logo
#

Latest news with #FiordlandTrailTrust

Legal review delaying Lake2Lake
Legal review delaying Lake2Lake

Otago Daily Times

time02-05-2025

  • Otago Daily Times

Legal review delaying Lake2Lake

It may be some time before any work is done on the extension to the Lake2Lake trail in Southland. The Fiordland Trail Trust said last month it had opted to pause the construction work from Patience Bay to Sinclair Rd as it was waiting for a decision from the Department of Conservation about an amendment for which it applied in December. The trust worked with a specialist herpetologist in October and, during this time, part of the vegetation was also cleared. After finding no evidence of the Southland green skink, which triggered the need for a plan, the trust sought an amendment with Doc to allow construction to the originally consented 3m trail formation, Mr Boniface said last month. "We proceeded to construct from Patience Bay up to Sinclair Rd within the conditions that the wildlife permit set for us and we have got to a point where we have applied for an amendment to those conditions to enable us to build a safe two-way trail," he said. "We have not had that approval. There are some complications around the Wildlife Act being challenged ... and I think our application for the amendment has been caught up in all of that." Department of Conversation Te Anau operations manager John Lucas confirmed the application had been assessed. But a court decision had thrown a spanner in the works. "There is likely to be a delay due to the recent High Court decision requiring a review of Wildlife Act legislation. The Fiordland Trail Trust application to construct a 3m trail on Public Conservation Land requires permission issued under the Wildlife Act for the disturbance/killing of wildlife." The decision referred to a case over Mt Messenger in the North Island. The High Court ruled the Doc permit for the Mt Messenger bypass project, which allowed the killing of protected wildlife, was unlawful. Doc said in a recent statement the decision had implications for other projects that involve potentially incidental killing of wildlife. While the ruling does not require immediate cessation of activities for existing Wildlife Act authorisations, operators must now take all reasonable steps to avoid harming wildlife.— APL

More frustration for trust as trail extension delayed again
More frustration for trust as trail extension delayed again

Otago Daily Times

time22-04-2025

  • General
  • Otago Daily Times

More frustration for trust as trail extension delayed again

The extension of the Lake2Lake Trail has hit another bump but the Fiordland Trail Trust hopes to be back on track by the end of the year. Chairman David Boniface said yesterday the trust opted to pause the construction work from Patience Bay to Sinclair Rd as it was waiting for a decision from the Department of Conservation about an amendment for which it applied in December. In August last year, it "finally" received the green light from Doc to extend the trail after it requested a wildlife permit and a lizard management plan for the area. The trust would also include a modified vegetation clearance method, and ensure the trail formation width was no more than 2.2m. Mr Boniface said the work with a specialist herpetologist started in October and, during this time, part of the vegetation was also cleared. However, after finding no evidence of the Southland green skink, which triggered the need for a plan, the trust sought an amendment with Doc to allow construction to the originally consented 3m trail formation, Mr Boniface said. "We proceeded to construct from Patience Bay up to Sinclair Rd within the conditions that the wildlife permit set for us and we have got to a point where we have applied for an amendment to those conditions to enable us to build a safe two-way trail. "We have not had that approval. There are some complications around the Wildlife Act being challenged ... and I think our application for the amendment has been caught up in all of that." He hoped to have it sorted by spring so the trust could continue to construct the extension which was about 2km long. If the trust gets the approval wanted, it would take about three weeks to a month for the work to be completed, he said. Mr Boniface said the last delay added to several other hicups they had encountered since the original consents and agreements were obtained in mid-2022. 'We've been frustrated from a long way back. "We've had a resource consent in place for — it'll be three years in August and our funders and the trail users in that are pretty concerned by all this. "We've got a lot more we want to get on with and this is delaying us, our progress as a trust." At present, the trail, which cost about $1.8 million to build, is about 35km long. Doc was approached for comment, but was unable to reply to questions by deadline.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into the world of global news and events? Download our app today from your preferred app store and start exploring.
app-storeplay-store