Six years late and £28bn over budget, this project signals disaster for Ed Miliband's nuclear plans

Six years late and £28bn over budget, this project signals disaster for Ed Miliband's nuclear plans

Telegrapha day ago

'Build and repeat.' That is the plan for Sizewell C, the nuclear plant on the Suffolk coast which Ed Miliband has announced plans to pump billions of pounds into. Writing in The Telegraph, he hailed a new 'golden age' for the British nuclear industry, pledging £14.2 billion for two reactors at Sizewell which will, eventually, provide six million homes with electricity.
Eventually being the operative word. News that the Government is throwing its weight behind nuclear in the midst of the Energy Secretary's pursuit of net zero was met with relief by some campaigners – and, indeed, by anyone who doesn't want to find themselves plunged into darkness if the grid is forced to grapple with unreliable renewables. But concerns have been raised about the modelling. Sizewell is to be a rinse and repeat of Hinkley Point C, the two-reactor power station in Somerset which has been beset with problems from the moment EDF first broke ground there in early 2017.
The Government says it's to be almost an exact replica. Meanwhile on its website, Sizewell C points to 'the benefits of replication'. 'Sizewell C will use the same design as Hinkley Point C,' it adds.
It says Hinkley has already 'created a huge workforce and supply chain' and that replication 'means Sizewell C will benefit from all the efficiencies and expertise learnt by our sister project'.
Efficiency and expertise. It's one way of summing up Hinkley, though it does rather overlook the £28 billion it has gone over budget to date, the endless delays and challenges from environmentalists, not to mention the international political tensions.
China's General Nuclear is a significant shareholder in the project, but in 2023 halted funding for it as relations between London and Beijing worsened; the same year the UK government took over the country's stake in Sizewell C.
Meanwhile, work at the site crawls on, its deadline shifting and bill expanding.
Still, EDF says Hinkley's second reactor is being built 25 per cent faster than the first unit, and suggests this should be taken as good news for Sizewell's envisaged two reactors, which are, effectively, planned to be the third and fourth in Britain's nuclear quartet.
Meanwhile, experts agree it makes sense in principle to transfer the lessons learnt and systems already established at the Somerset site to Suffolk. Iolo James, head of communications at the Nuclear Industry Association, stresses the importance of 'building in fleet rather than building one at a time'. 'The more you build, the cheaper and quicker that is,' he says.
That may be true, though there has been nothing cheap or quick about Britain's nuclear renaissance so far. Where we were once pioneers in the push for nuclear power (the world's first commercial-scale nuclear power station came online in Calder Hall, Cumbria, in 1956), decades of sparse investment have meant the UK has now fallen far behind other countries.
At Sizewell, many question how possible it will be in practice to shift operations from one side of England to the other. Alison Downes, of the campaign group Stop Sizewell C, suspects the idea that you can simply move teams and processes without a hitch is unrealistic. 'The company want people involved in Hinkley Point C to come over and do what they've done there again at Sizewell C, but unless there's a seamless transition and the roles that they're just finishing at Hinkley start at Sizewell, then the likelihood is those people will go off and find other jobs and then are lost to the supply chain,' she says.
'Hinkley has been delayed, yes, but Sizewell has also been delayed. It's very difficult to get two projects of this size to perfectly dovetail.'
Even if they do manage to bring some of that infrastructure across, it's hard to make the case that Hinkley has been a poster project for Britain's nuclear prowess.
Last February, EDF said it had taken a near £11 billion hit amid delays and overrunning costs on the project. The month before, it said the plant was expected to be completed by 2031 and cost up to £35 billion. Factoring in inflation, the real figure could be more like £46 billion.
It was, let's not forget, initially supposed to have started generating electricity in 2017 and cost £18 billion. When construction finally began the same year, it was expected that the plant would be completed by 2025.
It will now come online six years later than that and at more than double the cost of the initial estimate. So not, it would be fair to say, an unmitigated success as major infrastructure projects go.
Then again, some would argue successful infrastructure is an oxymoron in Britain today. The latest estimated spend for HS2 is £102 billion – almost double the projected cost. Crossrail cost £4 billion more than expected and weathered significant delays. And across the country, countless projects – bridges, tramlines and motorways – remain unfinished or unbuilt altogether.
'The public expectations on this sort of stuff is so low nowadays,' says Ed Shackle, a researcher at Public First. 'With all of these big promises – and that goes for things like HS2 as well – they are not expecting the Government to do anything. They're very sceptical that the Government could deliver anything big.'
The plan to launch us into a nuclear-powered future might sound promising, but can Labour get it done? While the public is supportive of the idea of projects like Sizewell in principle (Public First's polling shows there is a 41 per cent net support for the building of new nuclear power stations) and wants the Government to make big swings, time and again they have seen these things fail or fall by the wayside. 'They think the country is in a very bad way and we need major overhaul, but major projects have been poorly managed and delivered, and in their local areas, people see decline everywhere,' says Shackle.
'They want to see actual delivery behind these big promises.'
Downes points out the last update on Hinkley came in January last year, 'when there were still five or six years to go, so there was plenty of time for things to get even worse'. That same month, EDF said further delays were in the offing because of a row about fish. The energy company was struggling to agree protection measures for fish in the River Severn. Fears thousands could be killed in water cooling intakes had 'the potential to delay the operation of the power station'.
This was after months of tussling with environmentalists over the plant's seawater cooling system. At the time, Sir Keir Starmer, then in opposition, said delays to Hinkley were evidence of a system that was 'holding us back and stifling growth', citing 'countless examples of Nimbys and zealots gumming up the legal system often for their own ideological blind spots to stop the Government building the infrastructure the country needs'.
Now, dovetailing the construction of Sizewell with Hinkley is one of the main things bolstering confidence in the Suffolk project. Stuart Crooks, managing director of Hinkley Point C, said the 'innovation and experience' developed at Hinkley 'will benefit our twin project at Sizewell C from the start'.
'We have trained a new workforce and built the nuclear supply chain,' Crooks says. 'Now those skilled workers and businesses can give Britain the energy security and economic growth it needs at Sizewell C, together with small modular reactors and future large nuclear plants.'
Supporters also argue things will be different the second time around. The first nuclear build since the 1990s, Hinkley, they say, was always destined to take longer and cost more than initially predicted. 'It's been well documented that Hinkley has had issues in terms of going over budget, and the timescale,' says James. 'That's predominantly due to the fact that we haven't built a nuclear power station in a generation... We've had to relearn how to build them.
'The way Sizewell will benefit from that is all the learnings from Hinkley will be there for Sizewell and its team when it starts construction in earnest... If you view Sizewell C as unit three and four [after Hinkley's one and two], then you'll see the efficiencies become even greater for that project.'
Julia Pyke, joint managing director of Sizewell C, tells The Telegraph the site would be an 'exact copy, above ground, of Hinkley Point C'.
'When the design for Hinkley was brought into the UK, they had to make 7,000 design changes – because we're a copy, the equivalent for us is just 60,' she says.
'What that means in practical terms is that we know, in a way that Hinkley didn't know, how much concrete we need to pour, how much steel we need, how much cable we need to buy; we know how many hours it took to undertake a task for the first unit at Hinkley and the savings they were able to make for the second unit, and we can learn from that. We have a greater cost certainty because of that fixed design.'
It sounds promising, but campaigners are less optimistic, pointing out the significant geographical differences between the sites. 'I get the principals behind replication – but the thing you can't do is replicate the site,' says Downes, who understands Sizewell is set to be a more expensive site to develop than Hinkley.
'There are very specific complexities around the Sizewell C site... It's quite likely that any savings they might expect to make through replication will be absorbed in the more complex groundworks.'
While Hinkley is 'a dry site', Sizewell C is by the sea. 'It's going to need huge sea defences. They've got to build a crossing over a Site of Special Scientific Interest. They've got to build a deep cut-off wall. There's a lot of associated development that's needed because there's less infrastructure than there is down at Hinkley Point C. These are the sorts of things that concern us.'
The Energy Secretary, for his part, is still adamant this is to be the start of a 'golden age'. 'We will not accept the status quo of failing to invest in the future and energy insecurity for our country,' he said. 'We need new nuclear to deliver a golden age of clean energy abundance, because that is the only way to protect family finances, take back control of our energy, and tackle the climate crisis.'

Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Live Economy shrinks in blow for Reeves
Live Economy shrinks in blow for Reeves

Telegraph

time15 minutes ago

  • Telegraph

Live Economy shrinks in blow for Reeves

Britain's economy shrank at the start of the second quarter, official figures show, in a blow for the Chancellor after her spending review. UK gross domestic product (GDP) contracted by 0.3pc during the month, according to the Office for National Statistics (ONS). This was worse than analysts' fears that the economy would shrink by 0.1pc and follows a 0.7pc expansion during the first three months of the year. The data covers the month when Donald Trump launched his so-called 'liberation day' tariff onslaught which threatened to upend global trade. ONS director of economic statistics Liz McKeown said: 'After increasing for each of the four preceding months, April saw the largest monthly fall on record in goods exports to the United States with decreases seen across most types of goods, following the recent introduction of tariffs.' The figures come a day after economists warned that Britain faces tax rises in the autumn after Rachel Reeves unveiled her spending review. The Chancellor has made growing the economy one of her key missions as she battles to shore up the public finances. An expanding economy would mean that she is better able to pay off the nation's debt and would improve living standards. Ms Reeves said: 'Our number one mission is delivering growth to put more money in people's pockets through our Plan for Change, and while these numbers are clearly disappointing, I'm determined to deliver on that mission.'

UK economy shrunk in April as tax rises kicked in
UK economy shrunk in April as tax rises kicked in

BBC News

time19 minutes ago

  • BBC News

UK economy shrunk in April as tax rises kicked in

The UK economy shrunk by more than expected in April as tax increases kicked in for employers and British exporters faced huge uncertainty over US trade economy contracted by 0.3%, with the services sector being particularly hard hit. Economists had predicted a 0.1% April, employers' National Insurance rose while energy, water and council tax bills increased for figures come after a day after chancellor Rachel Reeves set out spending plans aimed at boosting growth, with funding increases for the NHS and defence, but budgets squeezed elsewhere.

Britain morphing into ‘National Health State', says think tank
Britain morphing into ‘National Health State', says think tank

The Independent

time20 minutes ago

  • The Independent

Britain morphing into ‘National Health State', says think tank

Britain is turning into a 'National Health State', a think tank has said after the Chancellor gave the NHS a major funding boost in her spending review. The health service was the big winner of Wednesday's spending review, receiving an extra £29 billion per year for day-to-day spending and more cash for capital investment. Overnight, the Resolution Foundation said Rachel Reeves's announcements had followed a recent trend that saw increases for the NHS come at the expense of other public services. Ruth Curtice, chief executive of the Resolution Foundation, said: 'Health accounted for 90% of the extra public service spending, continuing a trend that is seeing the British state morph into a National Health State, with half of public service spending set to be on health by the end of the decade.' Defence was another of Wednesday's winners, Ms Curtice said, receiving a significant increase in capital spending while other departments saw an overall £3.6 billion real-terms cut in investment. The Institute for Fiscal Studies (IFS) made similar arguments about 'substantial' investment in the NHS and defence coming at the expense of other departments, although the think tank's director Paul Johnson warned the money may not be enough. He said: 'Aiming to get back to meeting the NHS 18-week target for hospital waiting times within this Parliament is enormously ambitious – an NHS funding settlement below the long-run average might not measure up. 'And on defence, it's entirely possible that an increase in the Nato spending target will mean that maintaining defence spending at 2.6% of GDP no longer cuts the mustard.' Ms Curtice added that low and middle-income families had also done well out of the spending review 'after two rounds of painful tax rises and welfare cuts', with the poorest fifth of families benefiting from an average of £1,700 in extra spending on schools, hospitals and the police. She warned that, without economic growth, another round of tax rises was likely to come in the autumn as the Chancellor seeks to balance the books. She said: 'The extra money in this spending review has already been accounted for in the last forecast. 'But a weaker economic outlook and the unfunded changes to winter fuel payments mean the Chancellor will likely need to look again at tax rises in the autumn.' Speaking after delivering her spending review, Ms Reeves insisted she would not have to raise taxes to cover her spending review. She told GB News: 'Every penny of this is funded through the tax increases and the changes to the fiscal rules that we set out last autumn.'