Julaihi: Sibu's RM291 mln water treatment upgrade ahead of schedule
SIBU (July 30): The Salim Water Treatment Plant (WTP) upgrading project here is progressing smoothly, with 8.85 per cent advancement ahead of original schedule, said Utility and Telecommunication Minister Dato Sri Julaihi Narawi.
Implemented by Sibu Water Board (SWB), the project has reached 25.48 per cent physical progress compared to the original target of 16.63 per cent.
'Based on my observation of the works at the site today, I am pleased that everything is progressing smoothly.
'This is a very good sign, reflecting the extraordinary efforts by all parties involved,' he told reporters during a site visit here yesterday.
The project, which costs RM291.4 million (with the main contract valued at RM269.1 million), aims to double the water production capacity of the Salim plant from 150 million litres per day (MLD) to 300 MLD.
Julaihi said once completed, Sibu's total water supply capacity ― including the Bukit Lima Plant (45 MLD) will reach 345 MLD, providing a healthy reserve margin not just for Sibu but also surrounding areas.
'This upgrade will meet the increasing demand for clean water in Sibu and nearby regions,' he said.
He noted that 120 workers are currently involved in the on-site works to ensure the project remains on track.
Julaihi also expressed appreciation to SWB, project engineers and all stakeholders involved in the project's implementation.
'I hope this encouraging momentum will be maintained until the project is completed next year,' he added. Julaihi Narawi lead Salim Water Treatment Plant Sibu Water Board

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


The Star
a day ago
- The Star
Sada announces water tariff adjustment for Kedah
ALOR SETAR: Syarikat Air Darul Aman (SADA) is implementing a tariff adjustment through a review of the Tariff Setting Mechanism for all categories of users in Kedah. In a statement, SADA announced that the tariff adjustment took effect Friday (Aug 1) and would be reflected in the September billing cycle. 'To address water supply shortages, several new water treatment plant (WTP) projects are being developed, including the Pelubang WTP, Kodiang WTP Phase 1, Padang Saga WTP Phases 4 and 5, Sidam Kiri WTP Phase 1, Sungai Karangan WTP Phase 1, and the construction of a compact plant at Kulim Hi-Tech," it said. Sada added that repair works for distribution systems and pump houses were also being actively carried out to address low water pressure issues in several areas. It said additional revenue from the tariff adjustment would be used to cover operating costs, repair and maintenance of existing systems, development of new water supply systems and improve customer service. "The adjustment also considers the need to meet the company's operating costs for 2025, which are expected to increase by 6%," it said. Sada stated that the adjustment had undergone a thorough review with the National Water Services Commission (SPAN) and was being implemented in phases. – Bernama


Borneo Post
4 days ago
- Borneo Post
Julaihi: Sarawak to press on with master plan for 100 pct water coverage by 2030
Julaihi shows water processed by the Daro Acute System Project. Daro assemblyman Safiee Ahmad is at second right. DARO (July 30): Sarawak will press on with its ambitious Water Supply Master Plan to ensure 100 per cent water coverage across the state by 2030, said Dato Sri Julaihi Narawi today. The Minister for Utility and Telecommunication said the master plan, completed in 2021 and coordinated by the Sarawak Economic Planning Unit (EPU), lays the foundation for a long-term solution to water supply challenges, particularly in rural areas. 'The Water Supply Master Plan outlines Sarawak's water development up to 2070, with three strategic thrusts – water demand management, treatment and distribution, and the quality and adequacy of both raw and treated water,' he said at the launch of the Daro Acute System project in Mukah. The plan includes the creation of an integrated water grid system linking all major treatment plants across Sarawak, while off-grid solutions such as the Sarawak Alternative Water Supply System (Sawas) will serve remote communities. Julaihi said the government has allocated RM4.6 billion under Alternative Funding and the 12th Malaysia Plan to implement 406 water projects statewide. As of now, 292 projects have been completed, 77 are in pre-contract stages, and the remainder are in various phases of implementation. He highlighted ongoing efforts to reduce non-revenue water (NRW) through an RM1.1 billion pipe replacement programme covering 2,742km across Sarawak. In Mukah, RM10.4 million has been approved for 11 pipe replacement projects spanning 29.9km from 2024 to 2025, he said. 'The Premier of Sarawak has shown strong commitment to improving water supply, especially for rural areas,' Julaihi stressed, adding that he personally monitors project progress on the ground to ensure timely completion. The Daro Acute System project serves as a short-term solution to enhance local water supply until the full grid system is operational. Julaihi also urged the public to report vandalism of utility assets, warning that such acts cause not only financial losses but also disrupt the daily lives of residents. 'With continuous efforts and the support of all stakeholders, we can realize Sarawak's vision of a modern, efficient, and sustainable water supply system,' he said. Julaihi Narawi lead Sarawak Water Supply Master Plan


Malay Mail
5 days ago
- Malay Mail
Sibu's RM291m water treatment upgrade 8.85pc ahead of schedule, set to double regional water capacity, says Sarawak minister
SIBU, July 30 — The Salim Water Treatment Plant (WTP) upgrading project here is progressing smoothly, with 8.85 per cent advancement ahead of original schedule, said Utility and Telecommunication Minister Datuk Seri Julaihi Narawi. Implemented by Sibu Water Board (SWB), the project has reached 25.48 per cent physical progress compared to the original target of 16.63 per cent. 'Based on my observation of the works at the site today, I am pleased that everything is progressing smoothly. 'This is a very good sign, reflecting the extraordinary efforts by all parties involved,' he told reporters during a site visit here yesterday. The project, which costs RM291.4 million (with the main contract valued at RM269.1 million), aims to double the water production capacity of the Salim plant from 150 million litres per day (MLD) to 300 MLD. Julaihi said once completed, Sibu's total water supply capacity ― including the Bukit Lima Plant (45 MLD) will reach 345 MLD, providing a healthy reserve margin not just for Sibu but also surrounding areas. 'This upgrade will meet the increasing demand for clean water in Sibu and nearby regions,' he said. He noted that 120 workers are currently involved in the on-site works to ensure the project remains on track. Julaihi also expressed appreciation to SWB, project engineers and all stakeholders involved in the project's implementation. 'I hope this encouraging momentum will be maintained until the project is completed next year,' he added. — The Borneo Post