Delays in Goa road projects could cost Centre crores
Panaji:
Over the past few years, bridge and road projects worth over Rs 14,000 crore have been funded by the Union ministry of road transport and highways in Goa. However, some of these infrastructure projects could soon cause losses to the ministry running into hundreds of crores.
Contractors of three major projects have already gone in for arbitration in three separate cases, claiming that losses of Rs 300 to Rs 500 crore each have been caused to them due to delay in the projects, sources said.
The contractors have said that the delays in the project execution occurred because Goa govt was unable to complete land acquisition for the road or bridge works within the required time.
'Three separate cases are already in the process of arbitration for road and bridge stretches in Cortalim, Mormugao, and Salcete.
A fourth contractor is also in the process of taking the same route for work carried out in Pernem. The contractors have said that delays in land acquisition and changes to scope of work caused due to protests have caused them losses of around Rs 400 crore each,' said the source.
The contractors have said that their machinery lying idle due to the delay in the works are some of the causes for the losses to them.
'Three of the cases are in advanced stages of arbitration, and if the matter does not go in favour of the govt, then the ministry in two of the cases and Goa govt in one of the cases will have to pay a heavy amount in settlement,' said the source.
by Taboola
by Taboola
Sponsored Links
Sponsored Links
Promoted Links
Promoted Links
You May Like
Don't Bother With An Expensive Will (Do This Instead)
Local Will Finder
Undo
The Arbitration and Conciliation Act, 1996, allows for a streamlined system for resolving disputes outside of traditional court proceedings. 'The Act recognizes the parties' autonomy to determine the procedure for arbitration and conciliation. They agree on the terms and conditions of their dispute resolution process. Each party appoints their own arbitrator and there is a chief arbitrator, who could be a retired judge, etc,' said a source.
He said that although govt has placed its say that the Covid pandemic and other factors outside its control were also causes for the delay, usually these cases do end in the party having to cough up a settlement amount as per the arbitral award.
'As three of the four projects that have gone for arbitration were tendered by the ministry, the ministry will become liable to pay the amount as per the award,' said the source.

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Time of India
17 minutes ago
- Time of India
NDMC plans to replace 6.5k road signage by March 2026
New Delhi: New Delhi Municipal Council will soon start replacing around 6,500 signage installed on its roads. The council has set March 2026 as the deadline to complete the Rs 19-crore project. Tired of too many ads? go ad free now An NDMC official said a tender was invited and some clarifications were sought from an agency. "As soon as clarification is obtained, the task will be awarded, and the process will start on the ground," said the official. Currently, many signage in the NDMC area are painted green, which is meant for highways as per the Indian Road Congress (IRC) guidelines. This leads to confusion and a lack of uniformity. According to the project plan, all signage will be designed through software to ensure uniformity and consistency. A presentation in this regard was made to the lieutenant governor earlier. "The changes are also suggested as many of these signage outlived their life and their reflector system needs renewal," the official said. The executive engineers of the road divisions earlier surveyed the existing signage. It was found that 6,439 signage were installed on roads, service lanes, etc. Further, an additional 80 new signage will be required for schools and 20 more for other places. The matter was discussed with senior NDMC officers, and to minimise the estimated cost, it was decided, among other steps, to utilise the stainless steel frames of existing signage. Currently, due to the involvement of multiple agencies in the management of the national capital, the signboards are also not uniform in shapes and colours. In New Delhi Municipal Council area, which is a smart city, the road signboards are in green in rectangular-triangle shapes and the signage outside buildings are blue in the same shapes. But according to experts, as per the codes of IRC, the signage inside an urban city should be on a blue-coloured background with the writing in white. Most of the agencies in Delhi are still following the rules set during the 2010 Commonwealth Games when most of the city signage were changed.


Time of India
17 minutes ago
- Time of India
Dvpt fee may see up to 20-fold rise
Ahmedabad: Properties are set to get costlier with the Ahmedabad Urban Development Authority (Auda) approving a proposal to hike development charges for new projects in the city. The proposal got the nod at its board meeting on Tuesday, paving the way for a 10-20-fold increase in the charges, which will directly impact the cost of residential, commercial, and other properties. Besides areas under Auda's jurisdiction, the new rates — on getting the state govt's green signal — will also apply in Ahmedabad Municipal Corporation (AMC) limits. Development charges are levied based on the area of land and construction when a building plan is approved in Auda or AMC areas. This hike will push up the cost for builders, and as a result spill on to buyers of properties, including homes. The changes in rates come more than 40 years after the Gujarat Town Planning and Urban Development Act of 1976 came into effect on Feb 1, 1978. Section 99 of this law grants urban development authorities the power to levy development charges on land and constructions within their jurisdiction, with Section 100 listing a provision for determining the maximum charge. by Taboola by Taboola Sponsored Links Sponsored Links Promoted Links Promoted Links You May Like Play Chess on Your PC, Free Play Classic Chess Install Now Undo The 1976 law allowed charging Rs 50,000 per hectare or Rs 5 per sq m for land, and Rs 15 per sq m for construction. However, a govt notification on July 28, 2017, amended the law, allowing a maximum charge of Rs. 100 per square metre and setting the limit to Rs 10 lakh per hectare. On March 8, the next year, Auda proposed doubling the development charges, an idea which the state govt did not approve for five years. Auda however pulled back this proposal after Navsari Urban Development Authority in 2023 implemented revised charges. Auda then came up with updated rates at its board meeting in June 2023. These were finally approved at Tuesday's meeting and will now be sent to the state govt for a final nod. An Auda official speaking anonymously said, "Auda submitted a proposal to increase development charges in 2018, which remained pending with the state govt. It withdrew this proposal in 2023, the year the govt also increased jantri rates, which are likely to come into effect soon. Thus, we decided to revise the 2023 development charges and again submit a new proposal. The new charges determined at the board meeting on June 17 will now be sent to the state govt for approval. This is the first increase in development charges in over 40 years, previously approved by the state govt."


Time of India
17 minutes ago
- Time of India
Nitin Gadkari to inaugurate Ratu road flyover next month: Seth
1 2 Ranchi: The inauguration of the Ratu Road flyover has been postponed to July 3 against its original scheduled launch on June 19 due to unavailability of the Union road transport & highways minister Nitin Gadkari , Ranchi MP and Union minister of state for defence Sanjay Seth announced on Tuesday. The 4.18km long corridor is built by NHAI at a cost of Rs 291 crore. "It links NH- 23 on the Pandra side to NH- 75, with two lanes on one end and four lanes on the other. It includes bulletproof and soundproof barriers throughout, plus extensive plantation along the route," flyover's site manager Anand Kumar said. Once operational, the flyover will end traffic congestions on Ratu road. Politicking over naming the flyover has picked up pace before its launch. The JMM led INDIA bloc and the opposition camp, led by NDA have proposed various names and social and cultural outfits have also joined the bandwagon. While JMM and Congress demanded that the flyover be named after former chief minister Shibu Soren. Likewise, the BJP wants the flyover to renamed after a freedom fighter or legendary national figure. JMM general secretary Vinod Pandey said, "Naming the flyover after Shibu Soren will be a fitting tribute to his struggle for separate Jharkhand. It is the will of the entire state" BJP spokesperson Pratul Shahdeo said, "Flyover should be named after an icon without any tainted past." by Taboola by Taboola Sponsored Links Sponsored Links Promoted Links Promoted Links You May Like Flexible Phone Plans for Small Biz Undo A section of the city's Bengali community demanded that the flyover be named after Dr Shyama Prasad Mukherjee. Their representative Abhijeet Dutta said, "To acknowledge his vision for a unified India, this landmark should carry his name." Kesharwani Vaishya Samaj has demanded the govt to name it after Bishweshwar Prasad Kesari, leader of the Jharkhand movement, educationist and historian while Rashtriya Yuva Shakti, a social outfit, on Tuesday at a press meet urged the govt to name it after martyr Abhishek Kumar Sahu, who sacrificed his life in service of the nation in Leh-Ladakh on Oct 28, 2020.