Falkirk area primary school will remain closed for at least a year after mortar found to be deficient
Councillors are being asked to agree to appoint a company to manage the project to make the massive repairs
A Falkirk area primary school in that has been closed since February is not expected to reopen until summer 2026, after mortar used in its construction was found to be "significantly deficient".
A gable wall at Maddiston Primary School - one of Falkirk Council' s newest and largest primaries - was visibily damaged by Storm Eowyn in January this year, but investigations to assess the extent of the damage revealed more widespread problems affecting the entire building.
According to a report going to members of Falkirk Council's executive, the mortar used in the construction was "significantly deficient, providing inadequate bonding to the surrounding stone".
As the scale of the defects became clear, the decision was taken in February to shut the building and decant around 500 pupils to three primary schools across the district.
A report going to Falkirk Council's executive on June 19 will ask councillors to approve a procurement strategy that officials say will allow them to move as quickly as possible to the next stage in the work to repair the school building.
According to the report, the cost is estimated be around £5 million and the work is likely to take at least a year.
The report explains that "investigations confirmed that the defects were present throughout the building to varying degrees."
Since the decant, the report says, substantial works have been undertaken to "expose sections of the external walls, remove defective materials, and allow further intrusive inspections of the building's structural elements.
Councillors will be told that intrusive investigations have also been undertaken internally to ensure that all construction defects and wider condition issues are identified while the building remains unoccupied.
The report states: "The works required are extensive and complex, involving the removal and replacement of substantial elements of the external fabric, internal structural supports, and remedial works to ensure the building meets current safety, compliance and educational standards."
Council officers are looking for councillors to approve work continuing with a company called HUB East Central (HUBco) which is providing strategic support services, including project management, architectural, and structural engineering input.
Local members are being asked to agree that the works should progress through HUBco - which has a track record of working with local authorities including Falkirk - with a partner contractor being appointed once the full scope of works has been confirmed.
The report says that this approach "is expected to allow mobilisation on site at the earliest opportunity".
A construction quality review and a separate root cause analysis are also now underway.
The report says these will inform "not only the repair works Maddiston Primary School but also any potential future actions and wider lessons for future capital investment across the school estate".
The project board overseeing the works includes senior officers from Education and Place Services and is supported by external specialists.
Falkirk Council's head of investment, assets and climate, Paul Kettrick, said: "This has been a complex and urgent response to significant construction issues that have been identified at the school.
'Our focus is on delivering the necessary remedial works safely and to the highest standard as quickly as possible.
"The proposed approach will allow us to proceed efficiently while ensuring that upon completion we are satisfied the building is free of defects and meets all structural and condition requirements."
The report will be discussed by Falkirk Council's executive on Thursday, June 19 in Grangemouth Community Education Unit, Abbots Road, Grangemouth, at 10 am. It will also be livestreamed on Falkirk Council's YouTube channel.

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Daily Record
16 hours ago
- Daily Record
Falkirk pupils to use 'parts' of closed primary school for new term
The extension and modular units at the storm damaged Maddiston Primary School campus will be used for younger pupils next term Parts of Maddiston Primary School campus, near Falkirk, will be back in use for the new term although the main building will not reopen until August 2026 at the earliest. The school closed in February, after damage caused by Storm Eowyn revealed significant construction problems that were present throughout the 17-year- old building caused by mortar that was "significantly deficient". As the scale of the defects became clear, the decision was taken by Falkirk Council in February to shut the building and decant around 500 pupils to three primary schools across the district. Falkirk Council's director of education, Jon Reid, wrote to all parents and carers this week to tell them the arrangements for the school year starting in August. He said the school will be able to use the new extension and existing modular units which have been unaffected by the construction defects that have been found throughout the main school. In his letter, Mr Reid confirmed that the school would not reopen until at least August 2026. He said "This is clearly disappointing news, but it is essential that the building meets all necessary building standards before staff and pupils return." The letter also confirms that Maddiston Community Centre will be used for PE and lunch arrangements. The extension will accommodate three Primary 1 classes and two Primary 2 classes while one P2/3 class and two Primary 3 classes will be in the Modular Units. Primaries 4 and 5 will go to Wallacestone Primary and Primaries 6 and 7 will be in Bantaskin Primary. The Timezone and Inclusion class pupils will continue to attend Moray Primary and Carrongrange High School. Mr Reid said that the arrangements "allow us to make the best use of available facilities across our school estate, scale back the transport arrangements in place and ensure a stable and high-quality experience for all pupils and staff while work toward a full return to Maddiston." A report going to Falkirk Council's executive on June 19 revealed that the mortar used in the construction was "significantly deficient, providing inadequate bonding to the surrounding stone". The cost is estimated be around £5 million and the work is likely to take at least a year.


Daily Record
2 days ago
- Daily Record
Falkirk councillor suspended for three months over 'bullying' email
Billy Buchanan broke the councillors' code of conduct when he asked for advice on "the suspension of an officer" A Falkirk councillor has been suspended for three months after sending an angry email that said he wanted to "get advice on the suspension of an officer" and threatened to involve the police and a solicitor. A hearing of the Standards Commission today (Thursday) found that Independent councillor Billy Buchanan, who represents Bonnybridge and Larbert, had sent an email regarding a member of Falkirk Council' s planning staff that "amounted to bullying". Morag Ferguson, Standards Commission member and chair of the hearing panel, said: 'The panel found that, in an email of 9 June 2023, Cllr Buchanan was disrespectful towards a planning officer of the council. The panel further found that Cllr Buchanan's conduct, in respect of the email, amounted to bullying, even if this had not been his intent.' Members heard that the email, sent on June 9, 2023, read: "I am looking for a meeting with officials and Councillor K to make a formal complaint and get advice on the suspension of an officer pending the outcome of an investigation." The email referred to a controversial planning application that had been turned down by council officers, before Falkirk Council's planning review committee granted permission for the development to go ahead, subject to a legal agreement being signed. Baillie Buchanan told the panel that the application had sparked abuse that had affected both him and his family as well as other councillors involved. When the applicant's agent contacted him to say that the legal agreement had still not been signed months later, Baillie Buchanan emailed officers to ask that the matter be investigated. Several months later, he received another email - this time from a fellow councillor, who was not named - to say that the matter was still not resolved. A senior planning officer replied to advise members that the delay was caused by the introduction of new planning policy by the Scottish Government. But the panel found that Cllr Buchanan then sent an email, on 2 June 2023, to the other councillor and managers from the senior planning officer's team stating that he wanted 'an immediate investigation' into the situation and the concerns expressed regarding the senior planning officer's 'part in the handling' of the application. This was followed by the email on June 9, which suggested Cllr Buchanan was looking for advice "on the suspension of an officer" and referred to getting the police and his personal solicitor involved. He signed off the email saying, "It's scandalous!" Baillie Buchanan insisted that the reference to the police and his solicitor was not directed at the officer but had been because he and his family, along with other councillors, had been subjected to horrendous abuse because of the decision to grant planning permission. Baillie Buchanan said he had "never at any stage accused the complainant of anything" but he admitted it had been frustrating to send a complaint about a delay and "months and months later" to hear the matter had still not been resolved. He told the panel: "What I said, quite clearly, was that I wanted a meeting to get advice. "The reason to involve the police because we had had so much abuse. "I sent the email to try and bring this to a conclusion." But the panel was satisfied that Cllr Buchanan assumed the senior planning officer was responsible the length of time the application was taking. It was also satisfied that he was also suggesting the officer be suspended as a result, noting that the senior planning officer had been removed from the list of recipients in the email chain. The members of the panel accepted fully that Cllr Buchanan was entitled to raise questions about the progress of applications determined by the Committee and to raise concerns - with the appropriate line manager or senior officer - about delays potentially caused by a council employee. But they considered that anyone reading the email would conclude "from Cllr Buchanan's mention of a disciplinary measure, the police, his solicitor, and his use of the word 'scandalous', that he was clearly implying the senior planning officer was guilty of misconduct and or had deliberately done something that was improper or illegal. Cllr Buchanan said he was very angry that the email, marked private and confidential, had been shared with the officer. But members of the panel felt that "Cllr Buchanan should have known it was likely the contents of his email would be disclosed ... given the reference to disciplinary proceedings and seriousness of the inferred allegations about the officer's conduct (even if the full email was not shared)". The Panel agreed that it would be reasonable for the senior planning officer to have interpreted Cllr Buchanan's comments as a threat to contact both the police and an external solicitor about his conduct. Ms Ferguson said that unless there was a suggestion of illegality, an officer's conduct would be an internal council matter and Cllr Buchanan had not provided any evidence of illegality or misconduct. The panel found that Cllr Buchanan "had breached the provisions in the Code that require councillors to behave respectfully towards council officers and to refrain from any conduct that could amount to bullying". The panel agreed that Cllr Buchanan "should have known how to undertake his scrutiny role in respect of the application and overall process and could have asked relevant senior officers to establish whether and, if so why, any undue delays had occurred, without breaching the Code". Ms Ferguson added that they were concerned that Cllr Buchanan had not shown any remorse or insight into how his conduct may have affected others. But they noted that the conduct was limited to one email exchange and felt that a three-month suspension was an appropriate sanction.


Daily Record
3 days ago
- Daily Record
Falkirk area primary school will remain closed for at least a year after mortar found to be deficient
Councillors are being asked to agree to appoint a company to manage the project to make the massive repairs A Falkirk area primary school in that has been closed since February is not expected to reopen until summer 2026, after mortar used in its construction was found to be "significantly deficient". A gable wall at Maddiston Primary School - one of Falkirk Council' s newest and largest primaries - was visibily damaged by Storm Eowyn in January this year, but investigations to assess the extent of the damage revealed more widespread problems affecting the entire building. According to a report going to members of Falkirk Council's executive, the mortar used in the construction was "significantly deficient, providing inadequate bonding to the surrounding stone". As the scale of the defects became clear, the decision was taken in February to shut the building and decant around 500 pupils to three primary schools across the district. A report going to Falkirk Council's executive on June 19 will ask councillors to approve a procurement strategy that officials say will allow them to move as quickly as possible to the next stage in the work to repair the school building. According to the report, the cost is estimated be around £5 million and the work is likely to take at least a year. The report explains that "investigations confirmed that the defects were present throughout the building to varying degrees." Since the decant, the report says, substantial works have been undertaken to "expose sections of the external walls, remove defective materials, and allow further intrusive inspections of the building's structural elements. Councillors will be told that intrusive investigations have also been undertaken internally to ensure that all construction defects and wider condition issues are identified while the building remains unoccupied. The report states: "The works required are extensive and complex, involving the removal and replacement of substantial elements of the external fabric, internal structural supports, and remedial works to ensure the building meets current safety, compliance and educational standards." Council officers are looking for councillors to approve work continuing with a company called HUB East Central (HUBco) which is providing strategic support services, including project management, architectural, and structural engineering input. Local members are being asked to agree that the works should progress through HUBco - which has a track record of working with local authorities including Falkirk - with a partner contractor being appointed once the full scope of works has been confirmed. The report says that this approach "is expected to allow mobilisation on site at the earliest opportunity". A construction quality review and a separate root cause analysis are also now underway. The report says these will inform "not only the repair works Maddiston Primary School but also any potential future actions and wider lessons for future capital investment across the school estate". The project board overseeing the works includes senior officers from Education and Place Services and is supported by external specialists. Falkirk Council's head of investment, assets and climate, Paul Kettrick, said: "This has been a complex and urgent response to significant construction issues that have been identified at the school. 'Our focus is on delivering the necessary remedial works safely and to the highest standard as quickly as possible. "The proposed approach will allow us to proceed efficiently while ensuring that upon completion we are satisfied the building is free of defects and meets all structural and condition requirements." The report will be discussed by Falkirk Council's executive on Thursday, June 19 in Grangemouth Community Education Unit, Abbots Road, Grangemouth, at 10 am. It will also be livestreamed on Falkirk Council's YouTube channel.