A fight is brewing in Indiana over who should pay Big Tech's energy bills
Gov. Mike Braun is expected to sign a bill that would require large energy users like Big Tech's AI data centers to cover 80% of the costs of new power needed to run them if they seek a faster regulatory approval process, making it the first state to do so.
A second law Braun recently signed allows utilities to pass the cost to consumers of exploring a source of power that isn't operating at scale in the US yet. Big Tech companies have bet that a new generation of "small modular nuclear reactors," or SMRs, could soon provide around-the-clock power to data centers.
Consumer advocates said the two bills will ultimately hike energy bills for everyday Hoosiers and put them on the hook for nuclear projects that may never get up and running.
The debate in Indiana reflects one playing out across the country over the cost and environmental implications of the spike in energy demand from AI data centers.
Kerwin Olson, executive director of Citizens Action Coalition, a consumer advocacy group, called the bills "a disaster for Hoosier ratepayers" and said it will "exacerbate the utility affordability crisis."
Republican Rep. Ed Soliday, who co-sponsored the bills, other GOP lawmakers, and a trade group representing utilities in Indiana argued the bills contain sufficient safeguards for consumers and that SMRs are the future of clean and affordable energy as demand from data centers and new manufacturing plants grows.
Indiana's $15 billion data center pipeline
While Indiana doesn't top the list of major US data center hubs, the Rust Belt state is attracting more development due to tax incentives and a reliable power supply.
Big Tech companies, including Amazon Web Services, Google, Microsoft, and Meta, plan to invest about $15 billion combined in Indiana. In January, President Donald Trump announced that a billionaire in Dubai planned to invest $20 billion in data centers across the US, including in Indiana.
Data centers require around-the-clock electricity to power and cool the racks of servers fundamental to cloud computing and storage. These projects could demand thousands of megawatts of electricity by 2035 — more power than the nearly 7 million residents in Indiana combined, according to utility forecasts analyzed by the Citizens Action Coalition.
A bet on small nuclear
So far, most of the demand is expected to be met by fossil fuels. But many tech companies and utilities have promised to shift to cleaner energy and are therefore exploring SMRs, which don't produce carbon emissions.
SMRs are about one-third the size of traditional nuclear power plants, which could make them less expensive and quicker to build. To date, none are operating in the US, and only a few exist in Russia and China. It's unclear when the first plant might come online, with forecasts range from five to 15 years.
Cost estimates for SMR projects vary widely, from $2.4 billion to $4 billion, depending on the start-up.
A law Braun signed in April allows utilities to recoup the costs of exploring SMR projects from customers, even if they never supply power to the grid.
The utility Indiana Michigan Power is evaluating the potential of SMRs at a coal-fired plant in Rockport, and the aerospace manufacturer Rolls-Royce is considering SMRs for a plant in Indianapolis.
Soliday told Business Insider that allowing utilities to recover dollars from customers in real time for their early-stage activities will save Indiana residents money in the long run. Otherwise, utilities would have to fund the projects by raising capital, leading to extra costs that residents would ultimately pay for, he said. Soliday added that state regulators must approve the costs and determine they aren't overly expensive for customers.
Democratic Rep. Matt Pierce, who opposed the law, said it isn't fair to let utilities burn money investigating a technology that may never produce power, and then charge customers for it. Pierce noted that a federally funded SMR project by NuScale Power in Utah was canceled in 2023 due in part to escalating costs.
Braun appeared to agree in February, when he told News 10 that he supported nuclear power but that utilities should shoulder the costs. "They are out there as investor-owned, and some of that is going to have to be the risk that they take," Braun said.
When asked why he signed a law allowing the opposite, Braun's spokesperson, Griffin Reid, said it would address Indiana's high energy demand.
"Indiana is committed to pursuing diverse generation options, from fossil fuels to renewable energy to nuclear power, wherever they prove practical," Reid said.
Critics call out loopholes
Consumer advocates said the other bill passed by Indiana legislators isn't broad enough to shield residents from higher energy bills to cover the cost of new infrastructure for AI data centers.
While the bill requires tech companies to pay for 80% of the new power generation needed to serve them, this requirement is not guaranteed to apply to every project.
Danielle McGrath, president of the Indiana Energy Association, said in an email that the 80% requirement only applies if utilities pursue the new voluntary, fast-tracked approval process for big power projects.
"The legislation addressed concerns expressed by some large customers that speed was critical to their decision making and that longer timelines could serve as a deterrent to locating their projects," McGrath said.
Pierce and Olson said utilities can pursue other pathways outside the new fast-track process to recover the costs of new power plants and other infrastructure, which could ultimately raise customer rates. That includes special contracts hidden from public view that may not require large energy users like data centers to pay 80% of the bill.
Soliday told BI that the 80% cost-share applies no matter what pathway utilities seek to get projects approved by state regulators.
"You are not going to get any utility to build in the state of Indiana for a large load customer without that customer paying 80%," Soliday said. "Whether they take plan A or B to get there, they're paying it."
New infrastructure needed to serve Indiana Michigan Power's pipeline of data centers could cost up to $1 billion, according to a cost-share agreement the utility reached with the Citizens Action Coalition, Amazon Data Services, Google, Microsoft, and others.
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles
Yahoo
21 minutes ago
- Yahoo
Nvidia's $4.5 Trillion Market Cap Tops All 2,000 Russell Small-Caps Combined
Nvidia (NASDAQ:NVDA) just hit another mind-bending milestone. The chip giant's market cap has swelled to $4.5 trillion, putting it $1.5 trillion above the entire Russell 2000 index. That means one company is now worth more than 2,000 small U.S. firms combined. Warning! GuruFocus has detected 5 Warning Signs with NVDA. It's a snapshot of where the market's energy really is. While small-caps grind along, mega-cap tech led by Nvidia keeps sucking up the oxygen. The comparison shows how lopsided the rally has become, with AI demand fueling outsized gains for a handful of giants. Nvidia isn't just dominating in price. It's woven into the core of global investing. The stock sits inside 667 ETFs, which together control nearly 3.6 billion shares. Whether through passive funds or active bets, chances are, most investors already own a slice of Nvidia. That reach makes every tick of its stock ripple across portfolios worldwide. Nvidia isn't just a chipmaker anymore it's become a market-moving force, one whose valuation now rivals entire economies. This article first appeared on GuruFocus. Sign in to access your portfolio
Yahoo
21 minutes ago
- Yahoo
Terawulf (WULF) Jumps 78.3% on Google Backing
We recently published . Terawulf Inc. (NASDAQ:WULF) is one of the last week's top performers. Terawulf soared by 78.3 percent week-on-week as investors loaded up positions after earning financial backing from Google for the delivery of critical IT load to a premier AI cloud platform. In a statement on Thursday, Terawulf Inc. (NASDAQ:WULF) said it entered into an agreement with Fluidstack for the delivery of 200 MW of critical IT load at its Lake Mariner data center campus in Western New York. The agreements represent approximately $3.7 billion in contracted revenue over the initial 10-year term, with an option for two five-year extensions, which, if exercised, would bring the total contract revenue to $8.7 billion. According to Terawulf Inc. (NASDAQ:WULF), it received a $1.8-billion fund backing from Google to support project-related debt financing for the Fluidstack project, in exchange for warrants covering 41 million WULF common shares or 8 percent pro-forma equity. The first phase of deployment will involve 40 MW of critical IT load and is expected to come online in the first half of 2026, with the remaining 160 MW targeted for completion by year-end. Image by Лечение Наркомании from Pixabay In addition to Google's backstop, Terawulf Inc. (NASDAQ:WULF) announced its intention to access the capital market, but did not elaborate on whether in the form of debt or share sale. While we acknowledge the potential of WULF as an investment, our conviction lies in the belief that some AI stocks hold greater promise for delivering higher returns and have limited downside risk. If you are looking for an extremely cheap AI stock that is also a major beneficiary of Trump tariffs and onshoring, see our free report on the . Error in retrieving data Sign in to access your portfolio Error in retrieving data Error in retrieving data Error in retrieving data Error in retrieving data
Yahoo
21 minutes ago
- Yahoo
Google Bets on Nuclear to Power AI Data Centers by 2030
Google (NASDAQ:GOOGL) is turning to nuclear power to keep its AI-fueled future running. On Monday, the company said it's building its first small modular reactor (SMR) in Tennessee, with energy expected to start flowing by 2030. Warning! GuruFocus has detected 5 Warning Signs with VWDRY. The deal could deliver about 500 megawatts of capacity for Google's data centers in Tennessee and Alabama, using Kairos Power's advanced reactor technology in partnership with the Tennessee Valley Authority (TVA). TVA CEO Don Moul framed the project as bigger than just Google's energy needs. Nuclear is the bedrock of the future of energy security, he said, adding that Google's investment helps shoulder the cost and risk of developing new nuclear tech without passing the burden to TVA's 10 million customers. It's the latest sign of how energy-intensive AI has become. Back in October, Google signed deals to source power from multiple SMRs. This Tennessee project shows the company is willing to bet on first-of-its-kind nuclear solutions to keep its data centers and AI ambitions running on clean, steady power. This article first appeared on GuruFocus. Sign in to access your portfolio