Hale Interchange construction in Milwaukee County to begin week of May 27
Work is scheduled to begin the week of May 27 on a multi-year road construction project through the Hale Interchange in Milwaukee County.
The work will take place along I-41/43/894 between Lincoln Avenue and 84th Street, according to a statement from the Wisconsin Department of Transportation.
The project is expected to cost about $22.3 million.
The work is scheduled to be completed in late 2026.
Work will include:
Resurfacing and patching along the interstate between Lincoln Avenue and 84th Street.
Repairing multiple bridges within the Hale Interchange.
Repairing the parking lot at the Hales Corners Park and Ride.
Replacing guardrails and curb ramps.
Upgrading signals and lights.
Two-way traffic on the interstate will continue during construction, with resurfacing work taking place primarily overnight.
Work on bridges will cause ramp closures for about 45 days:
Starting in mid-summer, the northbound to eastbound system ramp will close.
Starting in late summer, the westbound to southbound system ramp will close.
At night, full closures of the freeway, lanes and ramps are expected.
The Hales Corners Park and Ride lot along with the MCTS Route 55 stop will remain open for partial use.