Juhu Circle flyover will add to our traffic woes: local residents

Juhu Circle flyover will add to our traffic woes: local residents

Hindustan Times29-05-2025
MUMBAI: The ₹630-crore flyover offering a quick zip from C D Barfiwala Lane to the Juhu-Versova Link Road, gliding over Juhu Circle, is a bridge that fits right in with the BMC's grand plan of connecting the high-speed corridors of the Mumbai Coastal Road. Local residents, however, argue that the flyover's approach roads will create bottlenecks for those traversing the roads below.
A long time in the making, the Juhu Circle flyover has gone through many changes of plan. First floated in 2016 to reduce congestion at Juhu Circle, the flyover was meant to go along the pillars of the Metro 2B line at a lower level. But this was scrapped as it was found to be clunky and difficult.
After the next route—through Airports Authority of India land—was also abandoned in 2023 on account of height restrictions, the civic body went back to the original plan of going parallel with Metro 2B. One entry point of the flyover will now begin after Barfiwala Bridge ends near Juhu Galli, and the other one will be on the Juhu-Versova Link Road.
Milaan Vigraham, a resident of the area, said that the roads where the flyover was being built were three-lane roads, with a few encroachments on C D Barfiwala Lane. 'Once the flyover is in the thick of construction, it will occupy two of them, leaving a measly one lane at the approaches for everyone who wants to go anywhere else at the junction,' he said. 'The flyover is only catering to those who want to go from Juhu to Andheri West and WEH, but the junction meets vehicles travelling from Gulmohar Road, NS Road Number 10, and CES Marg. They will all still have to wait for the two signals and also have the flyover's pillars to contend with.'
Vigraham also raised the concern that some trees along the Juhu-Versova Link Road would have to be axed to make space.
Along with architects and urban planners Alan Abraham and Nitin Killawala, the bunch tried to appeal to the BMC to choose an alternative when the work on the bridge was beginning in September-October 2024. 'Why doesn't the BMC work on reducing the signal time first, which would improve the congestion at the junction?' asked Vigraham. Abraham pointed out that the BMC needed to concentrate on the other roads earmarked in the Development Plan 2034, which will add alternatives to the traffic flocking to the circle. Due to scant support from the area's residents, however, their fight fizzled out.
Mahindra Chawla, an architect who uses the road frequently and was part of a campaign that argued for the bridge, said the Juhu Circle junction was terrible. 'The signals there are too long, and then they open for too short a time,' he said. 'Bottlenecks are inevitable in a city so chock-full of traffic but possibly around 80% of the traffic that uses the junction uses it to go to the other suburbs. The locals form possibly 20% of the traffic, so the flyover will be a boon for most.'
An official from the BMC's bridge department, however, said that traffic at the bottlenecks would not be an issue, as the flyover would divert much of the traffic going through Juhu Circle. 'Commuters from Versova and Juhu will reach Andheri and then go on to Gokhale Bridge towards the WEH in 10 minutes flat, way down from the current 45 minutes,' he said. 'The flyover will also have a link later to the Bandra-Versova Sea Link, so people coming from there can reach the WEH easily and quickly.'
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Potholes beat concretisation in Mumbai: 49% of concretisation project complete but potholes rise by 8% over last year
Potholes beat concretisation in Mumbai: 49% of concretisation project complete but potholes rise by 8% over last year

Indian Express

time17 hours ago

  • Indian Express

Potholes beat concretisation in Mumbai: 49% of concretisation project complete but potholes rise by 8% over last year

Even as the Brihanmumbai Municipal Corporation (BMC) achieved 49 per cent completion in its Rs 17,000 crore mega road concretisation drive to make the city pothole free, the potholes not only continue to riddle Mumbai's streets but the total number of potholes and thereby their complaints have, in fact, witnessed an 8 percent rise this year, in comparison to the same period last year. According to officials, this year, 6,758 potholes have been recorded in Mumbai from June until July 18. However, in 2024, 6,231 pothole complaints had been recorded across the city during the same period. Besides this, data shared by BMC shows that between June and mid-July (July 15), while the city had recorded 4,983 potholes in 2024 since June, the number of potholes jumped to 5,138 this year, during the same period. The surge in pothole woes has emerged despite BMC having achieved nearly half its (49 percent) target of the mega road concretisation project, which was launched in 2022 to make Mumbai's roads 'pothole-free'. With monsoon activity gathering pace in June, potholes surface on city roads in what slows down traffic and exposes motorists and pedestrians to potential accidents. In a bid to proactively identify pothole-plagued roads, the civic body also deploys its own engineers to carry out daily inspections across city wards while citizens can also register pothole-related complaints through social media, the civic disaster management number as well as the 'My Pothole Quick Fix' application. According to data furnished by civic officials, this year, at least 6,758 potholes have been identified across Mumbai's roads since June until July 18. Of the total complaints, 3,461 complaints had been flagged through channels like the pothole fixit app, social media, etc, whereas 3,297 were identified by the BMC's own body of engineers. Of the total sports reported, the BMC had resolved and patched as many as 6,213 pits along bad roads until July 18. The ambitious Rs. 17,000 crore project seeks to concretise 700-km of roads across the city, with 320 km (700 roads) pegged to be concretised in phase I and 378 km (1421 roads) proposed to be paved in concrete in phase II. Mumbai has a road network of 2,050 km, of which 1,333 km roads are already concretised. It is the remaining 700-km asphalt and paver block roads that the civic body has taken up for concretisation in a mega drive, with the objective of enhancing connectivity and eliminating potholes. Until the concretisation project work was stalled in May, owing to monsoon onset in June, the BMC said that it already achieved 63 percent of the target in the first phase with 101.67 km of roads (or 343 roads) completely concretised and 101.68 km partially completed. Meanwhile, in the second phase, 36 percent of the target has been achieved until May 31 with 84.33 km of road length concretised in entirety. By contrast, last year until May 31, the civic body had achieved only 26 percent of the concretisation works in phase I while the work on the second phase commenced only in December 2024. However, despite the near doubling in concretised roads in Mumbai (from 26% in May 2025 to 49% this year), the number of potholes have continued to rise in the same period. In 2024, 6,231 pothole complaints had been recorded across Mumbai between June and July 17, of which 6,051 potholes had been fixed by the BMC until that period. 'These are pothole complaints which are recorded by our engineers through inspections, social media and telephone complaints. These potholes are being filled within 24-48 hours. In many cases, when there is heavy rainfall, filling of potholes couldn't be done regularly and we have to wait till rainfall stops,' a civic official had told The Indian Express earlier. When contacted, Abhijit Bangar, Additional Municipal Commissioner (Projects) BMC said, 'While the city had recorded 5,138 potholes till July 15 this year as against 4,983 potholes in 2024 (same period), the quantity of mastic consumed to fill up potholes has seen a sharp decline over the last one year.' The BMC uses mastic to fix the potholes during the monsoon season and an average of 8 – 10 mastic cookers (machines) are deployed across the city daily. According to officials, in 2024, while 25,632 metric tonnes (MT) of mastic was consumed to repair potholes as well as carry out preventative maintenance ahead of monsoon, only 6,548 MT of mastic has been used so far, this year. As per records, until mid-July last year, the city's K/West ward (Andheri) recorded the highest pothole related complaints at 473, followed by G/North (Dadar, Mahim) ward at 217 complaints and P/North (Malad) ward wherein 172 reports emerged. Meanwhile, the maximum complaints were recorded along the Western Express Highway (WEH) and the Eastern Express Highway (EEH), which recorded 2,019 and 1,286 pothole related grievances respectively. Incidentally, this year too, the maximum number of pothole complaints by citizens have been flagged in the K/West ward, encompassing Andheri West, wherein at least 488 citizen complaints have been flagged until Saturday. Meanwhile, records from the pothole grievances live dashboard show that the second highest number of pothole complaints were reported in the areS ward (Bhandup) wherein 453 pothole complaints had been resolved and 235 complaints currently being resolved, until Saturday. Insiders say that ideally, with the rise in concretisation of roads, the overall pothole numbers should reduce. Speaking to The Indian Express, a senior official from BMC said, 'Ideally, as the number of concretised roads increase, the number of potholes should also reduce. At present, most potholes have been reported along roads which are not concretised.' He further said, 'The potholes on these roads are being addressed using mastic asphalt, with no usage of cold mix. For this purpose, we deploy mastic cookers daily and a certain amount of mastic is being laid overnight. However, what we have observed is that despite the number of potholes, the quantity of mastic used is much lower than what had been used last year in the same period. This is an indication of the fact that the potholes are smaller and their severity is much less.' According to the official, along with the reduced usage of mastic, the number of average mastic cookers deployed has also seen a dip. 'While the highest number of mastic cookers deployed in a single day in 2024 stood at 33, so far, the highest number of cookers used in one day stands at 24. Our focus is on proactively identifying these potholes and repairing them at the earliest to prevent them from becoming enlarged and a safety concern,' said the civic officer. This year, the BMC has pressed one road engineer in each of its 227 wards who have been tasked with daily inspections within a 10 – 15 km radius as well as resolving pothole complaints within a period of 24 – 48 hours. For the asphalt and paver-block roads which are yet to be concretised, the civic body has also allocated Rs. 154 crore for repairing potholes.

Mumbai Coastal Road Now Under 24x7 Surveillance With 236 High-Tech CCTVs
Mumbai Coastal Road Now Under 24x7 Surveillance With 236 High-Tech CCTVs

NDTV

time7 days ago

  • NDTV

Mumbai Coastal Road Now Under 24x7 Surveillance With 236 High-Tech CCTVs

Mumbai: The Brihanmumbai Municipal Corporation (BMC) has completed the installation of a comprehensive CCTV surveillance system on the newly opened Mumbai Coastal Road, enhancing safety, monitoring, and traffic regulation on the key arterial route. A total of 236 CCTV cameras with advanced features are now operational across the 10.58-kilometre stretch, from Shamaldas Gandhi Marg (Princess Street flyover) to the Worli end of the Worli-Bandra Sea Link. As part of its smart monitoring system, BMC has deployed four types of CCTV cameras to ensure smooth traffic flow and quick response to any accidents or violations. Key Features of the Surveillance System: Video Incident Detection Cameras (VIDS): 154 cameras are installed at a 50-meter interval inside the twin tunnels to detect accidents, wrong-way driving, and other incidents. Alerts are sent directly to the control room for immediate action. PTZ Surveillance Cameras: 71 Pan-Tilt-Zoom (PTZ) cameras will provide dynamic visual coverage, automatically focusing on incidents detected by the VIDS system. Automatic Traffic Counting Cameras (ATCC): Installed at tunnel entry and exit points, these cameras record the number and types of vehicles using the road. Automatic Number Plate Recognition (ANPR) Cameras: Seven cameras will monitor and capture images of vehicles that exceed speed limits, assisting authorities in enforcement. The BMC said the system will help address frequent complaints about overspeeding, racing, and noise disturbances along the coastal road. The real-time data provided by the cameras is shared with both the municipal administration and the Mumbai Traffic Police for effective traffic management.

54 containers carrying parts for Goregaon Mulund Link Road arrive from Japan
54 containers carrying parts for Goregaon Mulund Link Road arrive from Japan

Indian Express

time19-07-2025

  • Indian Express

54 containers carrying parts for Goregaon Mulund Link Road arrive from Japan

The ambitious Rs 6,500 crore Goregaon Mulund Link Road (GMLR) is set to witness a key threshold as at least 54 trailers comprising parts of the Tunnel Boring Machine (TBM), which will bore the Goregaon-Mulund Link Road (GMLR) project's twin tunnels, have arrived from Japan into Mumbai. With the final consignment of the first TBM slated to arrive by next month the work on the tunnel with a diameter of 14.5 metre will begin. GMLR's twin TBM tunnels will be amongst the widest road tunnel projects undertaken by the Brihanmumbai Municipal Corporation (BMC). Pegged at a cost of nearly Rs. 6500 crore, the GMLR is an ambitious project which aims to alleviate congestion by linking Goregaon in the western suburbs to Mulund in the eastern suburbs. A crucial part of the GMLR project are the 6.65-km long twin tunnels which will start from Film City in the western suburbs and open near Mulund's Amar Junction, which currently houses a huge slum pocket. The GMLR tunnels will surpass the Sanjay Gandhi National Park (SGNP), covering a complex topography of hillocks, forest and farmlands. The twin tunnels will be built using two TBM machines, which will commence boring from the launching shaft in Film City. Abhijit Bangar, Additional Municipal Commissioner (Projects) confirmed with The Indian Express that trailers containing parts of the first TBM machine started arriving from Japan in late March, this year. 'A total of 77 containers carrying parts of the first TBM machine will be arriving in the city. We received the first consignment on March 25. As many as 54 containers have already arrived and the balance of 23 containers will be received in the coming month,' said Bangar. According to officials, the remaining parts of the TBM machine are expected to arrive by August 15. Arriving from Japan, the containers are being unloaded at the JNPT port from where the consignments are being ferried in trailers up to the worksite. The parts of the first TBM will be assembled over a period of four months, after all the containers are received. Gearing up for the process, the civic body is currently undertaking piling works at the Goregaon work site at the launch shaft where the TBM tunnels will be lowered. Meanwhile, the consignments on the second TBM machine is slated to arrive in the city from December 2025. Raking beneath the SNGP, the TBMs are slated to dig a 5.30-kilometre tunnel before finally achieving its breakthrough at Mulund's Amar Nagar Junction, where the other end of the tunnel is proposed to open. Of the total 6.65-km tunnel length, nearly 1.35 km will be made up the approach roads and the box-tunnel, while nearly 5.30 km will comprise the portion dug by the tunnel boring machine.