Long-awaited road safety upgrade in Navan delayed over funding shortfall
She specifically questioned the causes behind the postponement and asked whether interim safety measures would be introduced in light of persistent red light violations and illegal exits from the Circle K service station, and the 'serious risk' to schoolchildren attending St. Oliver Plunkett and St. Paul's Primary Schools.
Last year, a major new safety scheme on the Proudstown Road at the junction of Beaufort Place, Blackcastle, and the Circle K garage was unveiled to councillors at a meeting. The proposals include two additional controlled pedestrian crossings: one just off the junction at the entrance to Blackcastle and St. Oliver's Church, and one on the main road north of Circle K close to the bus stop.
In its response, the Council confirmed that while the scheme has reached "shovel-ready" stage — with key components in stock, road safety audits completed, and ESB connections secured — the project was shelved after 'tender prices returned were significantly higher than budget forecasts.'
'The Local Authority did not have availability of additional funds and resources to deliver the project in its original planned form due to other commitments of delivering the LDR4 project requiring the upgrade of the Proudstown x Clonmageddan Road junction,' the Council said.
'We are also in discussions with the Circle K service station to get entrance and boundary works completed which will control the entry and exit of vehicles from the station into the junction. These works are required to be completed by the service station prior to delivery of the planned scheme.'
Meath County Council added: 'The scheme is at shovel ready stage with ESB connection agreements in place, Road Safety Audits completed and critical long lead time components in stock, however the required funding is still outstanding.'
Despite the funding gap, the council said they are currently in talks with the National Transport Authority (NTA) to secure partial funding that would allow for the installation of controlled pedestrian crossings. These would serve the children attending St. Oliver Plunkett and St. Paul's Primary Schools, both located within the high-risk zone.
'St. Oliver's School is on the Safe Routes to School programme for next year,' the council said, 'but we intend to deliver the controlled crossings this year, subject to the funding being made available.'
Speaking after the meeting, Cllr Adenuga said the delay was 'disappointing'.
'This is really disappointing and somewhat frustrating. I know that many will feel the same. I will keep pressing for the progress of this project,' she said.

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles

The Journal
3 days ago
- The Journal
Dublin City Council refuses permission for operator to rent 10 apartments near Temple Bar
DUBLIN CITY COUNCIL has refused planning retention to a significant Airbnb operator close to Dublin Castle and Temple Bar to continue offering its apartments for short term letting to tourists. Dublin Castle Suites advertises its 10 apartments on the AirBnB platform and can earn up to €350 per night per apartment on busy weekends. The owner of the apartments, facing onto Parliament Street and Dame Street, would earn only a fraction of its current rental income if the apartments are to be rented for long-term letting only. A question mark has now been put over the lucrative enterprise following the City Council's decision to refuse planning retention to allow the apartments to be continued to be used for short term letting. Applicants Olympia Real Estate Limited now have the option of appealing the decision to An Coimisiún Pleanála, which may reverse the council's planning refusal. However, in its decision, the city council pointed out that there is a general presumption in the Dublin City Council Development Plan against the provision of dedicated short term tourist rental accommodation in the city due to the impact on the availability of housing stock. In refusing planning permission, the Council stated that Olympia Real Estate Ltd has not provided a sufficient justification for the provision of short lease apartments at this location. The Council found that the proposal to continue the apartments for short term letting 'would create an undesirable precedent for similar type development and would devalue property in the vicinity'. Advertisement The planners concluded that the proposed retention of short-term residential use is not compatible with the architectural character, historic fabric and special interests of the protected structure. The Council planning report which recommended a refusal concluded that the continued use of the apartments for tourist accommodation 'would result in existing residential stock being lost to the residential housing system, meaning less long-term and secure accommodation will be available to the growing number of families and people who need it'. Olympia Real Estate Limited lodged the planning application after the Council issued it with a Warning Letter over the use of the apartments for short-term letting. Planning consultants for the applicants, Cunnane Stratton Reynolds (CSR) state that 'enabling housing as short term let accommodation in this instance redirects such demand away from mainstream housing'. The consultants state that 'the proposed tourism accommodation will assist in the attractiveness of the area for tourists and will promote a continued busy and vibrant city centre'. CSR state that its client's ability to acoustically meet the standards of normal accommodation is not available given the protected status of the subject premises. They state 'in a period of substantial housing crisis these units cannot remain vacant'. Objecting to the planned retention, Fiachra Brennan of Oakcourt Park, Dublin 20 and who works on Parliament Street said that 'these are high-quality urban apartments which should be available on the long-term rental market'. He said: 'The applicant has pointed to issues with regards to soundproofing and insulation – this should not preclude the use of the property for its intended purpose. He added: 'I work on Parliament Street – it is a vibrant area with a range of commercial and hospitality businesses but is also an important urban, residential city neighbourhood. This status should be protected.'


RTÉ News
4 days ago
- RTÉ News
Dublin City Council refuses planning retention to AirBnb operator
Dublin City Council has refused planning retention to a significant Airbnb operator close to Dublin Castle and Temple Bar to continue offering its apartments for short term letting to tourists. Dublin Castle Suites advertises its 10 apartments on the AirBnB platform and can earn up to €350 per night per apartment on busy weekends. The owner of the apartments facing onto Parliament Street and Dame Street would earn only a fraction of its current rental income if the apartments are to be rented for long-term letting only. A question mark has now been put over the lucrative enterprise following the City Council's decision to refuse planning retention to allow the apartments to be continued to be used for short term letting. Applicants, Olympia Real Estate Limited now have the option of appealing the decision to An Coimisiún Pleanála which may reverse the council's planning refusal. However, in its decision, the city council pointed out that there is a general presumption in the Dublin City Council Development Plan against the provision of dedicated short term tourist rental accommodation in the city due to the impact on the availability of housing stock. In refusing planning permission, the Council stated that Olympia Real Estate Ltd has not provided a sufficient justification for the provision of short lease apartments at this location. The Council found that the proposal to continue the apartments for short term letting "would create an undesirable precedent for similar type development and would devalue property in the vicinity". The planners concluded that the proposed retention of short-term residential use is not compatible with the architectural character, historic fabric and special interests of the protected structure. The Council planning report which recommended a refusal concluded that the continued use of the apartments for tourist accommodation "would result in existing residential stock being lost to the residential housing system, meaning less long-term and secure accommodation will be available to the growing number of families and people who need it". Olympia Real Estate Limited lodged the planning application after the Council issued it with a Warning Letter over the use of the apartments for short-term letting. Planning consultants for the applicants, Cunnane Stratton Reynolds (CSR) state that "enabling housing as short term let accommodation in this instance redirects such demand away from mainstream housing". The consultants state that "the proposed tourism accommodation will assist in the attractiveness of the area for tourists and will promote a continued busy and vibrant city centre". CSR state that its client's ability to acoustically meet the standards of normal accommodation is not available given the protected status of the subject premises. They state "in a period of substantial housing crisis these units cannot remain vacant". Objecting to the planned retention, Fiachra Brennan of Oakcourt Park, Dublin 20 and who works on Parliament Street said that "these are high-quality urban apartments which should be available on the long-term rental market". He said: "The applicant has pointed to issues with regards to soundproofing and insulation – this should not preclude the use of the property for its intended purpose. He added: "I work on Parliament Street – it is a vibrant area with a range of commercial and hospitality businesses but is also an important urban, residential city neighbourhood. This status should be protected."

Irish Times
5 days ago
- Irish Times
Cash not the issue for Government but how to spend it wisely, Ifac boss briefed ahead of committee
The Apple tax windfall, the budgetary impact of migration and value for money in the health service were likely questions flagged to Irish Fiscal Advisory Council (Ifac) chairman Seamus Coffey in briefings by his officials in advance of an Oireachtas appearance. Two Q&A documents were prepared for Mr Coffey in advance of the meeting of the committee on budgetary oversight in early July – one highlighting issues likely to be 'pertinent now' while the other looked at questions that arose 'consistently. 'On what to do with the €13.8 billion Apple tax windfall, a suggested answer for Mr Coffey said to remember the Government 'is not stuck for cash.' It said: '[The State] is stuck for its capacity to spend it on things we all want. There are three broad options – spend it, save it, [or] cut debt.' READ MORE The Q&A said spending it on housing was easier said than done as the biggest issues were 'construction sector capacity and planning bottlenecks' not the availability of cash. If asked about the budgetary implications of migration, the briefing noted there had been 'large increases' in numbers coming to Ireland in recent years. 'This has meant the labour force and employment has been able to grow as rapidly as it has in recent years,' it said, before noting that around €2.1 billion 'has been set aside for humanitarian assistance to refugees this year (€800 million of this is for Ukrainian refugees). 'In terms of future costs, these are uncertain,' the briefing note added. The Q&A said that getting migrants integrated into employment and their own homes would reduce costs for the Government. 'An increased supply of housing would mean some of the more expensive means of accommodation [hotels] may be replaced,' it said. On cost-of-living supports, which have been a big feature of recent budgets, the Ifac briefings said these were now 'likely permanent'. 'There is probably less of a case for once-off measures this winter,' the briefing document said. 'Permanent increases in social welfare could be targeted at specific groups. However, the measures have seldom been targeted.' Mr Coffey was also briefed on employment in construction and whether we needed more people working in that sector. 'Just over 6 per cent of all employment is in the construction sector,' his Q&A document noted, adding that between 2005 and 2007, this had reached over 10 per cent. 'This may have been unsustainable, however,' the briefing added, advising Mr Coffey to 'mention productivity, can we get more output from the same workforce?'. A Q&A on broader questions highlighted the challenges in creating a wealth tax that would be fair, not become an administrative burden, and collect enough money to make it worthwhile. On how to fix repeated overruns in health spending, the briefing said that 'poor budgeting' was a problem but that there was also evidence of 'reduced productivity'. It also explained how Ireland's failure to meet its climate targets carried a very real 'fiscal risk'. The Q&A said the State had already forgone €500 million from carbon credits it was entitled to sell and that costs of noncompliance were in the range of €8 billion and €26 billion. 'While several [EU] member states are projected to fall short, the potential costs are significantly higher for Ireland relative to the size of its economy,' the briefing noted. Asked about the records, Ifac said they had no further comment to make.