Udupi-Kasaragod power line project advances
The transmission line has a mandatory clearance of 5.63 meters horizontally and 7.33 meters vertically away from residential structures. For properties already situated within the transmission corridor, UKTL has pledged fair compensation, with assessments underway to address affected landowners equitably in accordance with government guidelines.
UKTL has called on residents planning new constructions in the project area to consult with the company beforehand to ensure compliance with safety regulations and avoid legal issues. The company also emphasised that farmers can continue cultivating crops such as paddy, papaya, mango, pepper, pineapple, and dragon fruit, provided these activities do not disrupt the transmission infrastructure. This approach aims to balance the region's agricultural traditions with the demands of modern energy development.
Significant progress has been achieved, with all 101 tower foundations completed in Kerala and 77 of the 177 planned towers erected in Karnataka.
UKTL's proactive communication seeks to dispel misconceptions, build community trust, and foster collaboration to ensure the project's timely completion while prioritising the safety and well-being of residents.
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


New Indian Express
2 days ago
- New Indian Express
Karnataka stands 2nd in BHASKAR startup registrations, Maharashtra top list
UDUPI: Karnataka has the second-highest number of startup registrations on the Bharat Startup Knowledge Access Registry (BHASKAR) portal, with 20,004 entities registered as of June 30, 2025. Maharashtra tops the list with 33,845 registrations, according to figures tabled in the Rajya Sabha in the ongoing Monsoon of the Parliament. Minister of State for Commerce and Industry Jitin Prasada gave these details in a written reply to a question from Karnataka MP Iranna Kadadi. BHASKAR, under the Startup India programme, is a platform designed to centralise, streamline and enhance collaboration among key stakeholders within the entrepreneurial ecosystem. These include startups, investors, mentors, service providers and government bodies. The initiative is aimed at reinforcing the nation's commitment to the startup movement. Through the BHASKAR portal, each registered entity receives a unique ID, enabling access to peer-to-peer interaction, partnerships, collaborative engagements and integration with microsites for implementing various schemes under Startup India. The state-wise data shows Uttar Pradesh in third place with 19,382 registrations, followed by Delhi (18,972) and Gujarat (17,370). Union Territories such as Lakshadweep (5), Ladakh (25), and Sikkim (22) recorded the lowest numbers.


The Hindu
7 days ago
- The Hindu
Arebetta holds key to launch of Vande Bharat on Bengaluru-Mangaluru route
Indian Railways will be able to operate at least two more pairs of passenger trains upon commissioning of a crossing station at Arebetta on the Sakleshpur-Subrahmanya Road ghat section of the Hassan-Mangaluru railway line. Thus, the South Western Railway (SWR) would be able to operate the much-sought-after Vande Bharat Express between Bengaluru and coastal Karnataka upon commissioning of the crossing station. At present, the ghat section handles eight pairs of trains in a 24-hour window, including five passenger trains: Bengaluru-Kannur Bengaluru-Karwar Bengaluru-Murdeshwar Vijayapura-Mangaluru Central Yeshwantpur-Mangaluru Junction/Karwar Express (day trains) The day services are suspended till November 1 to facilitate railway electrification work on the 55-km ghat section. Sources in SWR told The Hindu that Arebetta, located in between Shiribagilu and Yadakumari, does not have enough length to facilitate crossing of freight trains that require at least 750-metre-long loop line. With the available space, a loop line of about 600 metres could be constructed to cater to coaching trains, sources said. The crossing station is being established in view of the increasing demand to operate more passenger trains, including the Vande Bharat Express, between Bengaluru and the coast, sources said. Who will bear the cost Railway Minister Ashwinin Vaishnaw told the Lok Sabha recently that Hassan-Mangalore Rail Development Corporation (HMRDC) would bear the cost of developing Arebetta Crossing Station. In his reply to an unstarred question by Udupi-Chikkamagalru MP Kota Srinivas Poojary, the Minister said, 'It has been decided to develop Arebetta Railway Station as a Crossing Station.' Mr. Poojary has constantly been following up with the Railway Ministry regarding developing Arebetta station as a Crossing Station to enhance train handling capacity on the ghat section. Railway electrification update Mr. Vaishnaw said railway electrification was complete on the Subrahmanya Road-Shiribagilu (14 km) stretch and Sakleshpur-Donigal (9 km) stretch on the Subrahmaya Road-Sakleshpur ghat section (55 km). Work is underway in the remaining stretch — Shiribagilu-Donigal (32 km). Completion electrification work depends on various factors, including forest clearance, shifting of infringing utilities, statutory clearance by various authorities, geological and topographical conditions of the area.

The Hindu
09-08-2025
- The Hindu
Electricity, a ‘public good', must not be vulnerable to ‘undue political posturing', says Supreme Court
The Supreme Court has expressed a lack of confidence on whether Electricity Regulatory Commissions (ERCs) are living up to the independence and autonomy afforded to them under the law. ERCs have the exclusive authority of tariff determination, play a pivotal role in the promotion of competition, and in ensuring reliable power supply across the country. The court said electricity is a 'public good' and a 'material resource', and is especially vulnerable to 'undue political posturing'. The ERCs were meant to serve as a bastion under the Electricity Act of 2003 to ensure that electricity was sold and distributed for the common good, unruffled by the politics of the day, and uninfluenced by the market forces of demand and supply. In an 82-page judgment, a Bench of Justices P.S. Narasimha and Sandeep Mehta has, however, questioned the very 'functional autonomy' of the ERCs, while drawing attention to the 'manage and manoeuvre' tactics employed to arrive at tariffs by creating regulatory assets 'over and above all permissible limits' prescribed by the electricity laws. A regulatory asset is adopted as a measure by the Regulatory Commissions when the gap between the revenue required by a power distribution company to meet its costs and expenditure, and the actual revenue realised through immediate tariff, is so high that it would not only prejudice the consumer but lead to what is called a 'tariff shock'. The court noted that, in recent times, ERCs have allowed power distribution companies' regulatory assets to balloon for decades without liquidating them, much to the detriment of the public, who have to bear the ultimate burden of paying more for electricity. This is despite the emphasis in the Electricity Act that the tariff fixed by ERCs must progressively reflect the cost of supply of electricity, and reduce cross subsidies. 'This is where the problem lies. Though the Electricity Act envisages functional autonomy for Regulatory Commissions, and the statutory scheme is complete in all respects, the decisions taken by the Commissions, many a time, have not inspired confidence of independence and autonomy. The reasons are not difficult to conceive as there is an issue about the appointment process. The assertion of independence, however, comes through individual volition and that is where the mandate of transparency leads to accountability,' Justice Narasimha, who authored the judgment, pointed out. The Act requires ERCs to work in cohesion with the State to ensure the supply of affordable power to all sections of society, across regions and terrains. 'But the adverse effect of an overbearing regulatory asset extended beyond proportion is an anathema to good governance of the Electricity Act… The regulatory asset cannot be permitted to balloon into such proportions or continue for such periods, year after year, that the governance of the sector is set in peril, affecting the rights of the utilities and at the same time jeopardising the consumer interest, who eventually end up bearing the burden,' the court noted. Issuing a series of directions, the apex court ordered that regulatory assets must not exceed the reasonable percentage as envisaged in the Electricity Rules. Existing regulatory assets must be liquidated in a maximum of seven years from April 1, 2024, and those created in future must be liquidated in three years from April 1, 2024. The court directed ERCs to provide the roadmap for liquidation of regulatory assets in future, and also undertake a strict and intensive audit of the circumstances in which distribution companies have continued without recovery of their regulatory assets.