Massachusetts Wants Clean Energy. Why Is It So Hard to Make It Happen?

Massachusetts Wants Clean Energy. Why Is It So Hard to Make It Happen?

Politico23-02-2025

On a bright, sunny Monday in the summer of 2016, Massachusetts Gov. Charlie Baker sat outside the Bay State's gold-domed statehouse to sign a bill designed to ensure that 'Massachusetts and New England can remain a leader in clean and renewable energy production.' The bill sought to curtail the region's carbon emissions without driving up electricity bills. To that end, the Baker administration was authorized to coordinate the purchase of clean electricity generated from, among other potential sources, wind turbines planned for the shallow water off the state's southern coast and hydropower generated by dammed rivers in Canada. But because Massachusetts did not share a border with Canada, the new hydropower would have to travel through a neighboring state. And that, many quickly realized, would add several complications.
For starters, someone would need to build an enormous transmission line — the functional equivalent of a giant extension cord — from north of the Canadian border, across New York, Vermont, New Hampshire or Maine, and into the power grid serving Massachusetts. After evaluating proposals from a range of companies, Baker's administration decided in 2018 to move forward with a plan to build a 192-mile transmission line south from Canada, through New Hampshire and into Massachusetts. The challenge would be to get the Granite State to agree.
But as details became subject to greater public scrutiny, New Hampshire began to balk. The line was slated to cut through the iconic White Mountain National Forest. Interest groups like the Society for the Protection of New Hampshire Forests began to raise environmental concerns. Residents of the Granite State eventually concluded that their natural landscape was being sacrificed to serve the Bay State's thirst for clean power. Late in 2018, an obscure New Hampshire siting board killed the project by declining to authorize its construction. Massachusetts would have to look elsewhere.
Baker quickly pivoted to see if Maine might step up. Situated right across a long border from New Hampshire, the state that styled itself as America's 'Vacationland' was led at the time by a bombastic Republican who governed in much the same mold as President Donald Trump. Gov. Paul LePage viewed Massachusetts's thirst for Canadian hydropower less as a scourge than as a point of leverage. If the Bay State were willing to pay the cost, he could demand concessions. The line was poised, after all, to be constructed by Mainers. The line's owner would pay Maine in perpetuity to lease the land. Maine might even be able to purchase and divert some of the Canadian power on the cheap. And so LePage was supportive when Central Maine Power, a subsidiary of the Spanish-owned Avangrid, proposed to step in to build a project to be called New England Clean Energy Connect (NECEC).
Slated to cost a mere $950 million — more than half a billion dollars less than the original New Hampshire proposal — NECEC turned out to be more than a big extension cord. Engineers proposed that the new infrastructure also connect to several additional wind farm projects in western Maine. Avangrid, estimating that the new infrastructure would create 1,700 jobs, promised LePage that cheap power imported from Canada could act as a check on rising prices for traditional fuel, taking roughly $40 million off Maine's utility bills. The communities touched by the new lines, Avangrid proposed, would harvest more than $18 million in new local tax revenue. And perhaps best of all, as LePage and Avangrid were keen to remind Mainers, Massachusetts would foot the entire bill. By almost any standard, this was poised to be a bonanza for Vacationland.
But claiming that bonanza would be far from straightforward or simple. As advocates for bringing clean power to Massachusetts would discover over the next decade of court fights, referendums, public relations campaigns, protests, public hearings, impact statements and environmental reviews, the single biggest obstacle to their project was, ironically, a strain of progressivism itself. In short, the progressive instinct to get big things done was running up against an equally progressive instinct to challenge unchecked centralized authority.
Eight decades earlier, when the federal government had established a government-owned utility to power up the Tennessee Valley, public authority figures had been commissioned to make decisions about routes and means without being second-guessed — they enjoyed an enormous berth of discretion. During the 1960s and 1970s, however, reformers had begun questioning the Establishment's wisdom, coming to believe that, in many cases, powerful figures were making wasteful or self-interested decisions.
In the decades that followed, progressives at all levels had embraced a reform agenda designed to open the process to additional scrutiny. Each successive reform was designed to protect vulnerable citizens from the powerful elite. But, as the powerline's backers came to realize, the deluge of checks and balances, when taken together, combined to make it almost impossible to get good projects off the ground as well. And this internal conflict has very quietly but very profoundly over the past several decades crippled the progressive movement from within.
Like their neighbors in New Hampshire, Mainers soon came to worry that they were being 'used' by the Bay State. Environmental groups raised concerns about protecting the North Maine Woods. The new line not only threatened to gash through beautiful woodland, it would cross the Appalachian Trail three separate times. It was slated to run over the region's purported crown jewel, the Kennebec River Gorge. Vacationland was a draw for its natural beauty, and NECEC appeared increasingly like a scourge to the state's tourism industry.
There were financial complications as well. Avangrid was proposing to supply as much as a sixth of Massachusetts' electricity — enough to power 1.2 million homes. That new supply promised to claim market share from the older, dirtier, less efficient power plants that had long served many of the same consumers. The president of a trade group representing the incumbent generation plants complained that his members had invested more than $13 billion in various facilities on the presumption that they would be able to recover those costs over future years of service. And that prompted an archetypical 'politics makes strange bedfellows' moment: Those wanting to preserve the beauty of Maine's North Woods were aligned with advocates wanting to protect the fossil fuel industry.
Initially, NECEC's supporters appeared to have a leg up, having proactively nurtured relationships with the communities slated to host the line. Avangrid's representatives had gone town by town, carefully delineating all the benefits that would accrue to each municipality. Enhanced electricity reliability. Portions of a $50 million fund established to offset electricity bills. Tax revenue to renovate schools, improve roads or cut local levies. Details in hand, town boards in nearly all of the 29 separate communities along the power lines adopted resolutions supporting them. And to some outsiders, that made the venture appear like a slam dunk: If a Trump-like populist like LePage and the host of climate-focused interest groups were both supportive of a proposal that promised to be both a financial boon to Maine and a powerful blow against carbon emissions, could it realistically be defeated?
As it turned out, quite possibly yes.
Once the motley crew of conservationists, not-in-my-backyard localists and entrenched oil, coal and natural gas-burning electricity generators organized themselves, they emerged with a series of well-articulated counterpoints that echoed the same complaints that had scuttled the New Hampshire project. NECEC's development hinged on approvals from a whole range of government bureaucracies. Maine's Public Utilities Commission would have to determine whether there was sufficient demand for the new line. The state's Department of Environmental Protection would have to ensure the wilderness was properly preserved. The Army Corps of Engineers would have to ensure that the project would not unduly impact navigable waterways. Even the Department of State in Washington would have to approve, because the wires crossed an international border. If opponents could get any of these various bureaucracies to reject the project — any single one — they might prevail. The race was on to find a veto.
Admittedly, the line was going to exact real costs. Some portion of Maine's vast wilderness was going to be affected. So, to head off public frustration, Avangrid began making additional concessions.
Executives agreed to invest $22 million in conservation projects to compensate the state's tourism industry. Responding to concerns that the power line would somehow ruin the grand vista of the Kennebec River Gorge, the company abandoned its plan to build the line over the river, promising to bury the wires below — a shift that would cost $37 million. And when opponents began complaining that the package of compensation Maine would receive was paltry compared to what New Hampshire had been promised, Avangrid offered to sweeten the pot even further.
Nevertheless, it wasn't clear that these additional concessions would suffice. And as LePage was set to end his second term, Democratic Attorney General Janet Mills, poised to be installed as his successor, began to criticize the project on the campaign trail. Perhaps this was going to end up going down just like New Hampshire.
As it was, Mills came around after her inauguration. Soon thereafter, her administration negotiated and signed what became known as 'the stipulation,' a new pot sweetener that saw Avangrid agree to invest $140 million in 'rate relief' for ordinary Mainers, with an additional $50 million for low-income families. Avangrid promised also to invest $15 million to subsidize the installation of heat-pump furnaces — alternatives to the gas- and oil-burning boilers common throughout Maine. The company threw in $15 million to enhance the facilities required to accommodate electric cars, like charging stations. And executives agreed to specific concessions targeting the economically strained areas of western Maine touched by the new line. In total, the package came to $258 million — $17 million more than had been offered to New Hampshire. For a state that had long struggled economically, the infusion of capital appeared to represent a true lifeline.
The concessions had a powerful political impact, inducing the Conservation Law Foundation and the Acadia Center, both leading environmental groups, to endorse the venture. It gave Mills cover to come out publicly in support as well, her endorsement helping to convince the state's Public Utility Commission to grant the project a certificate of public convenience and necessity in April. By then it seemed as though the whole thing was settled.
But, again, the notion that Maine was being hoodwinked, as opponents would argue with heightened fervor, proved effective in stirring up public opposition. Various environmental groups and competing energy companies had no incentive to wave the white flag. And so, by some measure, the battle had just begun.
NECEC's detractors came to understand that convincing any government body to exercise a veto would depend primarily on their ability to turn public opinion. So they organized what turned out to be a very sophisticated public relations campaign.
Funded largely by a series of fossil fuel-burning energy companies — Calpine Corporation, Vistra Energy and NextEra Energy among them — local conservation groups served as the mouthpieces for what became known as 'Stop the Corridor.' The coalition published reports detailing the potential impacts of the new transmission line, arguing that it would gash through wetlands, cross streams and bisect globally significant bird-breeding habitats with a clearance 'as wide as the New Jersey Turnpike.' They managed to get Patagonia, the environmentally focused clothing company, to encourage its customers to sign a petition opposing approval. And they paid particular attention to the towns along the corridor, hoping to spark anger among the Mainers most likely to have vistas interrupted by the towers and lines.
This last move was particularly audacious, because many of these same towns had endorsed the project just a few months earlier. Local officials had in many cases spent significant time weighing the pros and cons of Avangrid's proposal, concluding that the localized benefits would outweigh the costs. But now, in the summer of 2019, with many of their constituents and neighbors mobilized by the Stop the Corridor campaign, some changed their minds. Those withdrawals put pressure on the state's Department of Environmental Protection and Land Use Planning Commission to look anew at whether the line violated the state's Natural Resources Protection Act and land use standards.
By the end of 2019, NECEC's opponents had settled on what was essentially a two-pronged strategy. The first centered on the regulatory bodies that would have to issue permits and approvals for the project; Stop the Corridor would aim to compel regulators to question whether approving the project would amount to dereliction of their duty.
The second, however, was further afield and, ironically, a vestige of early progressivism. More than a century earlier, the movement had fought to reform government so that citizens would have a new mechanism for legislating over the heads of captured political machines — reformers being of the mind that robber barons and corporate interests had too powerful a hand among elected officials. Now, NECEC opponents hatched a plan to have the legislature pass a bill giving every bisected community an opportunity to kill the project via local referendum. And while that idea did not ultimately gain a foothold, it laid the seed for another obstructive strategy: upending the project via a statewide referendum.
Stop the Corridor strategists remained hopeful it wouldn't come to that — that regulators would kill NECEC without their having to put the project up for a popular vote. The corporation running a gas-burning plant in Yarmouth, Maine, argued before the Public Utilities Commission that the alternatives to NECEC had not been sufficiently vetted, and that previous reviews had been 'replete with errors.' An ecologist with the Maine Natural Areas Program voiced concerns that the chosen route might impact terrain serving as a home to the small whorled pogonias, orchids considered 'threatened' by the federal government. A member of the state's congressional delegation berated the Army Corps of Engineers for failing to be more transparent about its study of the route.
Eventually it came time for Maine's 10-member Land Use Planning Commission to pass judgment on Avangrid's efforts to avoid spoiling three natural treasures: the Kennebec River Gorge, the Appalachian Trail and the little-known Beattie Pond — an area with just a single seasonal residence, reachable only on foot, 27 miles along a gravel road.
The company's vow to dig below the gorge had eliminated that issue of contention. Commissioners then accepted, however grudgingly, that there was no alternative to crossing the Appalachian Trail. But when it came to Beattie Pond, the commission dead-locked, frustrated that Avangrid had refused to accede to a local property owner's demand that the company pay 50 times market value for land that would reduce sight lines from the pond. After further search, Avangrid discovered a way to snake the wires over a strip of land nearer to the Canadian border owned by Yale University. For the cost of a single dollar (and other considerations kept hidden from the public), Yale granted Avangrid permission to erect towers through its property. And with that, the Land Use Planning Commission certified that the project met Maine's standards.
Approvals in hand, Avangrid began making the investments necessary to break ground. But opponents, still holding the threat of referendum in their back pocket, now endeavored to take the project to court. Several towns along the corridor joined a lawsuit to overturn the Department of Environmental Protection's decision-making process. Multiple environmental groups claimed that the wrong state bureaucracy had granted the project's approval. And NextEra Energy, still operating both an oil-burning power plant in Yarmouth and a nuclear plant nearby in New Hampshire, filed suit claiming that the state's approvals had been granted without substantial evidence. But none of these cases went anywhere. And so, as a last-ditch effort, NECEC's opponents turned to what seemed almost like a nuclear option.
In early 2020, four years after Baker signed that bill to make Massachusetts a leader in clean energy production, opponents submitted a petition with 75,000 signatures in support of holding a referendum to demand that the state's Public Utility Commission withdraw the new line's certificate of public convenience and necessity. Avangrid objected in court, claiming that Maine's constitution did not allow for a public voice to overturn a regulatory decision — that the proposed referendum 'exceed[ed] the scope of the legislative powers reserved to the people' under the state's constitution. In a remarkable turn, the state's Supreme Court ruled that the referendum could not go before the voters. 'What is proposed here is not legislation,' the ruling decreed. 'Directing an agency to reach findings diametrically opposite to those it reached based on extensive adjudicatory hearings and a voluminous evidentiary record, affirmed on appeal, is not 'making' and 'establishing' a law.' It seemed, for a moment, as though Avangrid had finally run the gantlet. But, again, no.
A continuing flurry of abortive legal efforts won opponents extended delays. They argued, for one, that the Army Corps of Engineers had not been sufficiently thorough when evaluating the project's environmental impact. But when these various process-oriented objections faltered, opponents were left to focus again on the public referendum. This time, rather than force a regulatory agency to reverse its own determination, they designed an initiative that would erect new political hurdles. If passed, this second referendum would require any proposed high-power transmission line to earn the support of two-thirds of the state legislature, and would furthermore ban wires through the remote portions of northern Maine. The language was explicitly legislative. And so, when a petition in support of the referendum was submitted with sufficient backing, the new statewide vote was deemed appropriate for the November 2021 ballot. Finally, an advantage for NECEC's detractors.
The battle over what became known as 'Question 1' became an almost all-consuming political affair through 2021, with $70 million spent on campaigns for and against passage. Opponents of the proposition — those campaigning to see the new transmission line through — pulled out all the stops. Governors Mills and Baker, a Maine Democrat and a Massachusetts Republican, respectively, both endorsed NECEC. Biden administration Secretary of Energy Jennifer Granholm made a public pitch for it. Both of the state's major daily papers wrote editorials dismissing the powerline opponents' objections. And the nation's broader clean energy community weighed in, fearful that passage would chill clean energy efforts across the country.
This last part was particularly profound. There were, at that point in 2021, at least 21 high-voltage transmission lines nearing approval throughout the United States — enough to grow solar and wind power by 50 percent. But if regulatory approvals like the one in Maine weren't considered ironclad — if this one project could be overruled post hoc by referenda — lenders might think twice about making loans to companies proposing similar projects elsewhere. Alternatively, to account for the risk, they might raise interest rates, putting promising projects beyond financial reach. And that could set back the transition to green energy by years, if not decades. Those interested in building out the nation's clean energy grid were watching the doings in Vacationland with studied concern.
The project's opponents almost inarguably had the more compelling pitch. As in New Hampshire, resentment toward Massachusetts was woven deep into Maine politics — the supposition was that the Bay State was somehow trying to take advantage of its provincial neighbors. And so, in the end, by a wide margin — with nearly 60 percent in favor — Mainers passed the referendum. Suddenly, and for the first time since the campaign had begun a half decade earlier, opponents of bringing hydro to New England seemed to have the upper hand.
Avangrid quickly filed suit, arguing that the referendum had violated Maine's constitution by reneging on a valid lease. The company's chief executive, noting that Avangrid had already spent $450 million on the project, cleared 80 percent of the right-of-way, and erected more than 120 electrical towers, vowed to complete the project by the end of 2023. But executives nevertheless agreed to halt construction until the litigation played out. Despite Avangrid's contention that they could find an alternative route to avoid the Upper Kennebec Valley, the Department of Environmental Protection suspended the company's license. Opponents were, by this point, elated. It appeared like their Hail Mary strategy had paid off.
The better part of a year later, in August 2022, the Maine Supreme Court weighed in. The justices wanted a lower court to decide whether the work Avangrid had done before their license was suspended was sufficient to protect the endeavor from being upended retroactively by the referendum. The case was tried in April 2023, nearly a year and a half after the opponents' victory at the ballot box. Avangrid's lawyers argued that the company had 'vested rights' to finish the line. The state of Maine, now litigating against a project it had once championed, argued that Avangrid had sped up its construction explicitly to rob Maine voters of the opportunity to work their will. At the end of a seven-day trial, nine jurors took a mere three hours to return with a unanimous verdict: Avangrid, they determined, did in fact have a vested interest in completing the approved route. The company could proceed with NECEC despite the referendum.
By then, however, another problem had emerged. The line, when initially approved, had been slated to cost $950 million — an amount that ratepayers in Massachusetts had agreed to cover. Now, however, Avangrid estimated that inflation and delay had driven the costs up to $1.5 billion. It had by then been seven years since former governor Charlie Baker had signed the climate law promising to finance the project, and Massachusetts was now halfway through the period it had given itself to reduce its carbon emissions to 50 percent below its 1990 levels. It wasn't clear, even then, that this cornerstone of the most ecologically progressive state's plan to address climate change was actually viable.
By the point that NECEC's financing became the subject of renewed debate, the project had been the focus of no fewer than 38 reviews.
The trial in April 2023 had generated two million documents. Vegetation had begun to grow in parts of the corridor that had previously been cleared. And despite all that, not a single watt of additional clean Canadian power had flowed into the American grid. To further cloud the picture, a Connecticut-based company filed suit to stop the project because, in their view, the line was not available for use by other small energy projects. The new governor of Massachusetts wanted to review whether Bay Staters were getting a fair deal. And it was anyone's guess what further obstacles opponents might throw in the project's way. As of last month, little more than a third of the project's construction was complete, and electricity was not slated to flow until 2026 — a full decade after Baker signed the law from the beginning of this story.
NECEC is just one project, running through just one state, tucked into one corner of an enormous country. Its fate, by itself, will not determine whether America can stem the global threat of climate change. But the barriers thwarting construction of this one high-voltage transmission line aren't unique — they were, and are, indicative of a more typical rigmarole. Not all transmission lines are worthwhile. Not all efforts at conservation — of neighborhoods, of forests, of species — are self-interested. Preposterous as some of NECEC's opponents may have been, others presented legitimate concerns. That said, the system's inability to metabolize objections, let alone come to an expeditious decision on whether to build the new line, poses what is perhaps the most important cut against efforts to stem climate change. Even if we have the will to overcome our addiction to fossil fuels, is there actually a way?
From the book WHY NOTHING WORKS: Who Killed Progress—and How to Bring It Back by Marc J.Dunkelman. Copyright © 2025 by Marc J. Dunkelman. Reprinted by permission of Public Affairs, animprint of Basic Books Group, a division of Hachette Book Group, Inc. New York, NY, USA. All rightsreserved.

Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Trump says more troops will be deployed. Where do things stand with California protests?
Trump says more troops will be deployed. Where do things stand with California protests?

Yahoo

time33 minutes ago

  • Yahoo

Trump says more troops will be deployed. Where do things stand with California protests?

Protests in Los Angeles continued to escalate late Monday, after the first contingent of National Guard troops, deployed by President Donald Trump, arrived to the city on Sunday. Late Monday news broke that Trump planned to deploy additional National Guard members to quell violent protests. Images out of L.A. showed scenes of chaos — Waymo self-driving cars lit on fire as masked protesters waved Mexican flags. At least five cars were set ablaze, according to a CBS News report. The Google-owned taxi service said they don't believe protesters intentionally targeted their vehicles but paused its service in the areas where it faced disruption. The LAPD announced they made 50 arrests during the demonstrations over the weekend. As Fox News' Bill Melugin reported, the charges included attempted murder with a Molotov cocktail, and assault with a deadly weapon on an officer. 'Five officers and five LAPD horses have sustained minor injuries, and crowds were using hand held radios to communicate law enforcement movements to each other,' Melugin reported. There was a brief reprieve in the violence early Monday, although city residents continued navigating street and freeway closures amid protests. Among the demonstrators was an interfaith group that sung hymns in front of the police, as CNN showed Monday morning. ICE agents stood behind LAPD officers. Trump announced Saturday night he would deploy 2,000 National Guardsmen to Southern California to protect federal buildings and U.S. Immigration and Customs Enforcement officers who were carrying out raids on migrants in the country illegally. On Monday, the Trump administration moved to also send 700 Marines to quell the protests. The troops were scheduled to arrive over the next 24 hours. 'You watch the same clips I did: cars burning, people rioting, we stopped it,' Trump said, speaking at the White House. 'If we didn't do the job, that place would be burning down just like the houses,' he added, referring to the wildfires in Los Angeles in January. 'I feel we had no choice ... We did the right thing.' While Trump says he felt his administration didn't have a choice and 'did the right thing,' California Democrats argue the president escalated the situation. California Gov. Gavin Newsom, who opposed the deployment of National Guard troops, criticized Trump for sending soldiers to California in a post on X. 'U.S. Marines have served honorably across multiple wars in defense of democracy,' Newsom said. 'They shouldn't be deployed on American soil facing their own countrymen to fulfill the deranged fantasy of a dictatorial President,' he said. 'This is un-American.' Hours later, in a separate post, Newsom said he 'was just informed Trump is deploying another 2,000 Guard troops to L.A.' He claimed the first set of National Guard members Trump sent to California didn't receive food or water and only roughly 300 of them are actively deployed while the rest await their next orders in federal buildings. 'This is Reckless. Pointless. And Disrespectful to our troops,' Newsom added. Newsom urged the Trump White House to rescind the National Guard deployment on Sunday. By Monday, his administration had filed a lawsuit against the federal government. Newsom and California Attorney General Rob Bonta announced they sued the Trump administration for sending the National Guard without the governor's authorization or request during a press conference Monday. 'Donald Trump is creating fear and terror by failing to adhere to the U.S. Constitution and overstepping his authority. This is a manufactured crisis to allow him to take over a state militia, damaging the very foundation of our republic,' said Newsom. 'Every governor, red or blue, should reject this outrageous overreach,' the governor added. According to Bonta, this marks California's 24th lawsuit against the Trump White House over the past four months. Newsom urged Californians to protest peacefully. During Monday's press conference, Bonta also cautioned violent demonstrators against breaking the law to avoid arrests. L.A. Mayor Karen Bass claimed the ICE raids last week and the military presence in the city sparked increased violence over the weekend. 'If you dial back time and go to Friday, if immigration raids had not happened here, we would not have had the disorder that went on last night,' Bass said on CNN's 'The Situation Room.' 'If they see ICE, they go out, and they protest, and so it's just a recipe for pandemonium that is completely unnecessary. Nothing was happening here. Los Angeles was peaceful before Friday.' Vice President J.D. Vance told the governor to do his job. 'That's all we're asking,' he added. Trump patted himself on the back for deploying the National Guard in a post on Truth Social. 'We made a great decision in sending the National Guard to deal with the violent, instigated riots in California,' he said. 'If we had not done so, Los Angeles would have been completely obliterated.' He criticized Newsom and Bass for not accepting the federal government's help nor expressing any gratitude for it. 'Instead, they choose to lie to the People of California and America by saying that we weren't needed, and that these are 'peaceful protests,'' he wrote.

Advocates denounce immigration enforcement raid at Southern New Mexico dairy
Advocates denounce immigration enforcement raid at Southern New Mexico dairy

Yahoo

time33 minutes ago

  • Yahoo

Advocates denounce immigration enforcement raid at Southern New Mexico dairy

Advocates on Monday denounced a recent immigration enforcement raid carried out by Homeland Security Investigations agents that led to the arrests of 11 workers at a southeastern New Mexico dairy farm. María Romano, coordinator of the Lea County office of the New Mexico worker and immigrant rights organization Somos Un Pueblo Unido, said the raid in Lovington — the first of her knowledge in the area — has stoked fear among immigrant communities as tensions surrounding immigration enforcement spike nationwide. "People are sad. They're angry. But more than anything, they're scared," Romano said in an interview in Spanish. In a June 4 post on X, formerly Twitter, the El Paso field office of Homeland Security Investigations — the federal law enforcement agency housed within U.S. Immigration and Customs Enforcement — announced agents had arrested 11 "illegal aliens for violations of fraud & misuse of visas, permits & other documents" during a raid at Outlook Dairy in Lovington. ICE's Facebook page noted the raid in a post Saturday, adding, "Criminal employers who hire illegal workers put other employees and our communities at risk. Plus, they undercut their competition by exploiting illegal alien labor, making it harder for legitimate American businesses to stay afloat." Outlook Dairy manager Isaak Bos declined to comment on the raid when contacted by The New Mexican on Monday. He told the Albuquerque Journal the workers provided false paperwork. Of the 11 people arrested during the raid, Romano said 10 were from Guatemala and one was from Mexico. While she doesn't know where the Guatemalans are currently, she said, she believes the Mexican worker is now back in Mexico. ICE did not immediately respond to The New Mexican's request for more information on the raid, including the location of the 11 people arrested. The Lovington raid and Romano's response to it come amid rising tensions between federal immigration enforcement and immigrant communities across the U.S. Thousands of protesters took to the streets in Los Angeles over the weekend to denounce the Trump administration's immigration crackdown. President Donald Trump deployed hundreds of National Guard troops to quell the demonstrations, while California Gov. Gavin Newsom announced plans to sue the president over the move, calling it an "unmistakable step toward authoritarianism" in a social media post Monday. U.S. Rep. Gabe Vasquez, a Democrat who represents much of the southern half of the state, on Monday advocated for the Trump administration to "reverse course to restore peace" and maintain focus on reforming the "broken" immigration system. "Raiding workplaces, turning federal agents and the military against American citizens, and transforming our streets into war zones is not how we enforce our immigration laws," Vasquez said in a statement. He added, "We need real immigration reform rooted in due process, public safety, and compassion, not inflamed tensions and conflicts in the street.' In response to the Lovington raid, Somos Un Pueblo Unido issued a news release calling on local and state officials to "push for humane immigration laws" while demanding transparency from ICE and protecting "the rights of all New Mexicans, regardless of immigration status." The organization also provides materials and organizes workshops to ensure immigrants know — and know how to exercise — their civil rights. It's something Romano encourages people to do. "We've spent many years telling people: 'Understand your rights. Learn your rights. Even if you're undocumented, you have rights,' " she said. Romano added, "We have to be very well-informed about our rights and avoid any missteps — because we already know where we'll end up."

Pasco graduation disrupted by student yelling ‘should have started with English'
Pasco graduation disrupted by student yelling ‘should have started with English'

Yahoo

timean hour ago

  • Yahoo

Pasco graduation disrupted by student yelling ‘should have started with English'

A Pasco High School graduate and his family will be meeting with administrators this week after he disrupted the school's commencement ceremony with comments that criticized the principal's use of Spanish. As Bulldogs from the class of 2025 were handed their diplomas Saturday at Edgar Brown Memorial Stadium, one student reportedly spoke into a microphone, 'This is America. You should've started with English.' His comments appeared to be in reference to Principal Veronica Machado's welcome speech, which was given first in Spanish and then in English. The school and broader community have a large Spanish-speaking population. More than 80% of the school's population come from Hispanic and Latino backgrounds, and more than half of Pasco residents overall speak a language other than English at home. The district appears to have edited out the student's comments from the livestream on Sunday, and on Monday took the video down to add edits to clarify students' names. The interruption was caught by audience members and has been shared thousands of times across social media. 'We are disappointed and saddened that a Pasco High School student chose to disrupt the graduation ceremony on Saturday, June 7, 2025, by making a personal statement that does not reflect the values of our school district,' Pasco School District administrators said in a statement. 'Before participating in graduation ceremonies, all students are required to sign an agreement to uphold standards of appropriate conduct. The student's decision to move into the personal space of the name readers and speak over their microphone was a clear departure from that agreement and selfishly took attention away from the achievements of all graduates being celebrated. The district will take steps to prevent disruption of speakers on stage at all future events,' the statement continued. An administrator reportedly addressed the disruption on stage and after the ceremony. The district plans to hold a series of meetings and listening sessions this week with students, staff and families who were impacted. While district and school admin plan to meet with the student and his family, it's unclear if he will face any discipline or repercussions. School Board President Amanda Brown said in a statement on her personal social media account that it's important all students and families know they belong in their schools, that their languages and cultures are valued, and that Pasco continues to strive toward an inclusive environment. 'While every student is entitled to their voice and lived experience, I do not condone the manner or message in which this moment unfolded,' Brown said. 'I believe it is important to reaffirm that Pasco is a diverse and inclusive community, and our schools should reflect and celebrate that diversity. Language is a powerful expression of identity, and the use of Spanish during the ceremony was a meaningful way to honor our bilingual students, families and staff,' she continued. The school district is home to the state's largest dual language program, educating more than 2,000 multi-lingual students with instruction in Spanish and Russian in addition to English. The district says this program promotes bilingualism, biliteracy, socio-economic competency and high academic achievement. About 509 students graduated from Pasco High School over the weekend.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into the world of global news and events? Download our app today from your preferred app store and start exploring.
app-storeplay-store