Completion date for new Bridgend school pushed back by two years
Completion date for new Bridgend school pushed back by two years
It comes after delays to ecology work at the site which was held up due to the presence of reptiles
Ysgol Gymraeg Bro Ogwr
(Image: Rob Browne )
Bridgend Council's cabinet has approved a new date for the completion of a replacement school site for Ysgol Bro Ogwr based on the outskirts of Bridgend. Under the proposals the Welsh-medium primary school would relocate from its current location at Princess Way, Brackla, to a new-build facility on land off Ffordd Cadfan.
The plans would see the site enlarged to help meet the local demand for places, with 525 places expected for learners aged four to 11 and a 90-place full-time-equivalent nursery.
While the school was initially set to be completed by September 2025 a report given to members said this was no longer achievable because of delays with ecology work at the site, which were held up due to the presence of reptiles.
It also said that the relocation of the reptiles was expected to take place over the summer of 2025 when the rest of the site would be able to be cleared of scrub and bramble.
Get daily breaking news updates on your phone by joining our WhatsApp community here . We occasionally treat members to special offers, promotions and ads from us and our partners. See our Privacy Notice
It added that with the full planning application for the school currently being finalised a new completion date could be brought forward for September 2027.
Article continues below
This would coincide with the beginning of the 2027-28 school year.
The report read: "The development of the scheme has been challenging due to the ecology issues which has prevented clearance of the Ffordd Cadfan site.
"This has impacted on the original planned implementation date".
The new date was later approved unanimously by councillors in attendance with the project expected to cost around £18.6m.
A consultation on the proposals will also be carried out before the submission of a formal planning application to the council's planning department.
Speaking at the meeting Councillor Martyn Jones of Garw Valley said: "We remain focused on delivering this project, which is now set at September 2027." For the latest Bridgend news sign up to our newsletter here.
Article continues below
The discussions around the school took place at a cabinet meeting in June and came just months after the announcement of new completion date for a replacement school for Mynydd Cynffig Primary in the village of Kenfig Hill. You can read more about the separate £17m project which has recently gone out to tender here.

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Wales Online
5 hours ago
- Wales Online
Completion date for new Bridgend school pushed back by two years
Completion date for new Bridgend school pushed back by two years It comes after delays to ecology work at the site which was held up due to the presence of reptiles Ysgol Gymraeg Bro Ogwr (Image: Rob Browne ) Bridgend Council's cabinet has approved a new date for the completion of a replacement school site for Ysgol Bro Ogwr based on the outskirts of Bridgend. Under the proposals the Welsh-medium primary school would relocate from its current location at Princess Way, Brackla, to a new-build facility on land off Ffordd Cadfan. The plans would see the site enlarged to help meet the local demand for places, with 525 places expected for learners aged four to 11 and a 90-place full-time-equivalent nursery. While the school was initially set to be completed by September 2025 a report given to members said this was no longer achievable because of delays with ecology work at the site, which were held up due to the presence of reptiles. It also said that the relocation of the reptiles was expected to take place over the summer of 2025 when the rest of the site would be able to be cleared of scrub and bramble. Get daily breaking news updates on your phone by joining our WhatsApp community here . We occasionally treat members to special offers, promotions and ads from us and our partners. See our Privacy Notice It added that with the full planning application for the school currently being finalised a new completion date could be brought forward for September 2027. Article continues below This would coincide with the beginning of the 2027-28 school year. The report read: "The development of the scheme has been challenging due to the ecology issues which has prevented clearance of the Ffordd Cadfan site. "This has impacted on the original planned implementation date". The new date was later approved unanimously by councillors in attendance with the project expected to cost around £18.6m. A consultation on the proposals will also be carried out before the submission of a formal planning application to the council's planning department. Speaking at the meeting Councillor Martyn Jones of Garw Valley said: "We remain focused on delivering this project, which is now set at September 2027." For the latest Bridgend news sign up to our newsletter here. Article continues below The discussions around the school took place at a cabinet meeting in June and came just months after the announcement of new completion date for a replacement school for Mynydd Cynffig Primary in the village of Kenfig Hill. You can read more about the separate £17m project which has recently gone out to tender here.


Wales Online
7 hours ago
- Wales Online
Child got stuck on a cliff 25m above popular Welsh beach
Child got stuck on a cliff 25m above popular Welsh beach Emergency crews were called after a child became stranded in a perilous position on the cliff face above the beach The child can be seen halfway up the cliff face (Image: Angle Lifeboat RNLI ) A child had to be rescued after he became stranded in a perilous position halfway up a cliff face at a Welsh beach, some 25 metres above the rocks below. RNLI volunteers dashed to Marloes Sands in Pembrokeshire on Tuesday, June 24, after reports that the child was sat on the cliff side and unable to come down safely. Members of the public were trying to reach the child, but the steepness of the cliff and lack of safe access to their position made this impossible. An image captured at the scene demonstrates how dangerous a position the child was in, with a huge drop to the rocky terrain on the beach below. Thankfully, RNLI crew and coastguard crews were able to help the child and he was brought to safety. For our free daily briefing on the biggest issues facing the nation, sign up to the Wales Matters newsletter here . A spokesman for Angle Lifeboat RNLI said: "Angle RNLI diverted to two separate incidents whilst afloat on a refuelling exercise. Shortly after launching on exercise this afternoon to refuel at Neyland Marina, Angle Lifeboat was tasked at 1.19pm to the report of a child stuck on the cliff at Marloes Sands. Article continues below "Information was scant, but the coastguard had received a dropped 999 calling stating that a child was stuck. The lifeboat immediately diverted and began making best speed to Marloes, and the crew arrived on scene and commenced a search 25 minutes later. "Soon after, the crew located the casualty sat precariously on the cliff side around 25 metres up from the base. There were also members of the public attempting to reach the child. "Dale and St David's Coastguard Teams were arriving on scene and were conned on to the casualty's position. Whilst the teams set up for a technical rescue, the lifeboat stood by." Article continues below

South Wales Argus
8 hours ago
- South Wales Argus
Pisgah Church, Talywain flats plan rejection appeal ruling
The church that has been vacant for six years would have been converted into six flats in a development a council acknowledged would have provided 'much needed housing'. But the plans for the former Pisgah Baptist Church, in Talywain, Pontypool were refused in October last year as applicant Beth Jones disputed Torfaen Borough Council's position she should carry out further surveys to check if the tiny mammals were roosting in the church that dates back to the 1820s. A preliminary roost survey in April, last year, found no evidence of bats internally or externally but did identify a number of potential roosting features. The report recommended a further two dusk emergence surveys be carried out during May and September, described as 'optimum bat season'. Ms Jones' agent suggested the council grant permission and require the further surveys be attached as a condition however Torfaen Borough Council said that wasn't acceptable as it wouldn't be able to establish whether there would be adverse impact on bats which are a protected species. That position has now been upheld by an independent planning inspector after Ms Jones appealed the decision to Planning and Environment Decisions Wales known as PEDW. READ MORE: Torfaen council broke bat protection rules in school refurb Inspector C Sweet said they considered it a 'reasonable likelihood' bats are present in the building based on its condition and their observations. Sweet said the Welsh Government's technical advice notice 'makes clear that it is essential' the presence of protected species, and the potential impact of developments, is established before planning permission is granted and also states permission shouldn't be granted with conditions attached. They also said while they acknowledged Ms Jones' 'intention to avoid harm to biodiversity' she hadn't followed the approach to maintaining and enhancing biodiversity, as set out in Welsh planning policy, and there wasn't sufficient information for any impact on bats to be assessed. Sweet did say: 'The proposal would make some contribution to the supply of housing locally and may also result in a degree of benefit to the local economy. However, such benefits would be modest and would not outweigh the harm to biodiversity interests that I have identified.'