Dasu inquiry fails to fix responsibility for soaring cost

Dasu inquiry fails to fix responsibility for soaring cost

Express Tribune13-04-2025

Listen to article
An official inquiry has not fixed the responsibility for an "astronomical increase" of 240% in cost of the Dasu Hydropower project to $6.2 billion on any single entity or individual but pointed figures at Chinese contractors, Wapda and the Planning Commission.
The three-member committee also blamed the local administration of Kohistan district for a delay in land acquisition. It said that the cost was increased by Rs48 billion because of enhanced security arrangements after two deadly attacks on the Chinese contractors. The impact of security arrangement was hardly 3.8% in the total cost escalation.
The report stated that "complex interplay of factors and unforeseen challenges" caused the 10-year delay and Rs1.3 trillion or 240% increase in the Dasu hydropower project cost to Rs1.74 trillion. In dollar terms, the cost was equal to $6.2 billion — an unreasonable price tag for a 2,160 megawatts hydropower project.
The committee said that the Chinese contractor ignored the consultants' instructions, local administration could not timely acquire the land and more importantly Wapda awarded the construction contracts "without ensuring availability of the land required by the contractors, which resulted in delays and idle claims".
The committee failed to fix the responsibility on any of the Wapda chairmen or any senior officer by name despite finding that it awarded contracts without having land in hand.
The Planning Commission has been held responsible for underestimating land acquisition and resettlement problems.
Headed by Planning Minister Ahsan Iqbal, the Central Development Working Party on Friday conditionally recommended the Dasu hydropower project for the approval of the Executive Committee of the National Economic Council.
"It is a considered opinion that the delays in Dasu Hydropower Project (Stage-1) are the result of a complex interplay of factors," reads the findings of the three-member committee.
In December, the government ordered the inquiry to identify the reasons and fix responsibility for inability to complete the project after the first revision made in the cost in 2019.
The inquiry committee was led by civil engineer Ather Hameed. Among the other members was Syed Ayaz Muhammad Haider, director monitoring of the Water Resources Ministry and Imran Najam procurement expert of the ministry.
The inquiry concluded that the construction delays have been compounded by unforeseen significant administrative challenges and procedural bottlenecks in land acquisition, compensation payment and resettlement processes".
Unforeseen technical challenges have further distracted the project implementation schedule. Social issues, including community grievances and resistance, have further slowed progress, according to the committee.
The inquiry committee further stated that the lack of seamless coordination between contractors and consultants, security challenges in the project area and natural causes such as difficult terrain, unforeseen geological conditions and flash floods have added to the delays.
"These issues are interconnected, making it clear that no single stakeholder or entity can be solely held responsible", concluded the inquiry committee.
When contacted, Water Resources Ministry Secretary Syed Ali Murtaza said that the inquiry was conducted by chief engineering adviser, which is an independent entity and is meant for undertaking such inquiries.
The secretary further said that the inquiry committee found out that 85% increase in the cost was because of increase in the prices and the remaining 15% was due to changes in the scope and design of the project.
The inquiry committee stated that the success of the project depends on a collaborative approach that fosters alignment and cooperation among the federal government, the provincial government of Khyber-Pakhtunkhwa, district administration of Kohistan, Wapda, contractors, consultants, and local communities.
The inquiry recommended enhancing stakeholders' coordination, streamlining the compensation and resettlement processes. It also proposed proactively addressing social issues particularly on 132kV transmission line and implementing a robust management strategy to handle technical, social, and security challenges.
But these are the issues that should have been catered for in 2014. The project has already been delayed by 10 years to 2029.
The original PC-I costing Rs486 billion had been approved in 2014 with an aim to generate 2,160MW of electricity and the completion date was 2019. Due to increased land rate, the cost was revised to Rs511 billion in October 2019 and implementation was extended to June 2024.
The main civil work contractor for Stage-I is M/s China Gezhouba Group Company (CGGC) while supervision is provided by a joint venture of M/s Nippon Koei of Japan and M/s Dolsar of Turkey in association with local sub-consultants including M/s DMC, M/s NDC and M/s PEES, according to January 2025 inquiry report.
As of January, the overall physical progress is 23.3% and the financial progress at 23%, states the inquiry report on the second revision. The project is mainly funded by the World Bank, local and foreign commercial banks and through Wapda equity. So far, Rs317 billion have been spent on the project.
The Rs1.73 trillion total cost included Rs479 billion interest on the loans to be taken for the completion of the project.
The World Bank had given $517 million and out of which till December $385 million had been utilized. The Credit Suisse Bank also provided a $350 million loan. The local bank's consortium led by M/s Habib Bank Limited also provided a Rs144 billion loan against the original cost of the project.
The World Bank is also ready to pour in another expensive loan of $1 billion for the project.
Cost escalation break-up
The inquiry report has listed a comparison of increased cost from Rs511 billion to Rs1.73 trillion. The civil works cost increased from Rs224.5 billion to Rs771 billion -a surge of Rs547 billion or 243%. The electrical and mechanical work cost increased from Rs54.3 billion to Rs87.3 billion -an increase of Rs33 billion or 61%.
The social resettlement cost was increased from Rs57.5 billion to Rs140.3 billion — a surge of Rs82 billion or 144%.
The security cost was increased from Rs1.5 billion to Rs50 billion -an increase of Rs48.2 billion or 3136%. The project has faced two suicide attacks resulting into killings of 15 Chinese nationals and four Pakistanis.
The project administration cost was increased from Rs13.5 billion toRs54.4 billion — an increase of Rs41 billion or 304%. The consultancies cost was increased from Rs8.3 billion to Rs56.5 billion — a surge of R48.2 billion or 580%. Since the quantum of the loans jumped, so does the interest cost. The interest cost increased from Rs107 billion to Rs479 billion — an increase of Rs372 billion or 349%.
The contingencies were increased from Rs44 billion to Rs99 billion -an increase of Rs55 billion or 124%.
The inquiry committee said that there was a significant delay in acquisition of land of 9,875 acres. But the land cost impact had already been included in the first revised project, and it is not the reason for the cost escalation in the second revision.
The committee noted that the design of the relocation of 52-kilometre-long Karakoram Highway underwent significant changes due to land acquisition delays and geological conditions. However, the committee did not fix the responsibility for ignoring geological conditions at the time of planning first in 2014 and then in 2019 when the project was revised.
The committee validly identified the security as a reason for the delay but it increased the cost by only Rs48 billion out of the total additional increase in the cost of Rs1.27 trillion.
Fixing Responsibility
The inquiry committee identified lack of coordination between contractor and the engineer. It said that delays occurred due to "the contractor's failure to submit activity plans, frequent disregard for the consultant's instructions, insufficient deployment of resources despite repeated directives and inadequate coordination between the contractor and the engineer".
It further said that the contractor's reports indicated that the resources currently available at each worksite are inadequate to achieve the target completion dates.
The committee said that the district administration was responsible for acquiring the land, which it could not timely acquire. The committee said that the Wapda awarded the contracts without ensuring availability of the land required by the contractors, which resulted in delays and idle claims.
The slow pace of the local area development programme eroded community trust and exacerbated local resistance, reflecting a lapse in Wapda responsibility for effective community agreement.
"Both Wapda and the Planning Commission not only clearly underestimated land acquisition and resettlement but also showed lack of cognitive approach regarding project planning and scheduling without substantial completion of land acquisition and resettlement process".
The inquiry committee said that the Chinese Contractor is also responsible for slow progress in the construction of the dam and powerhouse works due to mobilization of inadequate resources.
The committee said that Dasu Hydropower Consultants ad Design and Supervision Consultants were responsible for "frequent design changes, which highlight shortcomings on the part of the design consultant.
The absence of an approved dedicated PC-I for land acquisition as recommended by the Planning Commission, indicates a policy oversight that has contributed to the project delays.

Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Beijing launches AI ‘RoboBrain' to power next generation of humanoid robots
Beijing launches AI ‘RoboBrain' to power next generation of humanoid robots

Express Tribune

time6 hours ago

  • Express Tribune

Beijing launches AI ‘RoboBrain' to power next generation of humanoid robots

Humanoid robot "Tiangong" participates along with human runners in the E-Town Half Marathon & Humanoid Robot Half Marathon in Beijing, China April, 19 2025. PHOTO: REUTERS Listen to article China has taken a significant step forward in its race to lead global robotics innovation with the unveiling of RoboBrain 2.0 — an open-source artificial intelligence model designed to serve as the cognitive core of humanoid robots. The model was launched on Friday by the Beijing Academy of Artificial Intelligence (BAAI), a leading non-profit research institution, during its annual conference in the Chinese capital. The release marks a milestone in China's efforts to build smarter and more autonomous machines for its fast-growing robotics sector. Described by BAAI director Wang Zhongyuan as the world's most powerful open-source AI model tailored for robotics, RoboBrain 2.0 promises to enhance a robot's spatial perception and task-planning capabilities. Compared to its earlier version introduced just three months ago, the upgraded model is reported to operate 17% faster and with 74% higher accuracy. 'Currently, we are partnering with over 20 leading companies and are open to new collaborations to drive growth in the embodied intelligence industry,' Wang told attendees at the Zhiyuan Institute — BAAI's local moniker. The enhanced spatial intelligence enables robots to more accurately interpret their surroundings and judge distances, while improved planning algorithms allow them to autonomously deconstruct complex tasks into simpler, executable steps. RoboBrain 2.0 is part of BAAI's broader Wujie model suite, which also includes RoboOS 2.0 — a cloud-based distribution platform for robotics AI — and Emu3, a multimodal system capable of processing and generating text, images, and video. The model's launch comes amid intensifying competition in China's robotics landscape. Earlier this year, the Beijing Humanoid Robot Innovation Centre introduced its own general-purpose platform, Hui Si Kai Wu, which it envisions as the Android equivalent for humanoid robots. The centre made headlines in April after its Tien Kung humanoid robot completed a half-marathon in Beijing. BAAI has emerged as a pioneer in open-source large language models and has played a key role in China's generative AI boom. Many of its alumni have gone on to found successful AI start-ups. Despite being added to the US Entity List in March — which restricts access to American technology — the institute continues to push forward, with Wang calling the decision 'a mistake' and lobbying for its reversal. In a show of resilience and ambition, BAAI also announced a new strategic partnership with the Hong Kong Investment Corporation to promote innovation through joint initiatives in talent development, technology exchange, and venture capital. This year's BAAI Conference drew more than 100 global AI researchers and over 200 industry experts, including leaders from major Chinese tech firms such as Baidu, Huawei, and Tencent, alongside robotics-focused start-ups like Unitree Robotics, Zhipu AI, and Shengshu AI. As China accelerates its quest to develop commercially viable humanoid robots, BAAI's open-source approach could help democratise access to high-performing AI systems — and set the foundation for a new generation of intelligent machines.

US, China set for trade talks in London on Monday
US, China set for trade talks in London on Monday

Business Recorder

time9 hours ago

  • Business Recorder

US, China set for trade talks in London on Monday

WASHINGTON: Three of US President Donald Trump's top aides will meet with their Chinese counterparts in London on Monday for talks aimed at resolving a trade dispute between the world's two largest economies that has kept global markets on edge. US Treasury Secretary Scott Bessent, Commerce Secretary Howard Lutnick and Trade Representative Jamieson Greer will represent the United States in the talks, Trump announced in a post on his Truth Social platform without providing further details. China's foreign ministry said on Saturday that vice premier He Lifeng will be in the United Kingdom between June 8 and June 13, adding that the first meeting of the China-US economic and trade consultation mechanism would be held during this visit. 'The meeting should go very well,' Trump wrote. Trump spoke to Chinese President Xi Jinping on Thursday in a rare leader-to-leader call amid weeks of brewing trade tensions and a dispute over critical minerals. Trump says fresh US-China trade talks in London next week Trump and Xi agreed to visit one another and asked their staffs to hold talks in the meantime. Both countries are under pressure to relieve tensions, with the global economy under pressure over Chinese control over the rare earth mineral exports of which it is the dominant producer and investors more broadly anxious about Trump's wider effort to impose tariffs on goods from most US trading partners. China, meanwhile, has seen its own supply of key US imports like chip-design software and nuclear plant parts curtailed. The countries struck a 90-day deal on May 12 in Geneva to roll back some of the triple-digit, tit-for-tat tariffs they had placed on each other since Trump returned to the presidency in January. That preliminary deal sparked a global relief rally in stock markets, and US indexes that had been in or near bear market levels have recouped the lion's share of their losses. The S&P 500 stock index, which at its lowest point in early April was down nearly 18% after Trump unveiled his sweeping 'Liberation Day' tariffs on goods from across the globe, is now only about 2% below its record high from mid-February. The final third of that rally followed the US-China truce struck in Geneva. Trump has repeatedly threatened an array of punitive measures on trading partners, only to revoke some of them at the last minute. The on-again, off-again approach has baffled world leaders and spooked business executives. China sees mineral exports as a source of leverage. Halting those exports could put domestic political pressure on the Republican US president if economic growth sags because companies cannot make mineral-powered products. In recent years, US officials have identified China as its top geopolitical rival and the only country in the world able to challenge the United States economically and militarily.

North Korea hit by major internet outage, likely due to internal cause
North Korea hit by major internet outage, likely due to internal cause

Business Recorder

time16 hours ago

  • Business Recorder

North Korea hit by major internet outage, likely due to internal cause

SEOUL: North Korea's internet was hit by a major outage that lasted several hours on Saturday, knocking off connection to government web sites and official news services online and severing the reclusive country from cyberspace. It was not clear what caused the outage but it may have been internal rather than a cyberattack, as connections via China and Russia were affected, said researchers who monitor North Korea's internet and technology infrastructure. North Korea's main official news services, its Foreign Ministry, and the Air Koryo national airline were among websites inaccessible on Saturday, before they started coming back slowly around midday according to checks by Reuters. North Korea's entire internet infrastructure was not showing up on systems that can monitor internet activities, and email services were also affected, Junade Ali, a U.K.-based researcher who monitors the North Korean internet, said earlier. 'Hard to say if this is intentional or accidental - but seems like this is internal rather than an attack.' North Korea says military ties with Russia to ensure 'peace' Officials at South Korea's cyber terror response centre, a police division that monitors North Korea's cyber activities, could not be reached for comment. Martyn Williams, who specializes in North Korea's technology and infrastructure at the Washington-based Stimson Center, also said the cause appeared to be internal as the Chinese and Russian connections were not working. North Korea has one of the world's most strictly controlled internet systems, including access to any form of online communication. The general public has access only to an intranet set up by the government and that is not connected to the wider global network. An elite few in the government and leadership are allowed open internet access, and government and news websites often serve up propaganda for outside audiences. North Korea has in previous years experienced large internet outages suspected as being caused by cyberattacks. The country operates elite teams of hackers, including a group known as Lazarus run by the government intelligence apparatus, that are blamed for attacks against foreign institutions and companies and more recently for theft and the laundering of cryptocurrencies. North Korea denies involvement in hacking, crypto thefts and other cybercrime.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into the world of global news and events? Download our app today from your preferred app store and start exploring.
app-storeplay-store