HART's $968M budget under Honolulu City Council review
HART's budgets, expected to take effect July 1 if adopted, show marked increases to debt service on the project's loans as well as increased labor costs for the over-$10 billion Skyline construction.
They show other higher costs as well.
Rail officials indicate that due to the awarded contract of $1.66 billion for City Center Guideway and Stations, or CCGS, meant to take the rail line to Kakaako by 2031, the project's capital budget is expected to rise from $482.4 million in the current fiscal year to more than $526.9 million for 2026—a 9.2 % increase.
In August, HART awarded the CCGS contract to Los Angeles-based Tutor Perini Corp. to design and build Skyline's last 3-mile segment to Halekauwila Street.
But rail staffers say because of the large contract—about $360 million above original estimates—certain rail-related projects might need to be temporarily deferred.
Don 't miss out on what 's happening !
Stay in touch with breaking news, as it happens, conveniently in your email inbox. It 's FREE !
Email 28141 Sign Up By clicking to sign up, you agree to Star-Advertiser 's and Google 's and. This form is protected by reCAPTCHA.
Still, HART Executive Director and CEO Lori Kahikina told the Council's Budget Committee on Wednesday that Tutor Perini is 'moving quicker than I anticipated.'
'It's a design-build, so I thought they would take about a year alone just to do designs, ' she said. 'You should see columns starting to come up later this year.'
'They are going to start in Iwilei—kind of work out all the kinks and bugs—and they may have a second heading starting in Halekauwila, ' she added.
According to HART's budget information, 2025's total operating budget will rise to $174.7 million—an increase of $36.4 million, or 26.3 %, over the rail agency's current $138.3 million spending plan.
Of that amount, $169.7 million—or 97 %—is composed of debt serv ice expenditures.
That includes $129 million in principal payments on outstanding general obligation bonds—an increase of $40.8 million over the current fiscal year, budget reports indicate.
But the agency notes $40.3 million in interest payments on debt equates to a $4.6 million decrease compared with the current fiscal year.
Conversely, total labor costs are budgeted at $1.5 million—a $368, 153 increase, or 32.4 % higher than the current year.
HART's main funding sources—local taxes and federal funding—total over $1.25 billion for fiscal year 2026, budget plans indicate.
The federal funding source for 2025 totals $125 million, or about 10 % of the project's funding budget, compared with $518.3 million, or about 41 %, derived from local taxes, budget reports state.
Amended in February 2024, the Federal Transit Administration's Full Funding Grant Agreement initially provided $1.55 billion to construct the city's rail project.
Currently, Kahikina noted, $744 million is the amount outstanding from that agreement.
'When we complete City Center's Utilities Relocation package IV—that's the Dillingham corridor—we're eligible to apply for the remaining $125 million, ' she said.
'To date, we have received—in calendar year 2024—$125 million, ' she added. 'And then when we awarded that Tutor Perini contract, that was an additional $250 million, so we received $375 million in calendar year 2024.'
Two more FTA disbursements of $125 million—or $250 million in total—are expected to be gained by HART, she said. Another $119 million—not tied to any project milestones such as stations—also remains.
'So the total outstanding is $369 million, ' Kahikina explained.
Rail construction money is largely gleaned from the state's general excise tax, which is projected to be $371.4 million in 2025 ; transient accommodation tax, estimated at nearly $90 million ; as well as the city's own TAT at $57.2 million, among other sources, according to HART.
A $10 million city subsidy is among other funding sources comprising the remaining amounts.
The proposed operating and capital budgets will fund 72 full-time equivalent positions. As of February, 47 people were employed at the rail agency. It is authorized to have a total of 98 positions, HART reports indicate.
HART also proposes a $793.6 million capital budget for next fiscal year above the current $574 million—a nearly 38.3 % increase.
The capital budget includes future contract awards for Skyline's Pearl Highlands Transit Center as well as an H-2 freeway access ramp.
A planned Waipahu Station makai entrance—originally earmarked for $14 million—is now being proposed at $20 million, the CIP indicates.
At the meeting, Council Chair Tommy Waters queried HART officials on potential impacts—namely involving the Trump administration's freeze on federal funding—that could affect FTA and the city's rail project.
'Have you folks noticed any change in the team that you're working with over at FTA, and do you anticipate any of that occurring ?' Waters asked.
In response, HART Deputy Executive Director and CFO Rick Keene said, 'We haven't heard anything, so we think that's good news.'
'We hope that this next $125 (million ) that's budgeted in fiscal 2025 for the completion of segment two will not come about until the end of the year, ' he said. 'We're hopeful that by then the dust will have settled a little bit.'
Moreover, Keene alluded to talk 'in the media ' about the Republican-controlled Congress' possible defunding of California's long-planned high-speed rail system.
'And out of Washington, to us, there's been clear distinctions made between that situation and our situation. So at this point we haven't heard anything, ' he added. 'If we hear otherwise, we will let everyone know, but right now we still feel confident in the numbers.'
Members of the public also spoke at the budget hearing.
Donald Sakamoto, president of Citizens for a Fair Americans With Disabilities Act Ride, testified that he participated in the Office of the City Auditor's recent report over Honolulu's Skyline rail operations. That audit, in part, asserts Skyline has less than adequate features for the disabled around its stations.
'So I'm worried about construction of phase two and phase three of the rail stations, and the surrounding areas to be more accessible for our ADA persons like myself, who's blind, and others, ' he said, 'especially with the 35th anniversary of the ADA law this July 26, 2025.'
'So I look forward to the report from HART on the projection of their rail station, and the rail project and the ADA accessibility, ' Sakamoto added.
Meanwhile, Kahikina noted city rail's second segment—from the old stadium, past the airport, to Kalihi—will not be open for public service by October, as was stated by the city during a Council budget hearing Monday.
'HART has consistently said we will transfer the assets to (the city Department of Transportation Services ) before the end of the year, ' she said. 'I'm trying to temper expectations with you folks and the public, so we are still saying 'before the end of the year.''
'However, it is prudent for DTS and (city Department of Budget and Fiscal Services ) to budget ' for HART, Kahi kina added. 'The earliest we could possibly open is October, so we should budget for that, but just understand right now it's still the end of the year.'
HART's latest operating and CIP budgets—to be introduced as Bills 26 and 27, respectively—are scheduled to be heard Wednesday as first-reading measures during the full Council's meeting.
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles
Yahoo
3 hours ago
- Yahoo
Canton residents push back against project website
CANTON, Texas (KETK)– Canton residents are speaking out against the new website for the Grand Saline Creek reservoir, voicing their displeasure at the city council meeting on Tuesday. The Canton City Council met Tuesday night in a packed room filled with residents pushing back against the Grand Saline Creek reservoir project. 'If your land was being stolen, would you be upset? I mean, that's exactly what's happening,' Canton resident Donna Greer said. Amazon plans new delivery station in Nacogdoches At the meeting, the Canton City Council announced the launch of the Grand Saline Creek Reservoir website, where people can read about the project, see frequently asked questions, and submit questions. 'It was a last-ditch effort for transparency, of which there has never been any transparency through this whole thing,' Geer said. Residents said they think the information on the site is wrong, claiming it doesn't show the harm it would bring to people. 'My thoughts are it's misrepresented, it's not truthful, and it was put out the day before the big meeting,' Geer said. 'It was a last-ditch effort for transparency, of which there has never been any transparency through this whole thing.' Med truck tire blowout leads to crash, injuring 2 firefighters in Jasper County Van Zandt County resident John Borgstedt said he's surprised the mayor is still pushing this project forward and wants people to know he and others in the community will continue to fight against it. 'Families just want to take their house, 143 families' houses. She wants to take over 5000 something acres, and she says there are no structures that are going to be affected by this,' Borgstedt said Copyright 2025 Nexstar Media, Inc. All rights reserved. This material may not be published, broadcast, rewritten, or redistributed. Solve the daily Crossword


CBS News
4 hours ago
- CBS News
L.A. city leaders declare Valley Plaza shopping center a public nuisance
Los Angeles city leaders on Tuesday declared Valley Plaza, a once-thriving shopping center in the San Fernando Valley, a public nuisance after years of disrepair. The decision was unanimously approved by the city's Board of Commissioners of Building and Safety after they heard remarks from City Councilman Adrin Nazarian, who represents the area. He spoke on Tuesday, stating that the site, located at Laurel Canyon Boulevard and Victory Boulevard, has been a magnet for crime and concern in recent years. "These ruined buildings have cast a pall on the entire community, depressing commerce for our small businesses, degrading the quality of life for an entire neighborhood, and creating a real danger for the community," said a statement from Nazarian's office. "Once this shopping center was a source of pride to our community; now it's become a blight on the neighborhood and a constant danger to the public. The people of North Hollywood have waited too long. Enough is enough." Now that the decision has been approved, the city can demolish all six buildings in the 17-acre plaza, which is still owned by the Charles Company after it changed hands about a decade ago. It has been vacant since, despite requests from city officials to develop the site or sell it. "Under the Charles Company, the properties have decayed to what you see standing behind me," Nazarian said during a news conference outside the property. "They've been vandalized, covered with graffiti, filled with trash, damaged beyond repair." The Valley Plaza opened in 1951 and has housed a series of prominent grocery and retail stores until it became unoccupied. CBS News Los Angeles has reached out to the Charles Company for comment, but has not yet heard back.

Yahoo
8 hours ago
- Yahoo
Rudee Park multi-million redesign gets green light, attracts national interest
VIRGINIA BEACH — The City Council agreed Tuesday to finally move forward with the design plan for Rudee Park and start a capital fundraising campaign for the multi-million project set to transform the south end of the resort area. It was the final approval needed to bring the project to fruition. The council has already set aside $50 million to build the park, with the money coming from a tourism tax fund. But council members hope to offset that cost by obtaining at least $20 million in sponsorships, which could include naming rights on elements of the park or programs and events held there. 'We are getting national sponsors who are very interested in this,' said Vice Mayor Rosemary Wilson, who represents the district. 'The exposure is going to be phenomenal.' Rudee Park will be built on 8 waterfront acres at the southernmost end of the Oceanfront's resort area where city-owned parking lots currently exist. It will feature a walking path on top of the 1st Street jetty, a water plaza and splash pad, a fishing ledge, elevated walkways with an ocean overlook and a grassy sunset lawn cascading toward Rudee Inlet. It's expected to attract more than 3 million people a year, according to the city. The next step — completing construction drawings — will take about a year-and-a-half and cost $4 million, said Michael Kirschman, director of Parks and Recreation. The city has already spent $2.5 million on the park design. The council opted for a new surface parking lot with 360 spaces, instead of a parking garage, which would have cost an additional nearly $30 million. Related Articles Virginia Beach's Rudee Park design features elevated ocean overlooks, jetty walk Meet the influential 20-member board shaping Virginia Beach's resort area Here's a look inside Virginia Beach's new surf park, which opens Saturday Council members had previously asked how the park will affect festival logistics at the Oceanfront. Currently, Rudee Loop is used as a staging area for event equipment. Kirschman said the park can be used as a festival entrance and the new surface parking lot can become an operations area. He also addressed questions raised about flooding in the area. Rudee Loop sits about 4 feet lower than the Boardwalk, which serves as a flood wall. The park design calls for elevating the site to be level with the flood wall, Kirschman said. Also, new plants and trees will reduce the area's impervious surfaces by more than half, which will relieve flooding issues and cool down the space in the summer, he said. 'We really green up the site' Kirschman said. The park is expected to generate $2.5 to $3.5 million in annual revenue from events, sponsorships, retail and rentals. It will cost $2 to $3 million a year to operate and maintain. Part of the city's next steps will be creating a nonprofit organization with a board of directors and an operations team to run the park. 'They would plan the programs,' Kirschman said. 'They run the whole site.' Stacy Parker, 757-222-5125, Solve the daily Crossword