logo
Taps Run Dry in Top Burundi Cities as Flooding Risk Looms

Taps Run Dry in Top Burundi Cities as Flooding Risk Looms

Bloomberg5 days ago
The water-pipeline system in the biggest cities in Burundi has collapsed, with residents resorting to taking buckets to central pickup points and rivers to obtain the basic commodity.
A national utility piped supplies into homes three times a week in the largest city of Bujumbura and in the capital, Gitega, until June. But higher demand, a network that hasn't seen upgrades since the 1980s and the start of the dry season last month ground this supply to a halt, leaving people scrambling.
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Codelco Collapse Likely Caused by Mining Rather Than Nature
Codelco Collapse Likely Caused by Mining Rather Than Nature

Yahoo

timea day ago

  • Yahoo

Codelco Collapse Likely Caused by Mining Rather Than Nature

(Bloomberg) -- The seismic event that caused a fatal collapse at Codelco's biggest mine in Chile is likely to have been caused by mining activity rather than nature, according to a person with direct knowledge of the matter. All Hail the Humble Speed Hump Three Deaths Reported as NYC Legionnaires' Outbreak Spreads Mayor Asked to Explain $1.4 Billion of Wasted Johannesburg Funds Major Istanbul Projects Are Stalling as City Leaders Sit in Jail Chicago Schools' Bond Penalty Widens as $734 Million Gap Looms The probable scenario being used inside Codelco is that the incident was caused by geological stresses resulting from the project's own extraction processes rather than any naturally occurring shifting of tectonic plates, the person said, asking not to be identified given an investigation is ongoing. El Teniente, one of the world's biggest underground copper mines, has been halted since July 31, when six workers died and nine others were injured following a 4.2-magnitude event that caused part of the operation to collapse. The tremor affected a newly developed area known as Andesita. The accident has rocked the mining industry in Chile, where projects need to be built to withstand frequent and sometimes massive seismic activity. State-owned Codelco has filed a request to restart parts of the mine while it carries out an investigation into the cause of the incident. The scenario that Codelco is leaning toward is one shared by many industry experts. Nicolas Munoz, a copper supply analyst from consultancy CRU, thinks the seismic activity was more likely the result of mining than from natural causes. As the so-called panel-caving method used at El Teniente routinely involves the controlled collapse of depleted areas of the mine, this, combined with simultaneous mining activities in other areas, could have increased stress within the ore-body, said Munoz, who previously worked as an engineering contractor on projects including El Teniente. 'In some cases, parts of the rock cannot accommodate the new stress regime and fail suddenly, releasing stored energy as seismic events,' Munoz said. These so-called rock-bursts are very hard to predict in deep and highly active mines, he said. Other than the nature of the seismic event, a major question is whether it is safe to restart underground mining at El Teniente, which accounts for a quarter of Codelco's copper output. A one-day suspension could bring a loss of about 750 tons copper, or roughly $7.5 million of revenues, according to CRU. As Codelco seeks to restart in unaffected areas, the damage from last week's collapse appears to be greater than first thought. The Public Prosecutor's Office said Thursday that 3,700 meters (12,000 feet) of tunnel were affected — not only in Andesita but also in Recursos Norte, which has been producing for more than five years. That would be five times initial damage calculations provided by Codelco of 700 meters. If Chilean authorities order the mine to remain closed until investigations are complete, the lost production would heap financial pressure on indebted Codelco, which has major spending commitments and faltering output. To restart the mine, Codelco has to satisfy regulators and unions that the whole of the underground operation is stable, not only the affected areas. A comprehensive review of the mine's current plans, particularly the design assumptions and safety criteria applied in all key zones will be needed, Munoz said. In May, seismic activity leading to flooding at Kamoa Kakula — the biggest copper mine in Africa — was also found to be self-induced, according to its operator Ivanhoe Mines Ltd. Ivanhoe plans to stabilize the flooded section of the mine by installing larger structural pillars, while speeding up construction in another section to keep producing copper. But Munoz said this solution is not applicable at El Teniente, which reaches depths of 1,200 meters (3,936 feet) and had seen significant rockfalls in areas like Andesita. The collapse at Andesita — a relatively small section of El Teniente that was originally scheduled to produce 10,000 tons of copper this year — raises the possibility of Codelco changing its mining plan. But there would be many limitations. If the company prioritizes extracting copper from Andes Norte — a section 300 meters below Andesita that's significantly larger and seen as the future of El Teniente — it has the potential to generate 130,000 tons a year when fully ramped up. Blasting began in late May this year and construction is complete, but the panel caving mining method is a limiting factor, according to Munoz. 'While there may be interest in increasing activity at Andes Norte, doing so could be technically challenging,' he said. 'Additionally, Andes Norte is part of the deeper mining levels that have experienced rock bursts in the past, meaning that any effort to accelerate production may be constrained and could introduce additional operational risks.' Munoz concludes that while there may be opportunities to reorganize the mine plan, they seem unlikely to result in substantial production gains in the short term. In the meantime, ore stockpiles feeding El Teniente's converter facility have already run out, with the plant currently on maintenance. El Teniente's output is typically feedstock to make so-called ENM copper, a brand of cathodes eligible for delivery against London Metal Exchange and Chicago Mercantile Exchange contracts. (Adds detail to damage in ninth paragraph.) The Pizza Oven Startup With a Plan to Own Every Piece of the Pie Digital Nomads Are Transforming Medellín's Housing Russia's Secret War and the Plot to Kill a German CEO It's Only a Matter of Time Until Americans Pay for Trump's Tariffs The Game Starts at 8. The Robbery Starts at 8:01 ©2025 Bloomberg L.P.

New waste service helps recycle more than 331 tonnes of food waste
New waste service helps recycle more than 331 tonnes of food waste

Yahoo

time2 days ago

  • Yahoo

New waste service helps recycle more than 331 tonnes of food waste

A new waste and recycling service has helped recycle more than 331 tonnes of food waste. This is enough to fill more than 6,000 sacks. The New Forest District Council initiative has been underway for eight weeks and benefits more than 31,000 residents in the phase one area. The food waste is being turned into fertiliser and renewable energy, reducing incineration waste. Councillor Geoffrey Blunden, portfolio holder for environment and sustainability, said: "This is a big shift in how we manage waste locally, and we're incredibly grateful to everyone in phase one for embracing the changes. "The volume of food waste being recycled already shows the collective impact we can make. "Every peel and plate scrape recycled helps reduce our environmental footprint. "Thank you to our hard-working crews and to the residents who are working with us as we move towards a cleaner, greener New Forest." The new service, which limits the amount of general waste that can be left out in sacks, aims to encourage more recycling and less waste. This also helps make collections safer for crews, keeps streets tidier and helps the council meet upcoming national recycling requirements. The council is actively reviewing routes, adding extra staff and listening to resident feedback to help things settle.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store