logo
#

Latest news with #ElcorConstruction

New $21.3 million Link contract approved for $175.5 million rapid-transit project
New $21.3 million Link contract approved for $175.5 million rapid-transit project

Yahoo

time06-05-2025

  • Business
  • Yahoo

New $21.3 million Link contract approved for $175.5 million rapid-transit project

May 5—ROCHESTER — A new construction contract for street-level work along the planned Link Bus Rapid Transit route reduces the project's overall potential cost by $4.4 million, compared to an earlier proposed contract. The Rochester City Council approved a nearly $21.3 million contract on Monday with Rochester-based Elcor Construction for street, sidewalk and landscaping work related to the $175.5 million project. Work covered by the contract is along the planned 2.8-mile route through downtown Rochester, covering Second Street, between Avalon Cove Court Southwest and Third Avenue Southeast, as well as approximately four blocks south on Third Avenue. The contract comes two months after the council rejected an $83 million bid for work that also included the creation of a pedestrian tunnel under Second Street Southwest and connected transit center near Saint Marys Hospital and work on transit stations along the project. Steve Sampson Brown, Rochester's director of construction, reports dividing the project into two contracts led to a lower-than-expected bid for the work approved Monday. "The low bid received is approximately ($4.44 million) under our consultant's estimate," he wrote in a report to the council. The report also estimates the second half of the work from the earlier rejected contract will cost $57.3 million. The contract for that work remains to be seen by the council. Approximately $58 million the project's current $175.5 million budget already spent by March in securing 60-foot electric buses and preparing for construction, according to Sampson Brown. The project is being funded with $84.9 million in approved Federal Transportation Administration funds, with the majority of the remaining cost being covered through state and county Destination Medical Center transit funds. In March, the City Council approved a nearly $7.7 million contract with Elcor Construction for planned development of public spaces and amenities at the West Transit Village. The contract was approximately $1.4 million less than the estimated cost of the work, which includes the creation of a transit center plaza south of Cascade Lake. Work on the overall project is expected to start in mid- to late-June, according to project manager Josh DeFrang. In addition to the planned West Transit Village plaza, the Link project will include stations: * Near the 19th Avenue Southwest intersection of Second Street * Near Saint Marys Hospital * Near the Sixth Avenue Southwest intersection with Second Street * Near the Second Avenue Southwest intersection with Second Street * Near the Mayo Civic Center * Near the intersection of Third Avenue Southeast and Sixth Street. The West Transit Village and Sixth Street Southeast sites will serve as endpoints to the dedicated route, with other stations offering boardings in each direction every 5 minutes during peak periods and every 10 minutes during other times, including weekends. Peak periods are expected to be from 6 a.m. to 9 a .m. and 3 p.m. to 6 p.m. on weekdays, with service operations anticipated from 5 a.m. to midnight on weekdays and 8 a.m. to midnight on weekends. The transit system is expected to be operational in the spring or summer of 2027.

Demolition of Michaels restaurant property to start next week
Demolition of Michaels restaurant property to start next week

Yahoo

time31-01-2025

  • Business
  • Yahoo

Demolition of Michaels restaurant property to start next week

Jan. 31—ROCHESTER — The long-delayed demolition of the former Michaels restaurant site in the heart of downtown Rochester will officially start next week to address safety concerns and as a fulfillment of a pledge by Rochester developer Andy Chafoulias. One southbound lane of Broadway and the sidewalk in front of the property, next to the Galleria at University Square Mall, will be closed for the month of February for Elcor Construction to demolish four of the buildings that once housed the restaurant. The demolition is expected to take a month. The buildings, at 11, 13, 15 and 17 S. Broadway Ave., have stood empty since 2014, when the Pappas family closed the iconic restaurant on New Year's Eve to make way for development. However, development has not progressed as various issues, including conflict with the owners of a small fifth building on the site, have repeatedly delayed it. During that time, the buildings have steadily deteriorated to the point where they are now safety hazards. Rochester Police Chief Jim Franklin said that became a pressing issue last summer, when officers had to enter the buildings to remove trespassers who had sought shelter there. Then-Fire Chief Eric Kerska told Franklin that the buildings were unsafe for anyone to enter. "So we, myself and Chief Kerska, brought our public safety concerns directly to Mr. Chafoulias and said, 'You've got to do something here. This is a hazard for the community.' And to Mr. Chafoulias' credit, he 100% recognized that and was responsive," Franklin said. The smallest structure on the Michaels site, at 9 S. Broadway, stands behind a tower that contains an elevator and stairway for the nearby public parking ramp. That structure is owned by members of the Pappas family, through a company, PRE Holdings. The family and their representative, Tom Hexum, have not yet come to an agreement with Chafoulias. Earlier, in 2022, Chafoulias had started to make preparations to level the site. The work would have included a separate permit to also demolish the Pappas building. But through a letter signed by Don, George and Jim Pappas, the family opted out of that plan. In September 2024, Chafoulias brought development plans for a "Titan Transformational Gateway Project" to the Rochester City Council. At that time, the council approved a two-year exclusive negotiating rights agreement with Chafoulias and his company, Titan Development & Investments. The project Chafoulias presented includes a 14-story building with two floors of retail and three floors for the University of Minnesota Rochester for offices and classrooms on a level connecting to the adjacent Galleria at University Square Mall, where UMR already has space. Chafoulias' development plan further includes eight floors of student housing, plus a skyway connection across Broadway to the Hilton hotel, another property developed by Titan. While those plans are moving forward, Chafoulias still needs agreements with the City of Rochester and the Destination Medical Center Economic Development Agency before he can lock in project financing. If the agreements fail to materialize as hoped, Chafoulias may need to scale down the project. The hope was to have all of the agreements settled before the demolition occurred. However, Chafoulias said he wanted to honor his pledge to the fire and police chiefs that the site would be cleared early in 2025. "I told them that we as a company will not tolerate any buildings being in violation, but I need cooperation from my neighbor, but that didn't happen," said Chafoulias. "Now with the development agreement or not, I will be taking those buildings down because they're dangerous. I don't want to put the fire department or the police department in danger. That is more important to me than having a development agreement. I'm willing to take that financial risk." While the demolition is moving ahead, PRE Holdings and Hexum are renovating their small building into three office spaces. Hexum himself will be a tenant. "It's good that Titan is applying to get a demo permit and is doing its thing," said Hexum earlier this month. "We don't have any new news on ours."

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into the world of global news and events? Download our app today from your preferred app store and start exploring.
app-storeplay-store