Q1-2025 Production Results, Operational Highlights and Board Change
Q1-2025 Production Results, Operational Highlights and Board Change
Serabi Gold plc ('Serabi' or the 'Company') (AIM:SRB, TSX:SBI, OTCQX:SRBIF), the Brazilian focused gold mining and development company, is pleased to announce the Company's first quarter production results and operating highlights for FY2025 (all financial amounts are expressed in U.S. dollars unless otherwise indicated).
Q1-2025 HIGHLIGHTS
Gold production of 10,013 ounces, an 11% increase from Q1-2024.
Cash as at 31 March 2025 of $26.5 million vs $22.2 million as at 31 December 2024.
Net cash at quarter-end (after interest bearing loans and lease liabilities) of $21.1 million versus $16.2 million as at 31 December 2024.
The Company remains on track to achieve 2025 consolidated production guidance of 44,000 – 47,000 ounces gold.
Reported initial exploration update from the brownfield exploration opportunities at Palito Complex, Coringa Mine and São Domingos target, which is part of Phase II of the Company's growth strategy; initial exploration model indicates a potential for a satellite orebody to the Palito Complex – link to press release.
The Company is currently assessing appropriate mechanisms to return capital to shareholders.
Mike Hodgson, CEO of Serabi, commented:
'An excellent start to 2025 with over 10,000 ounces produced, an 11% increase on Q1-2024, and what was most pleasing within these numbers was the substantial grade improvements at both Palito and Coringa. Palito plant feed grades were 32% improved on Q1-2024, whilst Coringa plant feed grades showed a 10% improvement.
Q1-2025 has also been the first full operational quarter for the Coringa classification plant, and that 10% grade improvement is partly driven by this. We spent the quarter commissioning and optimising the classification plant at Coringa. High grade Coringa Run of Mine (ROM) ore was transported directly to the Palito Complex plant. Additionally, we used low grade stocks at Coringa (<2g/t Au) during the optimising of the sorter, which was extremely effective, with the ore sorted from these low-grade stocks supplementing the high-grade ROM sent from Coringa to the Palito Complex plant.
The Coringa Mine continued to perform exceptionally well with ore being mined in the Serra zone at levels 260m, 225m, 190m, and 158m. The main ramp is deepening to level 125m. The first quarter also saw the progression and development of Meio, the second sector at Coringa. The first two levels, 356m and 336m are now in development, with development ore already contributing to the Coringa gold production. Meio is expected to contribute significantly to Coringa production in 2025.
At Palito, the grades improved as mining has increased in the high grade Barrichello zone. This zone along with the G3 and Ipe zones are contributing the bulk of Palito Complex ROM and will continue to do so this year. The development of the G3 vein on levels -20m and -80m are particularly exciting, where we expect some excellent results this year.
Finally, during the quarter, we saw our brownfield exploration programme get underway. We now have two rigs at Palito and two at Coringa. The first results were published in early April with very encouraging results at Palito Complex with step out drilling on the Senna vein. At Coringa we are drilling the Coringa trend between the Galena and Mae de Leite zones with early success as well as intersecting the new zone called Jatobá. We are planning to spend approximately $9m in 2025 equally across both sites in our quest to double the current consolidated mineral resource inventory of 1Moz. I look forward to regularly updating investors on progress on our exploration success.
In light of the excellent operational performance, strong prevailing gold price, cash position and anticipated cash growth ahead, the Company is currently assessing appropriate mechanisms to return capital to shareholders.'
To access an interview of Mike Hodgson with Crux Investor discussing the Q1-2025 update, follow this LINK.
OPERATIONAL RESULTS
(1) The table may not sum due to rounding.
(2) Production numbers are subject to change pending final assay analysis from refineries.
Total production for the first quarter was 10,013 ounces. Total ore mined during the quarter was 44,924 tonnes at 7.09 g/t compared to 50,327 tonnes at 6.19 g/t for the fourth quarter of 2024. The increase in grade has mostly come from higher grade ore mined in the Barrichello and G3 zones in Palito, as well as improved grades in the Serra zone at Coringa. The Palito Complex process plant treated 48,155 tonnes of ROM ore at a grade of 6.70 g/t Au compared to 52,363 tonnes at an average grade of 6.21 g/t Au for Q4-2024.
A total of 3,505 metres of horizontal development has been completed for the quarter of which 1,849 metres was ore development. The balance was the ramp, crosscuts and stope preparation development.
The Coringa orebody continues to perform well. Production was focused on the levels of 260m, 225m, 195m, and 165m with development now ongoing on level 130m. The newly intersected Meio zone is still in development only with levels 356m and 336m advancing.
FINANCE UPDATE
Cash balances at the end of March 2025 were $26.5 million, in comparison to the cash balances at the end of December 2024 of $22.2 million. On 6 January 2025 the Company fully repaid its $5.0 million unsecured loan arrangement with Itau Bank in Brazil which carried an interest coupon of 8.47 per cent. On 22 January 2025, the Group secured a new $5.0 million loan from Banco Santander. The Banco Santander loan is repayable as a bullet payment on 21 January 2026 and carries an interest coupon of 6.16%. The Company had a net cash balance at the end of Q1-2025 (after interest bearing loans and lease liabilities) of $21.1 million (31 December 2024: net cash $16.2 million).
FY2025 PRODUCTION GUIDANCE
The Company remains on track to achieve 2025 consolidated production guidance of 44,000 – 47,000 ounces gold.
BOARD CHANGE
Mark Sawyer, non-executive director of Serabi Gold, informed the Board of Directors of his resignation effective 11 April 2025. Following his resignation, Mark Sawyer ceased to be a member of the Board of Directors of Serabi Gold with immediate effect.
' We thank Mark for his significant contributions to the Company and we wish him all the best.' commented Mike Hodgson, Chief Executive Officer of Serabi Gold.
About Serabi Gold plc
Serabi Gold plc is a gold exploration, development and production company focused on the prolific Tapajós region in Para State, northern Brazil. The Company has consistently produced 30,000 to 40,000 ounces per year with the Palito Complex and is planning to double production in the coming years with the construction of the Coringa Gold project. Serabi Gold plc recently made a copper-gold porphyry discovery on its extensive exploration licence. The Company is headquartered in the United Kingdom with a secondary office in Toronto, Ontario, Canada.
The information contained within this announcement is deemed by the Company to constitute inside information as stipulated under the Market Abuse Regulations (EU) No. 596/2014 as it forms part of UK Domestic Law by virtue of the European Union (Withdrawal) Act 2018.
The person who arranged for the release of this announcement on behalf of the Company was Andrew Khov, Vice President, Investor Relations & Business Development.
Enquiries
SERABI GOLD plc
Michael Hodgson t + 44 (0)20 7246 6830
Chief Executive m +44 (0)7799 473621
Andrew Khov m +1 647 885 4874
Vice President, Investor Relations &
Business Development
e contact@serabigold.com
www.serabigold.com
BEAUMONT CORNISH Limited
Nominated Adviser & Financial Adviser
Roland Cornish / Michael Cornish t +44 (0)20 7628 3396
PEEL HUNT LLP
Joint UK Broker
Ross Allister t +44 (0)20 7418 9000
TAMESIS PARTNERS LLP
Joint UK Broker
Charlie Bendon/ Richard Greenfield t +44 (0)20 3882 2868
CAMARCO
Financial PR - Europe
Gordon Poole / Emily Hall t +44 (0)20 3757 4980
HARBOR ACCESS
Financial PR – North America
Jonathan Patterson / Lisa Micali t +1 475 477 9404
Copies of this announcement are available from the Company's website at www.serabigold.com.
See www.serabigold.com for more information and follow us on twitter @Serabi_Gold
GLOSSARY OF TERMS
The following is a glossary of technical terms:
'actinolite' amphibole silicate mineral commonly found in metamorphic rocks, including those surrounding cooled intrusive igneous rocks
'Ag' means silver.
'alkalic porphyry' A class of copper-porphyry mineral deposits characterised by disseminated mineralisation within and immediately adjacent to silica-saturated to silica-undersaturated alkalic intrusive centres and being copper/gold/molybdenum-rich.
'albite' is a plagioclase feldspar mineral
'aplite' An intrusive igneous rock in which the mineral composition is the same as granite, but in which the grains are much finer
'argillic alteration' is hydrothermal alteration of wall rock which introduces clay minerals including kaolinite, smectite and illite
'AISC' means All-In Sustaining Cost – a non IFRS performance measurement established by the World Gold Council
'ANM' means the Agencia Nacional de Mineral.
'Au' means gold.
'assay' in economic geology, means to analyse the proportions of metal in a rock or overburden sample; to test an ore or mineral for composition, purity, weight or other properties of commercial interest.
'biotite' A phyllosilicate mineral composed of a silicate of iron, magnesium, potassium, and aluminum found in crystalline rocks and as an alteration mineral.
'breccia' a rock composed of large angular broken fragments of minerals or rocks cemented together by a fine-grained matrix
'brecciation' Describes the process where large angular broken fragments of minerals or rocks become cemented together by a fine-grained matrix.
'CIM' means the Canadian Institute of Mining, Metallurgy and Petroleum.
'CIP' or 'Carbon in Pulp' means a process used in gold extraction by addition of cyanide.
'chalcopyrite' is a sulphide of copper and iron.
'copper porphyry' copper ore body formed from hydrothermal fluids. These fluids will be predated by or associated with are vertical dykes of porphry intrusive rocks
'Cu' means copper.
'cut-off grade' the lowest grade of mineralised material that qualifies as ore in a given deposit; rock of the lowest assay included in an ore estimate.
'dacite porphyry intrusive' a silica-rich igneous rock with larger phenocrysts (crystals) within a fine-grained matrix
'deposit' is a mineralised body which has been physically delineated by sufficient drilling, trenching, and/or underground work, and found to contain a sufficient average grade of metal or metals to warrant further exploration and/or development expenditures; such a deposit does not qualify as a commercially mineable orebody or as containing ore reserves, until final legal, technical, and economic factors have been resolved.
'electromagnetics' is a geophysical technique tool measuring the magnetic field generated by subjecting the sub-surface to electrical currents.
'epidote' is a calcium aluminium iron sorosilicate mineral
'garimpo' is a local artisanal mining operation
'garimpeiro' is a local artisanal miner.
'geochemical' refers to geological information using measurements derived from chemical analysis.
'geophysical' refers to geological information using measurements derived from the use of magnetic and electrical readings.
'geophysical techniques' include the exploration of an area by exploiting differences in physical properties of different rock types. Geophysical methods include seismic, magnetic, gravity, induced polarisation and other techniques; geophysical surveys can be undertaken from the ground or from the air.
'gold equivalent' refers to quantities of materials other than gold stated in units of gold by reference to relative product values at prevailing market prices.
'gossan' is an iron-bearing weathered product that overlies a sulphide deposit.
'grade' is the concentration of mineral within the host rock typically quoted as grams per tonne (g/t), parts per million (ppm) or parts per billion (ppb).
'g/t' means grams per tonne.
'granodiorite' is an igneous intrusive rock like granite.
'hectare' or a 'ha' is a unit of measurement equal to 10,000 square metres.
'hematite' is a common iron oxide compound
'igneous' is a rock that has solidified from molten material or magma.
'indicated mineral resource' is that part of a mineral resource for which quantity, grade or quality, densities, shape and physical characteristics can be estimated with a level of confidence sufficient to allow the appropriate application of technical and economic parameters, to support mine planning and evaluation of the economic viability of the deposit. The estimate is based on detailed and reliable exploration and testing information gathered through appropriate techniques from locations such as outcrops, trenches, pits, workings and drill holes that are spaced closely enough for geological and grade continuity to be reasonably assumed.
'inferred mineral resource' is that part of a mineral resource for which quantity and grade or quality can be estimated on the basis of geological evidence and limited sampling and reasonably assumed, but not verified, geological and grade continuity. The estimate is based on limited information and sampling gathered through appropriate techniques from locations such as outcrops, trenches, pits, workings and drill holes.
'IP' refers to induced polarisation, a geophysical technique whereby an electric current is induced into the sub-surface and the conductivity of the sub-surface is recorded.
'intrusive' is a body of rock that invades older rocks.
'lithocap' Lithocaps are subsurface, broadly stratabound alteration domains that are laterally and vertically extensive. They form when acidic magmatic-hydrothermal fluids react with wallrocks during ascent towards the paleosurface.
'measured mineral resource' is that part of a mineral resource for which quantity, grade or quality, densities, shape, and physical characteristics are so well established that they can be estimated with confidence sufficient to allow the appropriate application of technical and economic parameters, to support production planning and evaluation of the economic viability of the deposit. The estimate is based on detailed and reliable exploration, sampling and testing information gathered through appropriate techniques from locations such as outcrops, trenches, pits, workings and drill holes that are spaced closely enough to confirm both geological and grade continuity.
'mineralisation' the concentration of metals and their chemical compounds within a body of rock.
'mineralised' refers to rock which contains minerals e.g. iron, copper, gold.
'mineral reserve' is the economically mineable part of a measured or indicated mineral resource demonstrated by at least a preliminary feasibility study. This study must include adequate information on mining, processing, metallurgical, economic and other relevant factors that demonstrate, at the time of reporting, that economic extraction can be justified. A mineral reserve includes diluting materials and allowances for losses that may occur when the material is mined.
'mineral resource' is a concentration or occurrence of diamonds, natural solid inorganic material or natural fossilised organic material including base and precious metals, coal, and industrial minerals in or on the Earth's crust in such form and quantity and of such a grade or quality that it has reasonable prospects for economic extraction. The location, quantity, grade, geological characteristics and continuity of a mineral resource are known, estimated or interpreted from specific geological evidence and knowledge.
'Mo-Bi-As-Te-W-Sn' Molybdenum-Bismuth-Arsenic-Tellurium-Tungsten-Tin
'magnetite' Magnetic mineral composed of iron oxide found in intrusive rocks and as an alteration mineral.
'monzodiorite' Is an intrusive rock formed by slow cooling of underground magma.
'monzogranite' a biotite rich granite, often part of the later-stage emplacement of a larger granite body.
'mt' means million tonnes.
'NI 43-101' means Canadian Securities Administrators' National Instrument 43-101 – Standards of Disclosure for Mineral Projects.
'ore' means a metal or mineral or a combination of these of sufficient value as to quality and quantity to enable it to be mined at a profit.
'oxides' are near surface bed-rock which has been weathered and oxidised by long-term exposure to the effects of water and air.
'paragenesis' Is a term used to describe the sequence on relative phases of origination of igneous and metamorphic rocks and the deposition of ore minerals and rock alteration.
'phyllic alteration' is a hydrothermal alteration zone in a permeable rock that has been affected by circulation of hydrothermal fluids
'porphry' any of various granites or igneous rocks with coarse grained crystals
'ppm' means parts per million.
'proterozoic' means the geological eon (period) 2.5 billion years ago to 541 million years ago
'pyrite' an iron sulphide mineral
'quartz-alunite ± kaolinite' Alunite is a hydroxylated aluminium potassium sulfate mineral. It presence is typical in areas of advanced argillic alteration and usually accompanied by the presence of quartz (a crystalline silica mineral) and sometimes kaolinite.(a clay mineral).
'saprolite' is a weathered or decomposed clay-rich rock.
'scapolites' are a group of rock-forming silicate minerals composed of aluminium, calcium, and sodium silicate with chlorine, carbonate and sulfate
'sulphide' refers to minerals consisting of a chemical combination of sulphur with a metal.
'tailings' are the residual waste material that it is produced by the processing of mineralised rock.
'tpd' means tonnes per day.
'vein' is a generic term to describe an occurrence of mineralised rock within an area of non-mineralised rock.
'VTEM' refers to versa time domain electromagnetic, a particular variant of time-domain electromagnetic geophysical survey to prospect for conductive bodies below surface.
'vuggy' a geological feature characterised by irregular cavities or holes within a rock or mineral, often formed by the dissolution or removal of minerals leaving behind empty spaces
Assay Results
Assay results reported within this release include those provided by the Company's own on-site laboratory facilities at Palito and have not yet been independently verified. Serabi closely monitors the performance of its own facility against results from independent laboratory analysis for quality control purpose. As a matter of normal practice, the Company sends duplicate samples derived from a variety of the Company's activities to accredited laboratory facilities for independent verification. Since mid-2019, over 10,000 exploration drill core samples have been assayed at both the Palito laboratory and certified external laboratory, in most cases the ALS laboratory in Belo Horizonte, Brazil. When comparing significant assays with grades exceeding 1 g/t gold, comparison between Palito versus external results record an average over-estimation by the Palito laboratory of 6.7% over this period. Based on the results of this work, the Company's management are satisfied that the Company's own facility shows sufficiently good correlation with independent laboratory facilities for exploration drill samples. The Company would expect that in the preparation of any future independent Reserve/Resource statement undertaken in compliance with a recognized standard, the independent authors of such a statement would not use Palito assay results without sufficient duplicates from an appropriately certificated laboratory.
Forward-looking statements
Certain statements in this announcement are, or may be deemed to be, forward looking statements. Forward looking statements are identified by their use of terms and phrases such as ''believe'', ''could'', 'should' ''envisage'', ''estimate'', ''intend'', ''may'', ''plan'', ''will'' or the negative of those, variations or comparable expressions, including references to assumptions. These forward-looking statements are not based on historical facts but rather on the Directors' current expectations and assumptions regarding the Company's future growth, results of operations, performance, future capital and other expenditures (including the amount, nature and sources of funding thereof), competitive advantages, business prospects and opportunities. Such forward looking statements reflect the Directors' current beliefs and assumptions and are based on information currently available to the Directors. Several factors could cause actual results to differ materially from the results discussed in the forward-looking statements including risks associated with vulnerability to general economic and business conditions, competition, environmental and other regulatory changes, actions by governmental authorities, the availability of capital markets, reliance on key personnel, uninsured and underinsured losses and other factors, many of which are beyond the control of the Company. Although any forward-looking statements contained in this announcement are based upon what the Directors believe to be reasonable assumptions, the Company cannot assure investors that actual results will be consistent with such forward looking statements.
Qualified Persons Statement
The scientific and technical information contained within this announcement has been reviewed and approved by Michael Hodgson, a Director of the Company. Mr Hodgson is an Economic Geologist by training with over 30 years' experience in the mining industry. He holds a BSc (Hons) Geology, University of London, a MSc Mining Geology, University of Leicester and is a Fellow of the Institute of Materials, Minerals and Mining and a Chartered Engineer of the Engineering Council of UK, recognizing him as both a Qualified Person for the purposes of Canadian National Instrument 43-101 and by the AIM Guidance Note on Mining and Oil & Gas Companies dated June 2009.
Notice
Beaumont Cornish Limited, which is authorised and regulated in the United Kingdom by the Financial Conduct Authority, is acting as nominated adviser to the Company in relation to the matters referred herein. Beaumont Cornish Limited is acting exclusively for the Company and for no one else in relation to the matters described in this announcement and is not advising any other person and accordingly will not be responsible to anyone other than the Company for providing the protections afforded to clients of Beaumont Cornish Limited, or for providing advice in relation to the contents of this announcement or any matter referred to in it.
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Cision Canada
an hour ago
- Cision Canada
Saltire Capital Ltd. Announces Voting Results from its Annual General and Special Meeting of Shareholders
TORONTO, June 26, 2025 /CNW/ - Saltire Capital Ltd. (TSX: SLT.U, SLT, & (" Saltire" or the " Company") announced today the results of voting at its annual general and special meeting of shareholders held on June 26, 2025 (the " Meeting"). Each of the seven nominees listed in the Company's management information circular dated May 21, 2025 (the " Circular") provided in connection with the Meeting were elected as directors of the Company. Saltire received proxies and virtual votes at the Meeting as set out below: In addition, Saltire reports that (i) an ordinary resolution approving the appointment of MNP LLP as Saltire's auditors for the 2025 fiscal year was passed by a majority of the votes represented at the Meeting, and (ii) an ordinary resolution approving the Company's new equity incentive plan, as described in more detail in the Circular, was passed by (A) a majority of the votes represented at the Meeting, and (B) a majority of the votes of disinterested shareholders represented at the Meeting. Details of the voting results on all matters considered at the Meeting are available in the Company's report of voting results, which is available under Saltire's profile on SEDAR+ at About Saltire Saltire is a long-term capital partner that allocates capital to equity, debt and/or hybrid securities of high-quality private companies. Investments made by Saltire consist of meaningful and influential stakes in carefully selected private companies that the management believes are under-valued businesses with high barriers to entry, predictable revenue streams and cash flows and defensive characteristics, with a view to significantly improve the fundamental value over the long-term. Although Saltire primarily allocates capital to private companies, Saltire may, in certain circumstances if the opportunity arises, also pursue opportunities with orphaned or value-challenged small and micro-cap public companies. Saltire provides investors with access to private and control-level investments typically reserved for larger players, while maintaining liquidity. SOURCE Saltire Capital Ltd.


Cision Canada
an hour ago
- Cision Canada
G Mining Ventures Announces Results of Annual General and Special Meeting
BROSSARD, QC, June 26, 2025 /CNW/ - G Mining Ventures Corp. (" GMIN" or the " Corporation") (TSX: GMIN) (OTCQX: GMINF) is pleased to announce the voting results from its annual general and special meeting of shareholders held today (the " Meeting"). All matters submitted to shareholders for approval, as set out in the Corporation's Notice of Meeting and Information Circular, both dated May 27, 2025, were approved by the requisite majority of votes cast at the Meeting. At the Meeting: 1. Election of Directors Each of the following individuals was elected to the Board of Directors of GMIN to serve until the next annual meeting of shareholders or until their successors are duly elected or appointed: 2. The Appointment of Auditors Shareholders approved the appointment of PricewaterhouseCoopers LLP as the Corporation's independent auditors for the ensuing year and authorized the directors to fix their remuneration. Votes For % For Votes Withheld % Withheld 186,028,835 99.97 % 52,240 0.03 % 3. Approval of the Corporations General By-Laws Shareholders approved, confirmed and ratified the Corporation's general by-laws as adopted by the Board on June 20, 2024. Votes For % For Votes Withheld % Withheld 153,057,223 84.88 % 27,266,290 15.12 % Detailed voting results from the Meeting are available on SEDAR+ ( under GMIN's issuer profile, on the OTC Markets website ( and on GMIN's website at About G Mining Ventures Corp. G Mining Ventures Corp. (TSX: GMIN) (OTCQX: GMINF) is a mining company engaged in the acquisition, exploration and development of precious metal projects to capitalize on the value uplift from successful mine development. GMIN is well-positioned to grow into the next mid-tier precious metals producer by leveraging strong access to capital and proven development expertise. GMIN is currently anchored by the Tocantinzinho Mine in Brazil, supported by the Gurupi Project in Brazil and the Oko West Project in Guyana — all with significant exploration upside and located in mining-friendly jurisdictions. Cautionary Statement on Forward-Looking Information All statements, other than statements of historical fact, contained in this press release constitute "forward-looking information" and "forward-looking statements" within the meaning of certain securities laws and are based on expectations and projections as of the date of this press release. Forward-looking statements contained in this press release include, without limitation, those related to the section entitled "About G Mining Ventures Corp.". Forward-looking statements are based on expectations, estimates and projections as of the time of this press release. Forward-looking statements are necessarily based upon several estimates and assumptions that, while considered reasonable by the Corporation as of the time of such statements, are inherently subject to significant business, economic and competitive uncertainties and contingencies. These estimates and assumptions may prove to be incorrect. Such assumptions include, without limitation, those relating to the price of gold and currency exchange rates, those outlined in the Technical Report and those underlying the items listed in the above section entitled "About G Mining Ventures Corp.". Many of these uncertainties and contingencies can directly or indirectly affect, and could cause, actual results to differ materially from those expressed or implied in any forward-looking statements. There can be no assurance that, notably but without limitation, (i) GMIN will achieve its objectives for Oko West, notably to bring the Project into commercial production, or (ii) GMIN will use TZ and Oko West to grow GMIN into the next intermediate producer, or (iii) the exploration upside of GMIN's properties will lead to additional mineral resources and reserves, as future events could differ materially from what is currently anticipated by the Corporation. In addition, there can be no assurance that Brazil and/or Guyana will remain mining friendly and prospective jurisdictions. By their very nature, forward-looking statements involve inherent risks and uncertainties, both general and specific, and risks exist that estimates, forecasts, projections and other forward-looking statements will not be achieved or that assumptions do not reflect future experience. Forward-looking statements are provided for the purpose of providing information about management's expectations and plans relating to the future. Readers are cautioned not to place undue reliance on these forward-looking statements as a number of important risk factors and future events could cause the actual outcomes to differ materially from the beliefs, plans, objectives, expectations, anticipations, estimates, assumptions and intentions expressed in such forward-looking statements. All of the forward-looking statements made in this press release are qualified by these cautionary statements and those made in the Corporation's other filings with the securities regulators of Canada including, but not limited to, the cautionary statements made in the relevant sections of the Corporation's (i) Annual Information Form dated March 27, 2025, for the financial year ended December 31, 2024, and (ii) Management Discussion & Analysis. The Corporation cautions that the foregoing list of factors that may affect future results is not exhaustive, and new, unforeseeable risks may arise from time to time. The Corporation disclaims any intention or obligation to update or revise any forward-looking statements or to explain any material difference between subsequent actual events and such forward-looking statements, except to the extent required by applicable law. SOURCE G Mining Ventures Corp


Cision Canada
an hour ago
- Cision Canada
Arizona Metals Corp Announces Results of 2025 Annual and Special Meeting of Shareholders
TORONTO, June 26, 2025 /CNW/ - Arizona Metals Corp. (TSX: AMC) (OTCQX: AZMCF) (the "Company" or "Arizona Metals") today announced the voting results of the annual and special meeting of shareholders of the Company convened and adjourned on June 18, 2025 and concluded today (the "Meeting"). The results of the vote in respect of the election of directors of the Company is set out below. Although they did not receive a majority of votes cast for their respective re-elections, Mr. Pilmer, Ms. Arnold and Ms. Rojas Espinoza have each graciously agreed to continue to act as members of the Company's board of directors (the "Board"), and Mr. Pilmer has agreed to continue in his role as Chair of the Audit Committee of the Board, in order to facilitate a seamless and orderly transition, in accordance with the Canada Business Corporations Act. In addition to voting on the election of directors, at the Meeting shareholders also re-appointed McGovern Hurley LLP, Chartered Professional Accountants, as auditors of the Company, and approved the resolution adopting the Company's new omnibus equity incentive plan. A total of 70,196,756 shares were voted at the Meeting, representing 51.18% of the common shares that were issued and outstanding as at the record date for the Meeting. Further disclosure on the matters approved at the Meeting can be found in the notice of meeting and accompanying management information circular filed in respect of the Meeting and available on SEDAR+ at About Arizona Metals Corp Arizona Metals Corp owns 100% of the Kay Project in Yavapai County, which is located on 1669 acres of patented and BLM mining claims and 193 acres of private land that are not subject to any royalties. An historic estimate by Exxon Minerals in 1982 reported a "proven and probable reserve of 6.4 million short tons at a grade of 2.2% copper, 2.8 g/t gold, 3.03% zinc, and 55 g/t silver." The historic estimate at the Kay Mine Project was reported by Exxon Minerals in 1982. (Fellows, M.L., 1982, Kay Mine massive sulphide deposit: Internal report prepared for Exxon Minerals Company) The Kay Project's historic estimate has not been verified as a current mineral resource. None of the key assumptions, parameters, and methods used to prepare the historic estimate were reported, and no resource categories were used. Significant data compilation, re-drilling and data verification may be required by a Qualified Person before the historic estimate can be verified and upgraded to be a current mineral resource. A Qualified Person has not done sufficient work to classify it as a current mineral resource, and Arizona Metals is not treating the historic estimate as a current mineral resource. The Kay Project is a steeply dipping VMS deposit that has been defined from a depth of 60 m to at least 900 m. It is open for expansion on strike and at depth. The Company also owns 100% of the Sugarloaf Peak Project, in La Paz County, which is located on 4,400 acres of BLM claims. The Sugarloaf Peak Project is a heap-leach, open-pit target and has a historic estimate of "100 million tons containing 1.5 million ounces gold" at a grade of 0.5 g/t (Dausinger, N.E., 1983, Phase 1 Drill Program and Evaluation of Gold-Silver Potential, Sugarloaf Peak Project, Quartzsite, Arizona: Report for Westworld Inc.) The historic estimate at the Sugarloaf Peak Project was reported by Westworld Resources in 1983. The historic estimate has not been verified as a current mineral resource. None of the key assumptions, parameters, and methods used to prepare the historic estimate were reported, and no resource categories were used. Significant data compilation, re-drilling and data verification may be required by a Qualified Person before the historic estimate can be verified and upgraded to a current mineral resource. A Qualified Person has not done sufficient work to classify it as a current mineral resource, and Arizona Metals is not treating the historic estimate as a current mineral resource. Qualified Person and Quality Assurance/Quality Control The qualified person who reviewed and approved the technical disclosure in this news release is David Smith, CPG, VP of Exploration of the Company and a qualified person as defined in National Instrument43-101 – Standards of Disclosure for Mineral Projects. Disclaimer This press release contains statements that constitute "forward-looking information" (collectively, "forward-looking statements") within the meaning of the applicable Canadian securities legislation. All statements, other than statements of historical fact, are forward-looking statements and are based on expectations, estimates and projections as at the date of this news release. Any statement that discusses predictions, expectations, beliefs, plans, projections, objectives, assumptions, future events or performance (often but not always using phrases such as "expects", or "does not expect", "is expected", "anticipates" or "does not anticipate", "plans", "budget", "scheduled", "forecasts", "estimates", "believes" or "intends" or variations of such words and phrases or stating that certain actions, events or results "may" or "could", "would", "might" or "will" be taken to occur or be achieved) are not statements of historical fact and may be forward-looking statements. Forward-looking statements contained in this press release include, without limitation, statements regarding directors remaining on the Board for a transitionary period and the appointment of one or more successor directors prior to the next annual meeting of shareholders. In making the forward- looking statements contained in this press release, the Company has made certain assumptions. Although the Company believes that the expectations reflected in forward-looking statements are reasonable, it can give no assurance that the expectations of any forward-looking statements will prove to be correct. Known and unknown risks, uncertainties, and other factors which may cause the actual results and future events to differ materially from those expressed or implied by such forward-looking statements. Accordingly, readers should not place undue reliance on the forward-looking statements and information contained in this press release. Except as required by law, the Company disclaims any intention and assumes no obligation to update or revise any forward-looking statements to reflect actual results, whether as a result of new information, future events, changes in assumptions, changes in factors affecting such forward- looking statements or otherwise.