Jun. 8—STERLING — Sterling's Riverfront Commission met Wednesday, June 4, to discuss updates for Sterling's $300 million multiphase Riverfront Reimagined project.
The riverfront park
The multiage, accessible park at the former Northwestern Steel and Wire Mill site represents phase one of the Riverfront Reimagined project. In addition to the park, later phases could include worker apartments, a hotel and events center, and a rooftop bar/restaurant for the four buildings at the Lawrence site. That could be followed by market-rate apartments, a fitness center and yet-to-be-determined uses of the National site.
Phase one includes the construction of a restroom facility, installation of playground equipment and a splash pad, new sewer and water laterals, concrete and brick paver pathways, upgraded lighting, electrical and technology improvements, landscaping, and overall site grading.
Although the city's yet-to-be-named riverfront park and splash pad were originally projected to be finished toward the end of June, Strand Associates project manager Zach Simpson said the last progress meeting with contractors indicated the project was slightly behind schedule.
The delay was mostly due to masonry work, which took longer than expected and required most of the site space.
Despite those delays, Simpson said, contractors are continuing to make progress, the park's shelter is starting to take shape, and most of the underground work is finished. Work on the park's splash pad also is advancing.
"They have two pours to finish up the pad this week, and they have to install the equipment," Simpson said. "I believe the mason work is done now as well. So now that he's going to be departing, they'll be able to focus on the playground and some of the other site work that's north and east of the building, and that'll start to take shape in the next couple of weeks."
The hope is that the site improvements to the park will be finished by early July, followed by the shelter in late August or early September.
"If they can get in there in the next week or two, I don't think that's a huge lift for them to install," Simpson said. "The equipment's here in storage. It's just a matter of getting some of the concrete ribbon curbs in and the base down for that stuff, and it should go pretty quick."
Phases two and three have been consolidated to include the completion of the amphitheater, an ice skating ribbon and parking lots at an expected cost of $4 million.
Barring any unexpected delays, Simpson expects the $655,000 ice ribbon likely will be constructed first this fall. The parking lot will follow in the spring, with the amphitheater construction planned for late spring or possibly into the summer or fall.
The Sterling Riverfront Foundation has been seeking investors to help fund the riverfront project. Sterling Alderman Josh Johnson said the Riverfront Foundation has received about $2.8 million in pledged donations, with $1.1 million in donations in the bank. This leaves a $3 million funding gap for phase two.
To address the issue, the city and the Riverfront Commission are considering separating the ice ribbon from phase two so that the money they already have could be used for its construction this year to avoid delays. If they choose to pursue this option, it will require the Sterling City Council's approval.
Lawrence building improvements
Improvements to the Lawrence Bros. building — such as new lighting and window banners — have been on hold while the city awaits bids for the environmental abatement work at the former Lawrence and National companies' sites. The work includes mitigating soil contamination; diminishing asbestos; and removing lead-based paint, contaminated concrete and hazardous materials in preparation for redevelopment.
Ron Clewer of developer Gorman & Co. said those bids came back "significantly" higher than expected.
"Two reasons for that," Clewer said. "One was the timing of the bids, and right now, there's a great deal of work being done because a lot of schools get done over the summer. So, some bidders didn't bid, and the two that did may have considered their capacity."
Clewer said the city, Gorman and the city's qualified environmental consultant, Fehr Graham Engineering & Environmental, advised reissuing those bids after school resumes in August, when companies have fewer projects to choose from and are likely to submit lower bids.
"If we use the bids we have, then the money we saved on other work, including the roof on the National, would have to be put toward the environmental work, which basically would have ate up the budget for lighting and banners anyway," Clewer said. "The goal is to get more respondents, lower the bid prices and not have to absorb the overage in the budget."
Fehr Graham's Ross Grimes suggested that the environmental work would have better pricing, timing and more vendors bidding if the work was reconfigured into smaller, individual projects.

Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Sterling holds its own against stronger dollar, trade optimism lends supports
Sterling holds its own against stronger dollar, trade optimism lends supports

Yahoo

time15 hours ago

  • Yahoo

Sterling holds its own against stronger dollar, trade optimism lends supports

By Lucy Raitano and Johann M Cherian LONDON (Reuters) -Sterling ticked higher against the dollar on Thursday, one of the few major currencies to hold its own against the greenback which regained ground after weak U.S. data dragged it lower on Wednesday. The pound was up 0.14% at $1.3574, while against the euro it was up 0.1% at 84.16 pence. Sterling remains a touch away from a more than three-year high hit on May 26, underpinned by ongoing dollar weakness with the pound up over 8% this year. Also helping is the fact the UK is the only country to have struck a trade deal with the U.S and was spared from higher U.S. steel and aluminium tariffs, though analysts question how beneficial those factors are. "The trade deal does matter," said Chris Beauchamp, chief market analyst at IG Group. "You might argue it's not a proper trade deal and that it doesn't solve all the problems, but at least it's a sign that there's a more compelling reason to hold the pound rather than be worrying about the euro," Beauchamp added. The Bank of England (BoE) will meet on June 19 to deliver its next policy decision with market bets firmly on the monetary policy committee (MPC) keeping rates steady. There had been expectations of a further 25 bps cut from the BoE at its June meeting but bets were slashed following weak economic data and a hotter-than-expected inflation read last month. On Tuesday, Bank of England Governor Andrew Bailey said he was sticking with a "gradual and careful" approach to cutting interest rates as global trade policy turmoil increasingly clouds the outlook. Reassurance came on Wednesday with a survey showing Britain's services sector returned to tepid growth last month. Error in retrieving data Sign in to access your portfolio Error in retrieving data Error in retrieving data Error in retrieving data Error in retrieving data

Updated completion dates predicted for Sterling's riverfront redevelopment
Updated completion dates predicted for Sterling's riverfront redevelopment

Yahoo

timea day ago

  • Yahoo

Updated completion dates predicted for Sterling's riverfront redevelopment

Jun. 8—STERLING — Sterling's Riverfront Commission met Wednesday, June 4, to discuss updates for Sterling's $300 million multiphase Riverfront Reimagined project. The riverfront park The multiage, accessible park at the former Northwestern Steel and Wire Mill site represents phase one of the Riverfront Reimagined project. In addition to the park, later phases could include worker apartments, a hotel and events center, and a rooftop bar/restaurant for the four buildings at the Lawrence site. That could be followed by market-rate apartments, a fitness center and yet-to-be-determined uses of the National site. Phase one includes the construction of a restroom facility, installation of playground equipment and a splash pad, new sewer and water laterals, concrete and brick paver pathways, upgraded lighting, electrical and technology improvements, landscaping, and overall site grading. Although the city's yet-to-be-named riverfront park and splash pad were originally projected to be finished toward the end of June, Strand Associates project manager Zach Simpson said the last progress meeting with contractors indicated the project was slightly behind schedule. The delay was mostly due to masonry work, which took longer than expected and required most of the site space. Despite those delays, Simpson said, contractors are continuing to make progress, the park's shelter is starting to take shape, and most of the underground work is finished. Work on the park's splash pad also is advancing. "They have two pours to finish up the pad this week, and they have to install the equipment," Simpson said. "I believe the mason work is done now as well. So now that he's going to be departing, they'll be able to focus on the playground and some of the other site work that's north and east of the building, and that'll start to take shape in the next couple of weeks." The hope is that the site improvements to the park will be finished by early July, followed by the shelter in late August or early September. "If they can get in there in the next week or two, I don't think that's a huge lift for them to install," Simpson said. "The equipment's here in storage. It's just a matter of getting some of the concrete ribbon curbs in and the base down for that stuff, and it should go pretty quick." Phases two and three have been consolidated to include the completion of the amphitheater, an ice skating ribbon and parking lots at an expected cost of $4 million. Barring any unexpected delays, Simpson expects the $655,000 ice ribbon likely will be constructed first this fall. The parking lot will follow in the spring, with the amphitheater construction planned for late spring or possibly into the summer or fall. The Sterling Riverfront Foundation has been seeking investors to help fund the riverfront project. Sterling Alderman Josh Johnson said the Riverfront Foundation has received about $2.8 million in pledged donations, with $1.1 million in donations in the bank. This leaves a $3 million funding gap for phase two. To address the issue, the city and the Riverfront Commission are considering separating the ice ribbon from phase two so that the money they already have could be used for its construction this year to avoid delays. If they choose to pursue this option, it will require the Sterling City Council's approval. Lawrence building improvements Improvements to the Lawrence Bros. building — such as new lighting and window banners — have been on hold while the city awaits bids for the environmental abatement work at the former Lawrence and National companies' sites. The work includes mitigating soil contamination; diminishing asbestos; and removing lead-based paint, contaminated concrete and hazardous materials in preparation for redevelopment. Ron Clewer of developer Gorman & Co. said those bids came back "significantly" higher than expected. "Two reasons for that," Clewer said. "One was the timing of the bids, and right now, there's a great deal of work being done because a lot of schools get done over the summer. So, some bidders didn't bid, and the two that did may have considered their capacity." Clewer said the city, Gorman and the city's qualified environmental consultant, Fehr Graham Engineering & Environmental, advised reissuing those bids after school resumes in August, when companies have fewer projects to choose from and are likely to submit lower bids. "If we use the bids we have, then the money we saved on other work, including the roof on the National, would have to be put toward the environmental work, which basically would have ate up the budget for lighting and banners anyway," Clewer said. "The goal is to get more respondents, lower the bid prices and not have to absorb the overage in the budget." Fehr Graham's Ross Grimes suggested that the environmental work would have better pricing, timing and more vendors bidding if the work was reconfigured into smaller, individual projects.

BP Marsh offloads Sterling to Australia's ATC Insurance
BP Marsh offloads Sterling to Australia's ATC Insurance

Yahoo

time3 days ago

  • Yahoo

BP Marsh offloads Sterling to Australia's ATC Insurance

BP Marsh, the UK-based specialist investor, has divested its approximately 20% stake in Sterling Insurance to ATC Insurance Solutions, an Australian underwriting agency in which BP Marsh already has a 25% holding. The transaction saw ATC acquire 100% of Sterling's issued share capital for a total consideration of A$33.2m, through a combination of cash and equity. BP Marsh's portion of the deal, corresponding to its 20% interest in Sterling, will be settled via equity in ATC valued at around A$6.5m. This increases BP Marsh's stake in ATC from 25% to 27%. BP Marsh initially invested approximately £1.9m in Sterling in 2013. The investment generated an internal rate of return of 8.8% over a 12-year period. The firm expects further value growth through its increased holding in ATC. As part of the transaction, Dan Topping has stepped down from his position as nominee director on Sterling's board, while retaining his board role at ATC. BP Marsh stated that the transaction is aimed at facilitating a combination of its two investee companies, allowing Sterling's senior management to roll equity into ATC and providing liquidity to long-term shareholders of Sterling. ATC chairman and managing director Chris Anderson stated: "Sterling is highly respected within its sector, with a strong focus on niche, hard-to-place and complex risks. We are thrilled to welcome Sterling to the ATC family and look forward to working closely with their team as we continue to grow together." Sterling Chairman Tony Parington said: "We are excited to be joining forces with ATC and look forward to contributing to the success of the combined business. "Our partnership with BP Marsh since 2013 has been productive, and we are pleased that this relationship will continue as part of ATC." "BP Marsh offloads Sterling to Australia's ATC Insurance " was originally created and published by Life Insurance International, a GlobalData owned brand. The information on this site has been included in good faith for general informational purposes only. It is not intended to amount to advice on which you should rely, and we give no representation, warranty or guarantee, whether express or implied as to its accuracy or completeness. You must obtain professional or specialist advice before taking, or refraining from, any action on the basis of the content on our site. Error in retrieving data Sign in to access your portfolio Error in retrieving data Error in retrieving data Error in retrieving data Error in retrieving data

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into the world of global news and events? Download our app today from your preferred app store and start exploring.
app-storeplay-store