developers are exempt from these restrictions, following a 2022 clarification by the Ministry of New and Renewable Energy. It stated that while SECI's procurement qualifies as public procurement, the contracts don't fall under 'works contracts,' thereby allowing unrestricted subcontracting, including from China.
Transmission developers, on the other hand, continue to face full restrictions under tariff-based competitive bidding (TBCB). 'Despite TBCB projects not being PPPs, the transmission service providers cannot procure or subcontract from countries sharing land borders with India, thereby severely limiting supplier choices,' said an industry official.
This asymmetry, industry players say, has created a systemic gap between RE generation and transmission readiness, particularly in HVDC-dependent regions like Rajasthan and Khavda in Gujarat.
Also Read:
Maharatna PSU Powergrid projects capex of over Rs 3 lakh crore by 2032
At present, only two domestic OEMs offer LCC-based HVDC systems, while global manufacturers in Europe and the US are booked until 2030, amid surging renewable installations in the West. As a result, the constrained market is pushing project costs higher, with tariffs reaching up to 17% above levelised rates, and project timelines extending up to six years.
'HVDC projects are vital for renewable energy development, and must be governed by the same procurement norms as RE projects,' EPTA said in its representation to the Power Ministry.
Data from two recently concluded HVDC bids show that it took 19 months just to finalise the tender, with an overall implementation window of 54 months. The Central Electricity Regulatory Commission (CERC) has also acknowledged the issue, noting that HVDC component supply constraints are inflating project costs and justifying higher bids.
Calling for urgent policy harmonisation, EPTA Director General G P Upadhyaya said: 'A systemic gap has emerged between generation readiness and
transmission infrastructure
timelines, particularly for HVDC-dependent RE zones like Rajasthan and Khavda in Gujarat. The timely execution of HVDC systems is a critical path for achieving India's renewable energy targets.'
With inputs from PTI
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Time of India
30 minutes ago
- Time of India
Sion police bust illegal call centre in Delhi, nab 1
Mumbai: Sion police have busted an illegal call centre operating out of Delhi and arrested its proprietor. They also issued notices to seven accomplices for impersonating bankers and, under the pretext of updating the KYC of credit/debit cards, duping people across India. Police uncovered the racket following a complaint from a Sion businessman who was defrauded of over Rs 4.5 lakh. In May, the complainant received a call from an unknown person who identified himself as a representative of a private bank. Under the pretext of updating his KYC, during the 50-minute call, the fraudster used social engineering tactics and digital tools to siphon off over Rs 4.5 lakh from his credit card. The victim lodged a complaint with Sion police who traced the SIM card to Krishna Bhatia (22) and his relative Hardik Bhatia in Faridabad, Haryana. Police learnt that multiple SIM cards in their names were handed over to Prince Kumar, who then passed them to Ayush Sharma in Shahjahanpur, UP. Eventually, the SIMs were delivered to the alleged mastermind, Manjit Kumar (29), who ran the illegal call centre at Uttamnagar in Delhi. Sion police, with the help of their Delhi counterparts, raided the call centre and arrested Kumar. He was brought to the city and produced before the Kurla court. — S Ahmed Ali


Time of India
30 minutes ago
- Time of India
Pay your holding tax by Jun 30, avail up to 10% rebate: RMC
1 2 3 Ranchi: The Ranchi Municipal Corporation (RMC) has already raked in 23% of its target revenue for the ongoing fiscal year through holding taxes, with over 54,709 households out of 2.34 lakh registered properties having paid their dues since April this year. "The RMC has collected Rs 22 crore in holding tax payments for the financial year 2025–26, achieving 23% of its annual target of Rs 97 crore," deputy municipal commissioner Gautam Prasad Sahu said. In a bid to encourage early payments, the civic body has announced rebates of up to 10% for those who pay by June 30. The highest rebate, 10%, is offered for payments made online, including through a newly launched WhatsApp chatbot – RMC Payment Mitra (Mobile No: 8986627070). This is the first time RMC is using a chatbot service for tax collection. "This year, a strong push is being made for digital payments. We've already crossed Rs 22 crore in collections within two months of launch," Sahu said. Apart from online, payments made at Jan Suvidha Kendras at the RMC headquarters and Doranda zonal office are eligible for a 7.5% rebate, while door-to-door collection through an authorised agency carries a 5% rebate. Additionally, certain categories such as senior citizens, persons with disabilities, transgender persons, and armed forces personnel can claim an extra 5% rebate upon submission of valid documents.


Time of India
31 minutes ago
- Time of India
The Leela is alloted plot in BKC for hotel
Mumbai: Schloss Bangalore (The Leela) has received MMRDA's allotment for a 2.1 acre commercial plot in Bandra-Kurla Complex (BKC) to set up a 250-room luxury hotel. The consortium backed by Brookfield Asset Management-backed Schloss Bangalore will pay the MMRDA a lease premium of Rs 1,302 crore for the plot. Tired of too many ads? go ad free now The hospitality company owns and operates the Leela Palaces, Hotels and Resorts and plans to develop a mixed-used project including a 250-key luxury hotel in BKC. According to a spokesperson, 25% of the total lease premium is payable within two months of the offer of allotment and the remaining 75% within 10 months thereafter. The possession of the plot will be handed over after payment of the total lease