Mumbai Coastal Road: BMC to rope in civil engineers from multiple departments to meet manpower demand
'To ensure the project is executed seamlessly, we will be deploying civic officials with civil engineering degrees from various departments, including roads, sewerage, and water supply. These officials will be responsible for supervising the contractors and the day-to-day progress of the job, along with other technicalities,' said a senior BMC official.
The BMC administration has thus mooted the deployment of nearly 200 additional officers to the bridges department, a proposal that is currently awaiting clearance from the municipal commissioner.
Officials said the bridges department does not have adequate manpower for all the projects it is executing.
'At present, there are several other key projects of the bridges department that are ongoing, including Goregaon-Mulund Link Road (GMLR). Besides this, there are several other projects of new bridge construction and maintenance of existing facilities that are in the pipeline. We will need manpower for this also. So we have to bank on other departments for manpower,' an official said.
The first phase of Mumbai Coastal Road, which connects Marine Drive with the Bandra Worli Sea Link, was inaugurated last year. For the construction and maintenance of this 10-km-long phase, civic authorities had constituted a dedicated department. However, the BMC's bridges department is executing the second phase.
Asked why the dedicated department, set up under the supervision of a chief engineer, was not assigned the task of executing the second phase, an official said, 'The department is responsible for the maintenance of the ready phase, and ancillary work like setting up open spaces and creating walkways also remains. Therefore, there will be extra pressure on that department.'
Phase two of the coastal road will have a series of underground tunnels, a cable-stayed bridge, and vehicular interchanges that will improve north-south connectivity.
BMC officials said the civil work for the coastal road would begin by September first week. This includes the mobilisation of machinery as well as setting up casting yards. The boring of twin tunnels that will connect Mindspace at Malad with Charkop is set to begin from early 2027, and the tunnel boring machine is set to arrive early next year, according to the officials.
The proposed second phase of the coastal road has been divided into six different packages. Package A will cover the 4.5 km between Versova and Bangur Nagar (Goregaon), and package B will cover the 1.66 km between Bangur Nagar and Mindspace. The packages C and D will include twin tunnels—3.9 km long—connecting Mindspace with Charkop in Kandivali. Package E will be 3.78 km long, connecting Charkop with Gorai, and package F will cover the 3.69 km between Gorai and Dahisar.
From Dahisar, the civic authorities are constructing an elevated corridor of 5.6 km that will extend till Bhayander in the Mumbai Metropolitan Region (MMR). The coastal road will also provide connectivity with GMLR, an east-west connector being constructed by the Mumbai civic body.
The cost of these two phases, covering 20 km in total, has been pegged at Rs 20,000 crore. The BMC secured environmental clearances for the project last year and started the on-ground work this year.

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Hindustan Times
19 hours ago
- Hindustan Times
BMC demolishes illegal bar, restaurant at Kamala Mills
MUMBAI: The Brihanmumbai Municipal Corporation (BMC) on Tuesday took stringent action against Living Liquidz restaurants located in NRK House, Kamala Mills compound in Lower Parel, by demolishing its unauthorised construction and cancelling both of its restaurant licenses. Living Liquidz had allegedly illegally converted the ground and first floors, originally meant for a tailoring shop and a garment shop, into restaurants with a bar and wine shop and dining area, respectively, as per BMC. Living Liquidz, also known as Mumbai Wines and Traders (P) Ltd, had illegally converted the ground and first floors, originally meant for a tailoring shop and a garment shop, into restaurants with a bar and wine shop and dining area, respectively. This unauthorised change in user, without a change in user permit, led to the BMC's stringent crackdown. Swapnaja Kshirsagar, assistant commissioner, G South Ward, said to HT, 'There were several violations. They were operating beyond the approved plan from the building proposals department and had changed the user. They were operating restaurants too, without a change in user permission.' Following complaints of unauthorised constructions, encroachments, and illegal operation of restaurants, pubs, and bars at the IT Park in the Kamala Mills compound, additional municipal commissioner Ashwini Joshi directed officials to inspect the premises and take action. Accordingly, on July 31, demolition and seizure operations were carried out at Theobroma, McDonald's, Shiv Sagar Hotel, Nano's Café, Starbucks, Bira Taproom, Toast Pasta Bar (Food by Devika), and BKT House in the Kamala Mills premises for unauthorised constructions. Continuing this intensive campaign, the BMC conducted a joint inspection of the Living Liquidz premises on August 4 and 5. During the inspection, officials found that shops on the ground and first floors were illegally transformed into restaurants. The establishment had also violated Floor Space Index (FSI) regulations by covering open spaces and constructing unauthorised roofing on the terrace. They discovered several other construction violations, including illegal wall constructions, unauthorised conversion of a space into a cold storage room, unauthorised alterations in the door structures, and the erection of wooden and glass partitions. Based on this inspection, the BMC issued a stop-work notice to Living Liquidz on Monday and demolished its premises on Tuesday. Furthermore, as the unauthorised commercial expansion was done without a mandatory fire safety certification, thereby posing a threat to public safety, the BMC cancelled its restaurant licenses. Following Joshi's directives, the joint operation was carried out in the presence of Deputy Municipal Commissioner (zone-2) Prashant Sapkale and Kshirsagar. Officials and staff from BMC's health, building and factories, and building proposal departments, as well as from the state excise department, participated in the operation. Similar actions will be taken against irregularities and unauthorised constructions or encroachments found elsewhere, as was done in the Kamala Mills area, to continue the campaign consistently, the BMC stated. Despite several attempts, Living Liquidz remained unavailable for comment.


Time of India
a day ago
- Time of India
BMC razes illegal structures at two Kamala Mills restaurants in Mumbai, cancels licences
M umbai: BMC on Tuesday demolished the unauthorised constructions at two restaurants of Living Liquidz in Kamala Mills compound at Lower Parel, and cancelled both its licences. Civic officials said it had illegally converted a garment store on the ground and first floors into a restaurant-bar and wine shop, and a tailoring shop on the ground floor into another restaurant. Following complaints of unauthorised construction, encroachments, and illegal operation of restaurants, pubs, and bars in the IT Park section of Kamala Mills, additional municipal commissioner Ashwini Joshi directed a site inspection and necessary action. Based on her instructions, on July 31, action, involving demolition and seizure, was carried out at various establishments including Theobroma, McDonald's, Shiv Sagar Hotel, Nano's Café, Starbucks, Bira Taproom, Toast Pasta Bar (Food by Devika), and BKT House. Continuing this drive on Monday and Tuesday, during an inspection at Living Liquidz, it was found that a garment store on the ground and first floors had been converted into a restaurant-bar and wine shop, and a tailoring shop on the ground floor into a restaurant. by Taboola by Taboola Sponsored Links Sponsored Links Promoted Links Promoted Links You May Like Got Lower Back Pain? Try This Food – It Might Soothe the Ache (It's Genius!) Read More Undo Additionally, several violations were found, such as covering open spaces in violation of FSI rules, unauthorised roofing on the terrace, illegally constructed walls, unauthorised conversion of space into cold storage, unauthorised alteration of door structures, and the construction of wooden and glass partitions. You Can Also Check: Mumbai AQI | Weather in Mumbai | Bank Holidays in Mumbai | Public Holidays in Mumbai On Monday, a stop-work notice was issued to Living Liquidz, and on Tuesday, the demolition action was carried out. BMC also cancelled the licences of both restaurants for illegally expanding commercial space and operating in a manner that posed a threat to public safety without obtaining the mandatory fire safety certification. BMC stated that similar action will continue in the future.


News18
a day ago
- News18
Mumbai Coastal Road: Why BMC Wants To Deploy 200 Extra Engineers For Versova-Dahisar Link Road
The 22.9 km Versova-Dahisar Link Road is the second phase of Mumbai's Coastal Road, connecting North Versova all the way to Dahisar Taking note of infrastructure projects such as the Goregaon-Mulund Link Road (GMLR), Madh-Versova bridge and reconstruction of other bridges currently underway, the Brihanmumbai Municipal Corporation (BMC) has proposed deployment of around 200 additional officers to supervise the Versova-Dahisar Link Road (VDLR) project. The proposal is currently awaiting administrative approval from Municipal Commissioner Bhushan Gagrani, the Free Press Journal reported. Acting on the state's orders, the BMC has expedited Phase II of the Mumbai Coastal Road Project (MCRP). The 20-km Versova-Dahisar Link Road (VDLR), costing Rs 16,621 crore, aims to ease traffic congestion. Additionally, a 5.6-km, 45m-wide elevated road from Dahisar to Bhayandar will be built at Rs 3,304 crore. Work begins in August 2025 and is expected to finish by December 2028. The BMC has created a dedicated department for the construction and maintenance of the 10.58 km Phase I of the MCRP, stretching from Marine Drive to the Bandra-Worli Sea Link. The Versova–Dahisar Link Road: Mumbai coastal road phase II The 22.9 km Versova-Dahisar Link Road is the second phase of Mumbai's Coastal Road, connecting North Versova all the way to Dahisar. The BMC has issued work orders for the VDLR under the overall Coastal Road scheme, comprising multiple packages and designed as an extension northward from the existing southern Coastal Road segment toward Bhayander, according to reports. It will be a mix of double elevated roads, roads on stilts, cable-stayed bridge, cut-and-cover tunnels. It will connect to Bandra-Versova Sea Link and Goregaon-Mulund Link Road (GMLR). The MCZMA formally approved the Phase 2 alignment (Versova to Dahisar and further to Bhayander) in September 2024. While CRZ clearance has been secured, construction is pending additional approvals from the MoEFCC, Bombay High Court, forest department, and clearance regarding mangrove diversion. Once completed, the Coastal Road will enable signal-free, controlled connectivity from Nariman Point through Worli, Bandra, Versova, Dahisar, and up to Bhayandar/Virar, dramatically cutting travel times and easing congestion across the Western Suburbs. It is expected to be completed around December 2028. view comments Disclaimer: Comments reflect users' views, not News18's. Please keep discussions respectful and constructive. Abusive, defamatory, or illegal comments will be removed. News18 may disable any comment at its discretion. By posting, you agree to our Terms of Use and Privacy Policy.