Mt Messenger contractors making strides underground and overhead

Mt Messenger contractors making strides underground and overhead

RNZ News03-06-2025
Contractors have offered a sneak-peak at two of the main features of Te Ara o Te Ata - the Mt Messenger Bypass on State Highway 3 in Taranaki.
A huge road-heading machine is excavating a 235m-long tunnel under the highest point of the maunga and construction of a 125m-long bridge toward the southern end of the project is underway.
The six-kilometre $360 million bypass aims to deliver a safer more resilient route north out of Taranaki, avoiding an existing steep and windy stretch of highway which includes a narrow tunnel.
NZTA project manager Caleb Perry.
Photo:
RNZ / Robin Martin
Waka Kotahi project manager Caleb Perry said the tunnel, which was 65m below the summit, was a key component of the project.
"The tunnel is 235m-long or will be once we've broken through and it's excavated in two headings. So, what we're standing in now is the top heading and the final road level will be about 3m below our feet here.
"So, we break through with this top heading out the other side probably in about October/November time this year. Then we bring all the team back to the start, drop down about 3m and carry on and remove what we call the bench."
Perry said two-lane bridge would be 13m wide by 9m high, giving an over-dimensional traffic envelope of 10m wide and 6m high when an emergency exit passage was installed one side and the lighting and fire safety equipment installed the roof.
Inside the tunnel.
Photo:
RNZ / Robin Martin
Tunnel supervisor Steve Wiley.
Photo:
RNZ / Robin Martin
A Tūrangi local, tunnel supervisor Steve Wiley learned his trade in Australia.
"A typical day underground is pretty much excavation, shotcrete, curing time and excavating again."
He loved life underground.
"It's just a challenge. You have challenging days, good days. And it's the people, you know, you run into some really good characters working underground."
Roadheader operator Carlos Cooper.
Photo:
RNZ / Robin Martin
Carlos Cooper pilots the 110-tonne road-header given the name 'Hinetūparimaunga' - the atua of mountains and cliffs - by project partners Ngāti Tama.
"She's one of the nicest machines you can drive in underground tunnelling. She's pretty good and particularly with this ground it's pretty soft, so she's easy cutting on this particular project."
The 110 tonne roadheader machine in the Mt Messenger tunnel.
Photo:
RNZ / Robin Martin
He also earned his stripes across the ditch.
"In Australia is where I started. I had a few mates who got into the underground game and I haven't looked back since."
The Whanganui local outlined his day.
"Arrive for a briefing at about 6.30am and come up here about 7am. Get into cutting mode and then it will take approximately two, two and a half hours to cut 1.2m and then we'll much the face out and shot crete will come in and do their bit and we'll bolt after that and shotcrete again."
Cooper was looking forward to emerging at the other end.
"It's quite a relief one of those special days you can look back on and tell your grandkids yeah you were on that project and it was one to remember.
He hoped to take a spin on the new highway once it was finished.
"Absolutely, yeah, hopefully I'll be one of the first."
Bridge building boss Nick Myers-Kay.
Photo:
RNZ / Robin Martin
Senior project engineer Nick Myers-Kay was in charge of constructing the project's longest bridge - which actually involved building two bridges.
"Currently we're standing on the 110m of temporary staging that needs to be constructed ahead of building the permanent bridge which is going to be located out to the right of us here.
"In the background here that's the first lot of permanent earthworks that the bridge is started on. That's pretty much where the abutment is going to start. The bridge had raking piers. That keeps the pier foundations out of the wetland."
The view from a service road down to the tunnel head.
Photo:
RNZ / Robin Martin
He said the temporary bridge - on which a 28 tonne crane was operating - helped minimised damage to the wetland below.
"The immediate challenge is the environment. I'm new to this area I've never worked in this region before, so I'm quite amazed at the ruggedness and steepness of the terrain around us.
"It's obviously very beautiful country here too the bush is just spectacular, so that is obviously a major challenge for us to navigate our way around that."
It was a point project manager Caleb Perry reinforced.
"This is a really important part of the natural environment here at the headwaters of the Mimi Stream and you can see off to the side the kahikatea swamp forest which is one of the last inland wetlands that we are working as hard as we can to protect."
A digger operating in the tunnel.
Photo:
RNZ / Robin Martin
That went as far as bending trees out of the way.
"You can see around me there are few trees with tie-downs, ropes around them. We basically put a team of ecologists in a basket hang them from a crane and the try and bend some of those trees out of the way, so the temporary bridge can go through.
"After we've built the main structure this temporary bridge won't be needed anymore and the team will come back and let the trees bounce back into their natural position."
A 28 tonne crane preparing to place a pile from the staging bridge at the construction site of the 125m steel girder bridge.
Photo:
RNZ / Robin Martin
The permanent bridge was due to be completed by September 2026.
New Zealand Transport Agency was still embroiled in a Public Works Act wrangle for land required for the project at its northern end.
If that was successful, it would take about four years to complete the bypass.
A surveyor working at the tunnel face.
Photo:
RNZ / Robin Martin
Sign up for Ngā Pitopito Kōrero
,
a daily newsletter curated by our editors and delivered straight to your inbox every weekday.
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Ethnic leaders call for more resources for better social cohesion
Ethnic leaders call for more resources for better social cohesion

RNZ News

time6 hours ago

  • RNZ News

Ethnic leaders call for more resources for better social cohesion

Representatives from the National Ethnic and Faith Community Leaders Network meeting opposition leader Chris Hipkins in Auckland on 15 August 2025. Photo: Supplied Ethnic leaders are calling for more resources to tackle issues such as social cohesion and health disparities at a meeting with opposition leader Chris Hipkins in Auckland on Friday. Representatives from the National Ethnic and Faith Community Leaders Network attended the meeting, with the Labour Party's ethnic communities spokesperson Jenny Salesa also present. After the event that was closed to media, Hipkins said they've discussed issues concerning the general public, such as employment, health, homes and cost of living, as well as these specific to migrant and religious communities, such as immigration. He said life has become tougher for the ethnic communities since he met the same group last year. "Issues around the cost of living have gotten worse. I think issues around polarisation continue to be a real area of concern when I speak to our community," he said. "More tension within the communities and more overt displays of racism within the communities are something I'm very concerned about." Hipkins said "the many faces of our community" needed to be reflected in the way services were being delivered such as health and education. When asked what would he do about the problems, Hipkins said it would be reflected in the Labour Party's policies before the next election. "Part of the reason that we're here is that we want to make sure that we're listening to New Zealanders as we develop our policies," he said. Dame Ranjna Patel, Chris Hipkins, and the Labour Party's ethnic communities spokesperson Jenny Salesa. Photo: Supplied Social cohesion was a topic that concerned Dame Ranjna Patel the most. "The social cohesion in the ethnic community and mainstream is very divided at the moment, and it's just progressively getting louder and more of a problem," she said. Patel said the differences of all the ethnic communities are so wide and groups should come together for solutions. "We do need to work together to give bite size problems with bite size solutions, not just say this is a issue, fix it. It's too hard for every government to do. We have to have a budget that lets us do that," she said. "To get communities to develop themselves to be able to deal with these, we'll need a lot more resources." Debbie Chin, president of the New Zealand Chinese Association's Wellington branch. Photo: RNZ / Liu Chen New Zealand Chinese Association's Wellington branch president Debbie Chin's area of focus was the health of wellbeing of Asian New Zealanders. "We're looking for improved access to services for our Chinese and Asian communities," Chin said. "That means that we need services that meet the needs of our population, and we also need to have providers who can... understand our culture." "We need diversification across all of those areas, across service delivery, cross workforce, cross funding and commissioning and the people in the decision making seats." Chin pointed to a recent report which found that almost half of Asian parents said their children have been bullied at school in the past 12 months often associated with racism. "I hope [the government] will put investment in to ensure that our people are not bullied and that the children understand that's not acceptable and that we build inclusion and social cohesion across our community, in our workplaces and in our schools," she said. Sign up for Ngā Pitopito Kōrero , a daily newsletter curated by our editors and delivered straight to your inbox every weekday.

Air New Zealand's online payment system down
Air New Zealand's online payment system down

RNZ News

time7 hours ago

  • RNZ News

Air New Zealand's online payment system down

A Boeing Dreamliner 787, from the Air New Zealand fleet. Photo: Supplied/ Air NZ Air New Zealand customers are unable to make online bookings due to a problem with the company's online payment system. "We are currently experiencing an issue with our online payment systems," the airline said on social media. "Customers can't make payments for bookings through our website or app." Air NZ said in-person payments at airports and the Airpoints Store are no affected. "Our teams are working hard to fix the problem and get things running again as quickly as possible," Air NZ said. "We apologise for the inconvenience and appreciate your patience while we work through this." Sign up for Ngā Pitopito Kōrero , a daily newsletter curated by our editors and delivered straight to your inbox every weekday.

The Panel with Anna Dean and Ed McKnight Part 1
The Panel with Anna Dean and Ed McKnight Part 1

RNZ News

time7 hours ago

  • RNZ News

The Panel with Anna Dean and Ed McKnight Part 1

Professor Michael Baker Photo: Supplied / Luke Pilkinton-Ching Tonight, on The Panel, Wallace Chapman is joined by panellists Anna Dean and Ed McKnight. First up, he government has confirmed how much it cost us to break the contract with South Korean ship builders for new ferries: $144 million. Was it worth it? then everyone is coming down with winter colds and illnesses - it feels bad this year, but is it? Public health expert Michael Baker says it's actually pretty normal.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store