Chairman WAPDA Naveed Asghar Chaudhry visited the Dasu Hydropower Project today to review construction work at key sites, including the main dam, powerhouse, transformer cavern, and the relocated section of the Karakoram Highway (KKH-1). The GM/PD Dasu Hydropower Project and representatives of the consultants and contractors were also present.
The chairman presided over a progress review meeting at the project office, where the project team briefed him on targets and achievements. Construction is currently underway at 20 different sites and is progressing at a satisfactory pace.
The excavation works on both the right and left abutments of the main dam have been completed. The extended right bypass tunnel and right-side open channel are also complete and ready to divert excess river flow during the high-flow season. Power generation is expected to commence in 2027.

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Express Tribune
9 hours ago
- Express Tribune
Dasu project to start generation in 2027
Listen to article Chairman WAPDA Naveed Asghar Chaudhry visited the Dasu Hydropower Project today to review construction work at key sites, including the main dam, powerhouse, transformer cavern, and the relocated section of the Karakoram Highway (KKH-1). The GM/PD Dasu Hydropower Project and representatives of the consultants and contractors were also present. The chairman presided over a progress review meeting at the project office, where the project team briefed him on targets and achievements. Construction is currently underway at 20 different sites and is progressing at a satisfactory pace. The excavation works on both the right and left abutments of the main dam have been completed. The extended right bypass tunnel and right-side open channel are also complete and ready to divert excess river flow during the high-flow season. Power generation is expected to commence in 2027.


Business Recorder
10 hours ago
- Business Recorder
Dasu hydropower project to start generating power by 2027: Asghar
LAHORE: Chairman WAPDA Naveed Asghar Chaudhry visited Dasu Hydropower Project Tuesday to review construction work on key sites, including the main dam, powerhouse, transformer cavern and the relocated section of the Karakoram Highway (KKH-1). The GM/PD Dasu Hydropower Project and representatives of the Consultants and the Contractors were also present on the occasion. The Chairman also presided over a progress review meeting at the project office. The project management team briefed him about the targets and the achievements on the project. He was briefed that construction work is currently underway on 20 different sites and is progressing at a steady yet satisfactory pace. Referring to the targets achieved so far and the milestones to be achieved in the days to come, it was briefed that the excavation works on both the right and left abutments of the main dam have been completed. The extended right bypass tunnel and the right-side open channel have also been completed and are ready to divert excess river flow during the high-flow season. Excavation of the main dam foundation is continuing and is scheduled for completion by October this year. Placement of Roller Compacted Concrete (RCC) in the main dam is expected to begin in March 2026. The excavation of the underground powerhouse is expected to be completed by February 2026, while the 25-kilometer-long relocated KKH-1-comprising seven tunnels and three bridges - is scheduled for completion by March 2026. Power generation from the project is expected to commence in 2027. Highlighting the strategic importance of Dasu Hydropower Project for Pakistan's energy needs and economic stability, the Chairman urged the Consultants and the Contractors to excel their efforts to meet the project timelines. Emphasizing upon the significance of maintaining the highest construction standards, the Chairman directed the Contractors to adhere to the stipulated quality standards for completion of the project. The 4,320 MW Dasu Hydropower Project is being constructed on the River Indus in Upper Kohistan District of Khyber Pakhtunkhwa with the financial assistance of the World Bank. The project is planned to be completed in two stages. Currently, WAPDA is executing Stage I, which will have an installed capacity of 2,160 MW and generate 12 billion units of clean, green, and affordable electricity annually. Copyright Business Recorder, 2025


Business Recorder
4 days ago
- Business Recorder
Wapda chairman resigns
ISLAMABAD: Chairman WAPDA Lt Gen. Sajjad Ghani (retd) has resigned from his post due to personal reasons Prime Minister Muhammad Shehbaz Sharif has appreciated his services and sent his resignation to the Cabinet Division for approval. Lt Gen Sajjad Ghani (retd) played a key role in the effective running of the national institution and monitoring important projects in the energy sector. The Prime Minister expressed his best wishes for him. His predecessor had also resigned. Copyright Business Recorder, 2025