Public healthcare network making good progress

Public healthcare network making good progress

The Star3 days ago

THREE key expansion projects of Penang Hospital with a combined value of RM758mil, are currently progressing at various stages.
Penang health committee chairman Daniel Gooi Zi Sen said the first project, the Women and Children's Block, had reach 34.35% completion as of May 22.
'The first project worth RM307mil is scheduled for completion in January 2026,' he said in a press conference after a site visit at Jalan Residensi.
Gooi said the project was being implemented under a design-and-build tender system and included the construction of a 12-storey parking complex and an 8-storey hospital building with a 329-bed capacity alongside various specialised healthcare services.
The parking complex, he added, would be able to accommodate 449 cars at one time.
Gooi said the second project, the new Stem Cell Services Centre Block, valued at RM23mil, was expected to be completed by March 2027.
'Additional infrastructure includes 25 parking bays, a covered connecting bridge, support buildings (including a waste house and M&E room) and utility upgrades.
'This project is 10.19% completed as of May 29, with completion scheduled for March 2027,' he said
The Women and Children Block is 34.35% completed as of May 22. It is expected to be ready by January next year. — Photos: LIM BENG TATT/The Star
The project, he elaborated, was being carried out using the conventional method under the supervision of the Public Works Department (JKR).
He said the facility would enhance transplant-related services, including apheresis units, stem cell laboratories and other support facilities.
'The third project, the Specialist Clinic and Ward Block, with a budget of RM428mil, is projected to be completed by May 2029.
'The project is being developed through a conventional approach under JKR, where the 14-storey block will house specialist outpatient clinics and wards with a capacity of 216 beds,' he said.
He added that the project currently stood at 3.33% progress as of May 20, with completion targeted for May 2029.
Gooi said these expansion projects, when ready, would mark a significant enhancement to the state's healthcare system and facilities.
The projects represented strategic investments by the Federal Government to upgrade public healthcare infrastructure in the state under the 10th and 11th Malaysia plans, he said.
'We are grateful to the Federal Government for approving these allocations. This marks a significant milestone in enhancing healthcare services for the people of Penang.'
Gooi said the developments would not only strengthen Penang's healthcare system but also significantly improve the quality of medical services for its residents.
He said the state government, through his office, remained committed to enhancing the public healthcare network, closing the gap in treatment accessibility and ensuring quality, equitable and comprehensive services for all.
Gooi added that these initiatives aligned with the Penang2030 vision and the Malaysia Madani framework, which prioritised values of well-being, justice and compassion in the delivery of public services.
Penang Hospital is one of the oldest public hospitals in Malaysia, with a history dating back to the colonial era.
Located in George Town, it is the largest government hospital in the northern region and is a tertiary referral centre for Penang, Kedah, Perlis and northern Perak.
It was established in the 19th century during British rule to serve the growing population in Penang, which was then an important trading hub.
Post-independence, the hospital underwent several modernisation projects, with the addition of new medical departments, specialist units, and upgraded facilities.
Over the decades, it expanded to provide specialist medical care, catering to the increasing healthcare demands.
The hospital also played a crucial role in handling major health crises, including the Covid-19 pandemic where it served as a key treatment centre.

Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Public healthcare network making good progress
Public healthcare network making good progress

The Star

time3 days ago

  • The Star

Public healthcare network making good progress

THREE key expansion projects of Penang Hospital with a combined value of RM758mil, are currently progressing at various stages. Penang health committee chairman Daniel Gooi Zi Sen said the first project, the Women and Children's Block, had reach 34.35% completion as of May 22. 'The first project worth RM307mil is scheduled for completion in January 2026,' he said in a press conference after a site visit at Jalan Residensi. Gooi said the project was being implemented under a design-and-build tender system and included the construction of a 12-storey parking complex and an 8-storey hospital building with a 329-bed capacity alongside various specialised healthcare services. The parking complex, he added, would be able to accommodate 449 cars at one time. Gooi said the second project, the new Stem Cell Services Centre Block, valued at RM23mil, was expected to be completed by March 2027. 'Additional infrastructure includes 25 parking bays, a covered connecting bridge, support buildings (including a waste house and M&E room) and utility upgrades. 'This project is 10.19% completed as of May 29, with completion scheduled for March 2027,' he said The Women and Children Block is 34.35% completed as of May 22. It is expected to be ready by January next year. — Photos: LIM BENG TATT/The Star The project, he elaborated, was being carried out using the conventional method under the supervision of the Public Works Department (JKR). He said the facility would enhance transplant-related services, including apheresis units, stem cell laboratories and other support facilities. 'The third project, the Specialist Clinic and Ward Block, with a budget of RM428mil, is projected to be completed by May 2029. 'The project is being developed through a conventional approach under JKR, where the 14-storey block will house specialist outpatient clinics and wards with a capacity of 216 beds,' he said. He added that the project currently stood at 3.33% progress as of May 20, with completion targeted for May 2029. Gooi said these expansion projects, when ready, would mark a significant enhancement to the state's healthcare system and facilities. The projects represented strategic investments by the Federal Government to upgrade public healthcare infrastructure in the state under the 10th and 11th Malaysia plans, he said. 'We are grateful to the Federal Government for approving these allocations. This marks a significant milestone in enhancing healthcare services for the people of Penang.' Gooi said the developments would not only strengthen Penang's healthcare system but also significantly improve the quality of medical services for its residents. He said the state government, through his office, remained committed to enhancing the public healthcare network, closing the gap in treatment accessibility and ensuring quality, equitable and comprehensive services for all. Gooi added that these initiatives aligned with the Penang2030 vision and the Malaysia Madani framework, which prioritised values of well-being, justice and compassion in the delivery of public services. Penang Hospital is one of the oldest public hospitals in Malaysia, with a history dating back to the colonial era. Located in George Town, it is the largest government hospital in the northern region and is a tertiary referral centre for Penang, Kedah, Perlis and northern Perak. It was established in the 19th century during British rule to serve the growing population in Penang, which was then an important trading hub. Post-independence, the hospital underwent several modernisation projects, with the addition of new medical departments, specialist units, and upgraded facilities. Over the decades, it expanded to provide specialist medical care, catering to the increasing healthcare demands. The hospital also played a crucial role in handling major health crises, including the Covid-19 pandemic where it served as a key treatment centre.

Three major health projects underway at Penang Hospital
Three major health projects underway at Penang Hospital

New Straits Times

time6 days ago

  • New Straits Times

Three major health projects underway at Penang Hospital

GEORGE TOWN: Three health projects are ongoing at Penang Hospital here, backed by a federal allocation of RM758 million under the Malaysia Plan. State Youth, Sport and Health Committee chairman Daniel Gooi Zi Sen said these projects represented a critical upgrade to the state's healthcare infrastructure. The three projects are the RM307 million women and children's block, the RM23 million stem cell services block and the RM428 million specialist clinic and ward block. Gooi said the women and children's block involved demolishing the existing block and constructing an eight-storey hospital building with 329 beds and a 12-storey car park with 449 parking bays. "It includes major services such as outpatient and inpatient care, diagnostic and treatment units, medical support services, administrative offices, and public amenities including a cafeteria, surau and playground. "This block will consolidate all women and children's services, reducing congestion and eliminating the need for patients to access the main hospital block. "The project is currently 34.35 per cent completed as of May 22, and is targeted for completion by January 2026," he said during a visit to the women and children's block construction site here today. Gooi said the stem cell services block was aimed at upgrading stem cell transplant services, including allogeneic bone marrow transplant facilities, apheresis units and stem cell labs. He said additional infrastructure included 25 parking lots, a covered connecting bridge, support buildings (including a waste house and M&E room), and utility upgrades. "This project is 10.19 per cent completed as of May 29, with completion scheduled for March 2027. "As for the specialist clinic and ward block, this 14-storey building will house specialist clinics (levels 1–11) and wards (levels 12–14) with 216 beds, along with parking on levels 2–7 and mechanical facilities in the basement. "The project currently stands at 3.33 per cent progress as of May 20, with completion targeted for May 2029," he added. Gooi said that despite earlier delays due to the Covid-19 pandemic and handover constraints, construction had picked up pace, particularly following the piling phase. He said the implementation of the Industrialised Building System was expected to accelerate progress. "These upgrades will enhance public healthcare access, reduce overcrowding and resolve long-standing parking issues at the hospital. "These developments reflect the government's commitment to a more equitable, high-quality healthcare system," he said. Gooi said they would continue to strengthen public health infrastructure to ensure no one is left behind.

Penang Hospital's RM758m development projects progressing as planned, set for completion by 2029, says state exco
Penang Hospital's RM758m development projects progressing as planned, set for completion by 2029, says state exco

Malay Mail

time6 days ago

  • Malay Mail

Penang Hospital's RM758m development projects progressing as planned, set for completion by 2029, says state exco

GEORGE TOWN, May 30 — The three development projects at Penang Hospital costing a total RM758 million are on track for completion between 2026 and 2029. Penang Health, Youth and Sports committee chairman Gooi Zi Sen said the construction of the RM307 million Women and Children's Block is now 34.35 per cent complete and is expected to be completed by January 2026. 'The project includes a 12-storey car park and an eight-storey hospital building with a capacity of 329 beds,' he said when visiting the construction site today. The block will consist of eight main services, including outpatient and inpatient service, diagnostic and treatment, medical support, administrative offices, medical staff services and public amenities such as a cafeteria, a playground and a surau. He said the second project, a new Stem Cell Centre Block, costs about RM23 million and is expected to be completed in March 2027. He said the project is being carried out under the supervision of the Public Works Department. 'The scope of the project includes upgrading transplant services, such as an Allogeneic bone marrow transplant, an Apheresis unit and a stem cell laboratory,' he said. He said the block will include 25 car park lots, a connecting overhead bridge and other auxiliary buildings. The third project is the RM428 million Specialist Clinic and Ward, which is expected to be completed by May 2029. 'The scope of the project includes a 14-storey building with 500 parking spaces, specialist clinics and a ward with a 216-bed capacity,' he said. All three projects are funded by Putrajaya under the 10th and 11th Malaysia Plans. Gooi thanked the federal government for approving the allocation for the projects as it will improve the infrastructure and facilities at Penang Hospital. 'These projects will strengthen the state's healthcare service system and will improve the quality of treatment for patients,' he said. He said the state government will continue to strengthen the public health system and ensure access to treatment for all.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into the world of global news and events? Download our app today from your preferred app store and start exploring.
app-storeplay-store