Long Eaton regeneration projects face further delays

Long Eaton regeneration projects face further delays

BBC News2 days ago

Several multimillion-pound regeneration projects in Long Eaton have been delayed by several months.Erewash Borough Council was given £25m of government funding to rejuvenate the town more than five years ago.However, all but one of the projects are still in their pre-construction phases.Funding for all of the schemes in the Town Deal must be spent by March 2026 or it faces being pulled back by central government. They must be completed in full by March 2027.
A meeting of the Long Eaton Town Board heard that construction of the listed building next to Long Eaton Town Hall has been extended by four months because of defective designs, with completion now set for August rather than April.The Stable Block building is set to become a modern working hub with new office and workshop space.
The Britannia Mills Bridge, which will form part of an improved pedestrian and cycling network, now faces a six-month delay and will begin in September this year, with completion set for March 2026.
Starting works at Broad Street Bridge, connecting West Park with the town centre over Erewash Canal, also faces delays. Work was originally mooted to begin in January but has been delayed again from July to August while further cost benefit analysis is completed but with no knock-on delay to completion expected.
The project to revitalise Long Eaton's high street has faced "unexpected queries" from Derbyshire Highway Authority, according to the council, resulting in delays.Completion of works, estimated to cost about £10m, will not happen until July 2026, instead of June. This date however has been bought forward than the original October 2026 estimate for completion.Work will begin in September this year.
Meanwhile the former Galaxy Row cinema, where demolition work began in May, has also faced another round of delays.It will begin its development stage in September this year, a month after the time it was originally mooted to be finished.The latest slowdown will see the project, which will see the site turned into shops and flats, now expected to be completed in December 2026 instead of October.A project to improve lighting in West Park to encourage walking and cycling was completed last year.
'Challenges to overcome'
The leader of Erewash Conservatives Wayne Major said the delays were "a real concern"."While it's positive that there's now some leeway from government on deadlines, that flexibility should be used to get projects over the line, not to drift further behind."Keeping to budget and timeline is essential if we're going to make the most of this funding."
A spokesperson for Erewash Borough Council said: "The Town Deal continues to be a massive project for the borough council. Like almost all the other such schemes across the country we have had challenges to overcome along the way."The conditions set by the Towns Fund is for all projects to be in contract by the end of March 2026 – with projects completed by the end of March 2027. We are well on track to achieve this."

Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

New Rotherham park and ride site opens
New Rotherham park and ride site opens

BBC News

time39 minutes ago

  • BBC News

New Rotherham park and ride site opens

A new park and ride site for tram train passengers has opened next to Rotherham's Parkgate Shopping free 289-space car park is part of a £12.9m project to improve transport connections across South for the site, which includes 14 EV chargers, cycle racks, disabled access spaces, and parking for solo motorcycles, has come from the government's £166m Transforming Cities Read, leader of Rotherham Council, said: "The new Park and Ride is a real win for Rotherham – it's about making everyday journeys easier, greener and more accessible for local people. "Whether you're hopping on the Tram Train, cycling to the shops, or charging an EV, this investment helps us cut congestion, reduce emissions, and build a better-connected future for our town," he money was also used to build a new link road to make it easier for people to reach the shopping park and reduce traffic congestion on the A633 and A6123. South Yorkshire's Mayor Oliver Coppard said: "South Yorkshire deserves nothing less than a world-class public transport network so our communities can access the jobs and opportunities they deserve; and that we can all stay near and go far."Mark Kanaris, senior operations manager for Parkgate Shopping Park, added: "This investment will have a daily impact, benefitting the hundreds of people who work here and the thousands of visitors who enjoy our big name stores and restaurants each week." Listen to highlights from South Yorkshire on BBC Sounds, catch up with the latest episode of Look North

Oxford Bus Company welcomes plan to tackle 'devastating' traffic
Oxford Bus Company welcomes plan to tackle 'devastating' traffic

BBC News

time39 minutes ago

  • BBC News

Oxford Bus Company welcomes plan to tackle 'devastating' traffic

A bus company has welcomed council plans to develop proposals to tackle Oxford's "devastating" Bus Company previously urged Oxfordshire County Council to find a "Plan B", after the ongoing Botley Road closure delayed the authority's planned introduction of traffic council responded to this by confirming it would be drafting new plans to deal with the city's congestion Marion, the bus company's managing director, said he was "encouraged by the announcement" and "looked forward to engaging" with the council to "improve journeys" for bus users. "A robust bus network is critical in order for the Council to achieve its sustainability targets on the county's roads which we are wholly supportive of," Mr Marion said."To further enhance the appeal of travelling by bus, we need journeys to be faster and more reliable than is currently possible."Present levels of congestion are having a devastating impact on our city which we're keen to help resolve through positive discussion."Oxford Bus Company said journey times on the Abingdon Road had increased by an average of 17% since the Botley Road was closed, with services between Blackbird Leys and Oxford city centre slowing by 33% compared with Mr Marion's correspondence, the council confirmed that potential options to improve travel conditions would be discussed by the council had planned to introduce contentious traffic filters on several major roads in autumn 2024, but they were pushed back for another two years due to the ongoing closure of Botley councillor Brad Baines previously argued argued that the county council plans did "not answer questions about affordability of bus services or routes going where people need to go"."These are key barriers which are yet to be addressed or even considered." You can follow BBC Oxfordshire on Facebook, X (Twitter), or Instagram.

Green light for battery energy storage system at Ferrybridge site
Green light for battery energy storage system at Ferrybridge site

BBC News

time39 minutes ago

  • BBC News

Green light for battery energy storage system at Ferrybridge site

Plans to build a battery energy storage system (BESS) next to a former power station have been Plant Developments wants to install the facility on greenbelt land off Stranglands Lane, near to the former Ferrybridge C power facilities take in power from renewable energy sources and then release it back to the National Grid when demand is Council gave its backing to the plan, which received no comments of support but only one objection. One Plant Developments said it had chosen the location due to its proximity to the Ferrybridge C substation, according to the Local Democracy Reporting firm said: "There are no residential properties in the immediate vicinity of the application site, and the proposed development is not likely to affect any significant number of people."Given that the proposed BESS will be an unmanned facility, with access required only for occasional maintenance inspections, and there being no public access to the site, there are no particular access issues that require to be addressed."The former Ferrybridge power plant, close to the River Aire, was shut in March 2016 after more than 50 years of energy was once one of the biggest power generators in Europe, with its coal-fired boilers producing enough electricity to power 2m homes. Listen to highlights from West Yorkshire on BBC Sounds, catch up with the latest episode of Look North.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into the world of global news and events? Download our app today from your preferred app store and start exploring.
app-storeplay-store