'India's longest-pending rail project': Train to this Punjab village delayed by 40 years; Rs 2,000 crore project limps at 87% completion
Punjab
have slowed the completion of the railway line — from
Nangal Dam
to Talwara — making it one of the longest-pending projects in the country
Can you tell us when the train will come?' Jatinderpal Singh, 62, asks, with the leaden tone of one who knows the answer. After all, he was a boy when he first asked this question. His village, Bringali, situated on the banks of the Beas in Punjab's Talwara, some 200km from Chandigarh, is a dusty dot on a nearly four-decade-old railway plan.
Sanctioned in 1981-'82 and initiated in the summer of 1985, the central govt project involves laying a new broad-gauge railway line from Nangal Dam to Mukerian via Talwara.
At an estimated cost of over Rs 2,000 crore, the project aims to provide seamless rail connectivity in the hilly regions of Punjab and Himachal Pradesh. Progress has crawled to 87% after four decades, making it one of the longest -pending projects in the country.
Hurdles in land acquisition, environmental clearances, and relocation of utilities in Punjab have taken the steam out of the work.
Now, there is a renewed attempt to pump some energy into the project. Prime Minister Narendra Modi has himself reviewed the project and warned against further delays even as residents remain sceptical. At present, it is stalled in the Mukerian-Talwara range due to problems in obtaining permission for digging in Punjab.
by Taboola
by Taboola
Sponsored Links
Sponsored Links
Promoted Links
Promoted Links
You May Like
Gentle, Needle-Free Way to Monitor Blood Sugar—Now Being Tried by Seniors
Zakdavi
Undo
Need Of The Hour
For the project's completion, Punjab needs to expedite the acquisition of approximately 72 hectares of land. Additionally, the railways, the state govt, and the environment ministry must accelerate forest clearance for the extraction of earth in the state. Sources say the railway ministry has taken up the issue with the environment ministry. While the paperwork drags on and the project crawls, another generation has filled the gap years, and a new set of youngsters is hearing of the train that will come someday.
Dream Deferred
Jatinderpal, whose family has stayed in Bringali for 300 years, says: 'Our hopes were raised when surveys were conducted in 1976 to acquire land for the construction of an elevated rail corridor from Daulatpur Chowk in Himachal to Talwara. I was so young, and we were so enthusiastic about the project that each day we used to accompany the project teams to watch them work on demarcation lines. We can still point out the spots,' he told TOI .
Point pillars were installed back then to demarcate the land, and the project was formally notified in 1981. 'The project was to be initiated in 1985, and some construction started, but look around, and look at me. I am 62 years old and still waiting for the train to arrive,' he said.
So far, a 60km section from Nangal Dam has been completed and is operational up to Daulatpur Chowk. Work is progressing rapidly on the remaining 23.7km elevated corridor between Daulatpur Chowk and Talwara, which is almost 50% complete.
However, sources in the railways ministry confirmed that a critical 2.5km to 3km stretch of land near Talwara is still pending acquisition, posing the final hurdle to the project.
For many, the rail line is not just infrastructure — it's a dream deferred. 'I'm nearly 70, still waiting to ride the train through my village,' said a local landowner.
'Unequal Terms'
Dissatisfaction over compensation remains a sore point. Many landowners allege they were paid far below fair value for their property.
'In Himachal, land was acquired at Rs 1 lakh per marla (25.3 sqm), while in Punjab we were offered only Rs 8,500 per marla,' said a landowner. Several residents have refused to accept the compensation and have moved acourt, demanding either higher payouts or land pooling in exchange.
While some payments have already been disbursed, residents from villages near Talwara are pressing for a more equitable settlement. 'We are not against the project,' said a farmer, 'but we want justice.
Give us land against land or pay us fairly.'
Wait May End Soon
The rail link is being built by three major construction firms — NP Jain Construction Company, RKC Company, and HMM Infrastructure — with RKC handling the bulk of the elevated corridor. Despite delays and disputes, officials remain optimistic that the railway line will be completed by Dec 31, 2027. Those who have waited four decades say they can wait two more years, but you can sense the scepticism in their tone.
In the last monthly Pragati meeting, a web-based platform aimed at ensuring the timely implementation of govt initiatives, PM Modi reviewed this project along with two others — the North Koel Reservoir Project in Bihar-Jharkhand, and the 5th Stream Refinery Expansion at Nalco's plant in Odisha, delayed by six years and one year, respectively.
In the meeting with secretaries at the state and central level, the officials concerned were directed to expedite the projects, said sources. The PM underlined that delays in project execution came at the 'dual cost of escalating financial outlays and denying citizens timely access to essential services and infrastructure.'
Officials said that unhappy with the inordinate delay, the Prime Minister would take a separate review of the project this month.

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Time of India
22 minutes ago
- Time of India
Janmashtami to be celebrated at every police station: Yogi
1 2 Lucknow: Chief Minister Yogi Adityanath on Wednesday said Janmashtami would be celebrated at every police station and police training institute in the state on Aug 16. "The occasion would provide trainees with an opportunity to showcase their cultural and artistic talents, making the festival a symbol of cultural unity," Yogi made this announcement during his visit to Moradabad where he inaugurated and laid foundation stones for 87 development projects worth Rs 1,172 crore. Accusing the Samajwadi Party of having tried to restrict Janmashtami celebrations when it was in power, Yogi said his govt would ensure grand celebrations across the state. Referring to the result of the Kundarki bypoll held in Nov 2024, where BJP trumped the SP candidate in a Muslim majority area, the CM called it Moradabad's rejection of SP's and Congress' divisive politics. "The public chose satisfaction over appeasement, leading to the forfeiture of SP-Congress deposits," he said. Highlighting the global recognition which Moradabad's handicraft are getting, the CM said "It was the commitment of BJP's double-engine government to elevate the city and its products on the world stage. Once known for chaos and hooliganism, Moradabad is now renowned for its excellent handicrafts and brass items under the ODOP scheme, exporting products worth Rs 11,000 to Rs 15,000 crore." He added that Moradabad's artists, including one who received a Padma award, are working tirelessly to realise Prime Minister Narendra Modi's vision of a self-reliant India. Sponsored Links Sponsored Links Promoted Links Promoted Links You May Like Most Luxurious Hotels in the World Learn More Undo by Taboola by Taboola The CM urged people to gift Swadeshi or locally made products to friends and families during festivals to promote local talent and encourage local economies. The CM also linked Raksha Bandhan and the Kakori Train Action anniversary, which are falling on the same day this year. He paid tributes to revolutionaries like Ram Prasad Bismil, Ashfaqullah Khan, Thakur Roshan Singh, Rajendra Prasad Lahiri and Chandrashekhar Azad, who sacrificed their lives for the country's freedom.


Time of India
22 minutes ago
- Time of India
Kadoor panchayat brings governance to citizens' doorsteps
Udupi: In a move that redefines grassroots governance, the Kadoor gram panchayat in Brahmavar taluk is taking administration directly to the people right at their doorsteps. Under the innovative 'Janavasati Kade Namma Nade' initiative, the panchayat has moved beyond traditional practices where citizens must visit the office for services. Instead, every 15-20 days, a special public meeting is held in residential clusters, often at a local home, anganwadi centre, or another central location, making governance more accessible, inclusive, and responsive. What sets these meetings apart is their action-oriented approach, said panchayat development officer Mahesh K. He said they are not mere information-sharing sessions. Govt officials and elected representatives from departments like health, women and child development, revenue, and panchayat attend these gatherings, offering services such as accepting grievances and scheme applications, conducting on-the-spot health checkups, inspecting local infrastructure, collecting house and sanitation taxes, and resolving issues immediately whenever possible. The meetings are strategically held after 4pm to ensure that working citizens, particularly daily wage labourers, can attend. This timing has led to higher participation and greater impact. "Several health issues were identified and addressed during these sessions. A colony in Kalrashi is now seen as a problem-free zone thanks to timely interventions," said Jalandhar Shetty, president, Kadoor GP. Meetings are held with a minimum of five houses, and hence we can focus on development, health of individuals, and implementation of MGNREGA. by Taboola by Taboola Sponsored Links Sponsored Links Promoted Links Promoted Links You May Like She Was The Dream Girl In The 1980s, Here She Is Now. Boite A Scoop Undo Several issues in the Koraga colony have been solved. While many local-level meetings are limited to collecting grievances, these 'Janavasati Kade Namma Nade' meetings go further; they identify and solve problems right at the source, he added. The PDO said that with all department officials available near citizens' homes, even routine tasks like house tax collection become easier and more efficient. "The initiative has been widely appreciated for setting a new benchmark in participatory governance," the PDO added. Zilla panchayat CEO Prateek Bayal said, "Mandatory gram sabhas and ward meetings are crucial at the local level. But this is an excellent concept as they lay a strong foundation for better planning and effective scheme implementation. " So far, eight meetings have been held, and it is seen as a win-win situation for the public as well as for the panchayat.


Time of India
22 minutes ago
- Time of India
Govt engages Tata Tech to upgrade state polytechnics
Lucknow: The UP govt in collaboration with Tata Technology Limited (TTL) would set up Tata Technology Excellence Centres in 121 govt polytechnics across the state to help these technical educational institutes meet industry requirements. In a govt order (GO), additional chief secretary, technical education, Narendra Bhooshan said the decision was taken to bridge the industry-academia gap prevalent in the diploma sector of technical education. "In polytechnics, some topics have become irrelevant or are not in accordance with industry requirements. These centres will upgrade them and bridged the industry-academia gap," Bhooshan said. For this, Rs 57.3 crore will be spent on installation of machines and equipment in each of the 121 polytechnics. Of the total Rs 6935.8 crore, 87%, that is, Rs 6034.2 crore, will be borne by TTL, and the remaining 13% (Rs 1063.9 crore) by the govt. Also, the state govt will spend an additional Rs 858 crore – Rs 709.2 lakh per institution – towards civil infrastructure and other basic facilities. In the first phase, 45 polytechnic institutions will be upgraded. The project is aimed at providing quality technical education to students studying in the diploma sector of the state, thereby enhancing employment. by Taboola by Taboola Sponsored Links Sponsored Links Promoted Links Promoted Links You May Like How Retirees Can Potentially Minimize RMD Taxes SmartAsset Learn More Undo It will also help students acquire essential skills like soft skills and personality development as per industry requirements. As per the GO, TTL will involve global partner companies and institutions in upgrading the polytechnics. TTL will also prepare the project document related to the execution of the upgradation work and determine short, medium, and long-term strategies in it. In addition, they will prepare a baseline study report related to the status of the polytechnic institutions before the implementation of the project. TTL will also make available two trainers for the first two years and one trainer for the third year in each selected institute from its own sources. Besides, it will ensure the availability of training material, an online platform for training, and experts from industries as per demand in all 121 institutes and organise dialogue programmes at regular intervals.