logo
#

Latest news with #IsaacConstruction

Council Prioritises Fix For ‘Uneven' Rolleston Intersection
Council Prioritises Fix For ‘Uneven' Rolleston Intersection

Scoop

time07-05-2025

  • Automotive
  • Scoop

Council Prioritises Fix For ‘Uneven' Rolleston Intersection

Article – Jonathan Leask – Local Democracy Reporter The new $5.6 million intersection in Rolleston being uneven within a month of being sealed will be fixed by the end of May. The 'uneven' surface of a new $5.6 million intersection in Rolleston will be fixed by the end of May, council says. Levelling work needs to be completed on the major Canterbury intersection, between Levi Road and Masefield Drive. The Selwyn District Council issued a statement on May 6 via social media that it was 'aware of the uneven surface(s) on Levi Road' and that contractors will be working on levelling the surface as soon as they can. Council infrastructure and property executive director Tim Mason said the road was built to design and there are no structural issues. 'The ride quality at the two entrances to the supermarket development along Levi Road that motorists are experiencing is a temporary issue. 'There are no safety concerns relating to this minor issue and currently a 30 km/h temporary speed limit is in place as a precautionary measure.' The issue was identified during the April 4-6 'super weekend' when the contractors, Isaac Construction, worked a straight 84 hours to install the traffic lights and complete the final roading, piping, electrical work, he said. 'Since then, the council, design consultants, and the contractor have been working on the final stage of design for remediation for the ride quality. 'We expect to have this completed by the end of May. 'We are currently working with our contractor and design consultants to prioritise remediation,while also confirming responsibility for costs as part of that process.' This issue was not caused by last week's heavy rain, but the bad weather delayed the remediation work, he said. 'We can confirm that the drainage around the intersection is working effectively and was not impacted by the recent weather event.' The intersection is a main arterial route linking traffic in and out of Rolleston to the Christchurch Southern Motorway. The finishing touches, such as road markings, had been scheduled to be completed by the end of April. However, this was only partially completed due to the bad weather conditions in the last two weeks, Mason said. Isaac Construction have been approached for comment. The intersection upgrade was originally included in the council's 2021–31 long-term plan, ahead of Foodstuffs South Island announcing their development plans. Foodstuffs is building the South Island's largest Pak'nSave, covering 8100 square meters, on the corner of Levi Road and Lincoln Rolleston Road. It is scheduled to open by the end of the year. It's understood that development contributions from the new supermarket will have offset some of the $5.6m cost, as well as a NZ Transport Agency subsidy.

'Not even': New $5.6m Rolleston intersection to be repaired
'Not even': New $5.6m Rolleston intersection to be repaired

1News

time07-05-2025

  • Automotive
  • 1News

'Not even': New $5.6m Rolleston intersection to be repaired

The "uneven" surface of a new $5.6 million intersection in Rolleston will be fixed by the end of May, the council says. Levelling work needed to be completed on the major Canterbury intersection, between Levi Road and Masefield Drive. The Selwyn District Council issued a statement on May 6 via social media that it was "aware of the uneven surface(s) on Levi Road" and that contractors would be working on levelling the surface as soon as they can. Council infrastructure and property executive director Tim Mason said the road was built to design, and there were no structural issues. "The ride quality at the two entrances to the supermarket development along Levi Road that motorists are experiencing is a temporary issue. "There are no safety concerns relating to this minor issue and currently a 30km/h temporary speed limit is in place as a precautionary measure.' The issue was identified during the April 4-6 "super weekend" when the contractors, Isaac Construction, worked a straight 84 hours to install the traffic lights and complete the final roading, piping, electrical work, he said. "Since then, the council, design consultants, and the contractor have been working on the final stage of design for remediation for the ride quality. "We expect to have this completed by the end of May. "We are currently working with our contractor and design consultants to prioritise remediation, while also confirming responsibility for costs as part of that process." This issue was not caused by last week's heavy rain, but the bad weather delayed the remediation work, he said. 'We can confirm that the drainage around the intersection is working effectively and was not impacted by the recent weather event." The intersection is a main arterial route linking traffic in and out of Rolleston to the Christchurch Southern Motorway. The finishing touches, such as road markings, had been scheduled to be completed by the end of April. However, this was only partially completed due to the bad weather conditions in the last two weeks, Mason said. Isaac Construction have been approached for comment. The intersection upgrade was originally included in the council's 2021–31 long-term plan, ahead of Foodstuffs South Island announcing their development plans. Foodstuffs was building the South Island's largest Pak'nSave, covering 8100 square meters, on the corner of Levi Road and Lincoln Rolleston Road. It was scheduled to open by the end of the year. It's understood that development contributions from the new supermarket will have offset some of the $5.6m cost, as well as a NZ Transport Agency subsidy. LDR is local body journalism co-funded by RNZ and NZ On Air

Council Prioritises Fix For ‘Uneven' Rolleston Intersection
Council Prioritises Fix For ‘Uneven' Rolleston Intersection

Scoop

time07-05-2025

  • Automotive
  • Scoop

Council Prioritises Fix For ‘Uneven' Rolleston Intersection

The "uneven" surface of a new $5.6 million intersection in Rolleston will be fixed by the end of May, council says. Levelling work needs to be completed on the major Canterbury intersection, between Levi Road and Masefield Drive. The Selwyn District Council issued a statement on May 6 via social media that it was 'aware of the uneven surface(s) on Levi Road' and that contractors will be working on levelling the surface as soon as they can. Council infrastructure and property executive director Tim Mason said the road was built to design and there are no structural issues. 'The ride quality at the two entrances to the supermarket development along Levi Road that motorists are experiencing is a temporary issue. 'There are no safety concerns relating to this minor issue and currently a 30 km/h temporary speed limit is in place as a precautionary measure.' The issue was identified during the April 4-6 'super weekend' when the contractors, Isaac Construction, worked a straight 84 hours to install the traffic lights and complete the final roading, piping, electrical work, he said. 'Since then, the council, design consultants, and the contractor have been working on the final stage of design for remediation for the ride quality. 'We expect to have this completed by the end of May. 'We are currently working with our contractor and design consultants to prioritise remediation,while also confirming responsibility for costs as part of that process.' This issue was not caused by last week's heavy rain, but the bad weather delayed the remediation work, he said. 'We can confirm that the drainage around the intersection is working effectively and was not impacted by the recent weather event." The intersection is a main arterial route linking traffic in and out of Rolleston to the Christchurch Southern Motorway. The finishing touches, such as road markings, had been scheduled to be completed by the end of April. However, this was only partially completed due to the bad weather conditions in the last two weeks, Mason said. Isaac Construction have been approached for comment. The intersection upgrade was originally included in the council's 2021–31 long-term plan, ahead of Foodstuffs South Island announcing their development plans. Foodstuffs is building the South Island's largest Pak'nSave, covering 8100 square meters, on the corner of Levi Road and Lincoln Rolleston Road. It is scheduled to open by the end of the year. It's understood that development contributions from the new supermarket will have offset some of the $5.6m cost, as well as a NZ Transport Agency subsidy.

$5.6m intersection needs repairs after less than a month
$5.6m intersection needs repairs after less than a month

Otago Daily Times

time07-05-2025

  • Business
  • Otago Daily Times

$5.6m intersection needs repairs after less than a month

A new $5.6m intersection in Rolleston is uneven and needs to be repaired within a month of being sealed. Photo: Supplied A new $5.6m intersection in Rolleston is uneven and needs repair work within a month of being sealed. The major Canterbury intersection between Levi Road and Masefield Drive became fully operational in early April after contractors worked a straight 84 hours to install traffic lights and complete the final roading, piping, electrical work. The Selwyn District Council issued a statement today (May 6) on social media that it was 'aware of the uneven surface(s) on Levi Road'. 'Our contractors will be working on levelling the surface as soon as they can. 'Road marking will be completed as the weather allows it.' The council has been contacted for more details on the situation, including if the issues were caused by last week's heavy rain and who would pay for the remediation works. The intersection is a main arterial route linking traffic in and out of Rolleston to the Christchurch Southern Motorway. Contractor Isaac Construction worked through the weekend of April 4-6 to complete the road works on the intersection. The intersection upgrade was originally included in the council's 2021–31 long-term plan, ahead of Foodstuffs South Island announcing their development plans. Foodstuffs is building the South Island's largest Pak'nSave, covering 8100 square meters, on the corner of Levi Road and Lincoln Rolleston Road. It is scheduled to open by the end of the year. It's understood that development contributions from the new supermarket will have offset some of the $5.6m cost, as well as a NZ Transport Agency subsidy. A new Mitre 10 Mega, planned next to the Pak'nSave, is going through the consenting process. A private plan change request has been submitted to the council to rezone the area from medium-density residential to large-format retail. The council decided last year to combine three different projects, including the widening of Levi Road, the new traffic lights, and the entry points for the new supermarket, to minimise the overall timeframes of the projects. - LDR is local body journalism co-funded by RNZ and NZ On Air.

$5.6m Canterbury intersection 'uneven' within a month
$5.6m Canterbury intersection 'uneven' within a month

Otago Daily Times

time07-05-2025

  • Business
  • Otago Daily Times

$5.6m Canterbury intersection 'uneven' within a month

A new $5.6m intersection in Rolleston is uneven and needs to be repaired within a month of being sealed. Photo: Supplied A new $5.6m intersection in Rolleston is uneven and needs repair work within a month of being sealed. The major Canterbury intersection between Levi Road and Masefield Drive became fully operational in early April after contractors worked a straight 84 hours to install traffic lights and complete the final roading, piping, electrical work. The Selwyn District Council issued a statement today (May 6) on social media that it was 'aware of the uneven surface(s) on Levi Road'. 'Our contractors will be working on levelling the surface as soon as they can. 'Road marking will be completed as the weather allows it.' The council has been contacted for more details on the situation, including if the issues were caused by last week's heavy rain and who would pay for the remediation works. The intersection is a main arterial route linking traffic in and out of Rolleston to the Christchurch Southern Motorway. Contractor Isaac Construction worked through the weekend of April 4-6 to complete the road works on the intersection. The intersection upgrade was originally included in the council's 2021–31 long-term plan, ahead of Foodstuffs South Island announcing their development plans. Foodstuffs is building the South Island's largest Pak'nSave, covering 8100 square meters, on the corner of Levi Road and Lincoln Rolleston Road. It is scheduled to open by the end of the year. It's understood that development contributions from the new supermarket will have offset some of the $5.6m cost, as well as a NZ Transport Agency subsidy. A new Mitre 10 Mega, planned next to the Pak'nSave, is going through the consenting process. A private plan change request has been submitted to the council to rezone the area from medium-density residential to large-format retail. The council decided last year to combine three different projects, including the widening of Levi Road, the new traffic lights, and the entry points for the new supermarket, to minimise the overall timeframes of the projects. - LDR is local body journalism co-funded by RNZ and NZ On Air.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into the world of global news and events? Download our app today from your preferred app store and start exploring.
app-storeplay-store