Wastewater treatment project approved to boost sustainability
A project approved by the Executive Committee of the National Economic Council (ECNEC), under the federal Planning and Development Department, for the construction of the Eastern Wastewater Treatment Plant (33 MGD) – Phase I in Faisalabad is expected to have long-term positive impacts on the environment and groundwater sustainability.
Officials say the project, to be established at Chak 244-RB in Faisalabad, includes the construction of a wastewater treatment facility, rehabilitation of a Katcha channel, laying of a trunk sewer from the terminal point of Channel 4 to the plant covering 2.6 kilometres, and the development of a 10.5-kilometre force main to discharge treated water into the Gogera Branch Canal.
With a total estimated cost of Rs53.66 billion, the project is included in the Annual Development Programme 202425 and is being funded through a loan by the Danish government's Danida Sustainable Infrastructure Finance (DSIF).
According to WASA Faisalabad Deputy Managing Director Saqib Raza, the Project Management Unit (PMU) was established in March 2022, and 90 acres of state land were transferred to the Housing and Urban Development Department for the project.
The selection process for a consultant began in February 2022 and was concluded in March 2022 with the appointment of NIRAS, Denmark, as the official project consultant.
WASA Managing Director Amir Aziz said a pre-qualification notice was issued in October 2022, and the process was finalized in December 2022 with two firms being pre-qualified.
Tender documents were issued in February 2023, technical bids opened in July 2023, and financial bids were reviewed in November 2023.
However, the submitted financial bids were higher than the approved loan ceiling, prompting WASA to negotiate a revised scope with the bidder.
The revised plan involved reducing the treatment plant's capacity from 200,000 to 150,000 million gallons per day and shortening the operation and maintenance period from five years to three.
WASA submitted a revised PC-1 in July 2024 through the Housing Department to the Planning and Development Board in Lahore. Following rigorous scrutiny, the Provincial Development Working Party (PDWP) cleared the project on October 2, 2024, and formally approved the revised PC-1 on January 27, 2025.
After months of technical planning and negotiation, the final approval by ECNEC has paved the way for launching the project.
The loan agreement with the Danish government is expected to be signed next week, operationalising a major environmental upgrade, an official said.
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Express Tribune
5 days ago
- Express Tribune
007 First Light revealed: New James Bond game by IO Interactive
Danish studio IO Interactive has confirmed the official title of its long-anticipated James Bond game. Formerly referred to as Project 007, the game is now known as 007: First Light and will be unveiled later this week, ahead of the annual Summer Game Fest. According to the game's official website, 007: First Light will present 'a wholly original Bond origin story,' allowing players to step into the role of the iconic British spy and earn their 00 status. The studio has not disclosed specific platforms for the game, but First Light was briefly teased during April's Nintendo Switch 2 Direct, suggesting the title will appear on Nintendo's upcoming console. IO Interactive, best known for its Hitman series, is crafting the game independently of any existing James Bond films. Chief executive Hakan Abrak confirmed in previous interviews that the studio's iteration of Bond will be unique to its universe and not derived from the portrayals seen in cinema. 'What's exciting about that project is that we actually got to do an original story,' Abrak said. 'It's not a gamification of a movie. It's completely beginning and becoming a story, hopefully for a big trilogy out there in the future.' 007: First Light is set to launch as the opening chapter in a planned trilogy. Its announcement is part of a broader slate of third-party titles revealed for the Nintendo Switch 2, including Final Fantasy VII Remake Intergrade, Street Fighter 6, Yakuza 0: Director's Cut, and FromSoftware's The Duskbloods. Nintendo also confirmed several first-party titles, such as Donkey Kong Bananza, Mario Kart World, and Kirby Air Riders. While IO Interactive has not confirmed whether First Light will feature at Summer Game Fest Live—scheduled for Friday, 6 June—fans are anticipating further details. The showcase is also expected to feature new footage from Hideo Kojima's studio and a mysterious title known only as Ill.


Business Recorder
31-05-2025
- Business Recorder
‘WASA Faisalabad completes arrangements for rainy season'
FAISALABAD: Provincial Parliamentary Secretary for Housing, Urban Development and Public Health Engineering Barrister Sultan Bajwa has said that WASA Faisalabad has completed all arrangements to provide quality drainage services during the rainy season, all machinery is functional while alternative power arrangements have also been made at the disposal station. Talking to media representatives at WASA Head Office along with Managing Director WASA Amir Aziz, he said that Punjab Chief Minister Maryam Nawaz Sharif is focused on providing the best drainage services across Punjab including Faisalabad and under a comprehensive and effective plan, WASA Faisalabad has made a lot of improvements in terms of drainage and water supply service delivery during the last one year and currently WASA Faisalabad is at the top in terms of performance among all WASAs across Punjab. Copyright Business Recorder, 2025


Business Recorder
30-05-2025
- Business Recorder
66 cities of Punjab to be uplifted in new financial year
LAHORE: Under the Chief Minister Cities Development Programme, the Punjab government has decided to launch development schemes in 66 cities of Punjab in the new financial year. Under this programme, all dirt roads will be paved or repaired, along with the construction and repair of connection roads, and a comprehensive sewage system will be introduced. Moreover, disposal stations will be solarised while sewerage problems will be solved by keeping in mind the needs of the population in 2050. In addition to rainwater drainage, storage tanks will also be built, and restoration of parks will also be included in the project. In this connection, the copies of PC-1 have been sent to the relevant municipal bodies. In this regard, Punjab Local Government Minister Zeeshan Rafiq issued instructions while chairing a meeting through a video link on Thursday. Punjab Local Government Secretary Shakeel Ahmed Mian, Additional Secretary Ahmar Kaifi, PMDFC MD and Deputy Commissioners of various districts participated. The Minister directed the concerned deputy commissioners to keep the model of the Lahore Development Programme in mind while working on the development schemes. He clarified that there will be no additional recruitment for the Cities Development Programme except for technical experts, and thus, only the available human resources will be utilised. 'The Punjab Local Government Department will complete this mega project in collaboration with Public Health Engineering,' he added. Rafiq said that in the next phase, 110 more cities will be included in the programme; in every city, all dirt roads will be paved or repaired, along with the construction and repair of connection roads, and a comprehensive sewage system will be introduced. 'In this connection, the copies of PC-1 have been sent to the relevant municipal bodies,' he added. He said the deputy commissioners have also been made members of the steering committee. He observed that in the past, only partial schemes were completed in cities; however, for the first time, an end-to-end solution for sanitation will be provided. He directed that transparency should be taken care of while implementing the project on the timeline. On this occasion, the Secretary said that e-tendering and digital payment methods should be implemented in the programme. He directed that before the construction of the streets, sui gas, electricity companies and cable network institutions should complete their work. 'After the completion of the work,' he warned, 'digging will be prohibited without the NOC of the district administration.' He said the use of safe and durable sewer pipes is the highlight of this program, adding that the benefits of HTP-lined sewer pipes will last for the next 100 years. Copyright Business Recorder, 2025