Mick Clifford: A half-built school lying idle is a lesson in the State's inability to get things done
In reality, it's nothing like that. Instead, the idle site of a half-built school at a time when all manner of infrastructure and housing is desperately needed, is attributable to a kind of stasis that is increasingly a feature of State-related projects. The task of actually getting things done efficiently and expeditiously has never been as frustrating.
The site in question is on Dominick Street, just off Parnell Square, and has been dormant since May 23. It was to be the location of an old and venerated school in the area, Gaelscoil Coláiste Mhuire.
Then last week, it emerged the contract with the builder had been terminated. As recently as autumn 2024, it was hoped the 16-classroom complex could be occupied for the coming school year. Now, all the indications are it will be 2027 before it can open for education.
The school has been in temporary accommodation for the past 23 years. That means private rented accommodation and all the cost and inconvenience that accrues from that. The new location was sourced from Dublin City Council, which owned the site, and was acquired by the Department of Education. So, two State bodies were involved in the transaction, which would infer the whole thing should be done quickly. It wasn't.
The tender for the job was won by a local contractor from north Dublin to a value of €11.5m. Today, the estimates are by the time the job is completed it will cost at least €22m.
According to the department, soon after the project began, 'a number of issues arose', something it says 'is not unusual given the nature of a brownfield city centre site'.
The school has been in temporary accommodation for the past 23 years. That means private rented accommodation and all the cost and inconvenience that accrues from that.
Well, yes and no. If the site had previously been in the ownership of a private entity, that might well be the case. But it wasn't. One way or the other, the department maintains these issues 'led to a delay'.
Among the 'unforeseen' issues was services on the site related to the adjoining Luas line, 'which had not been apparent until excavation began'.
How could that not be apparent? The Luas is loud and imposing. It didn't just appear. Surely, particularly as Dublin City Council had previously owned the site, that issue could have been foreseen and taken into account.
Another issue was with 'foundations of an adjoining protected building, which needed careful consideration as to a solution'. Right. This protected building was there all along, adjoining the site, its status as protected quite obviously known. And it wasn't foreseen there might be that kind of problem?
That was only the start of it. Further delays ensued. There were disputes with the contractor over who was responsible for what, and how much the various issues impacted on the original contract and price. This is precisely the kind of dispute that has seen the building of the National Children's Hospital expand from a job into a long-running saga.
Parents and local politicians were supposed to be kept in the loop as to how things were going, but that doesn't appear to have been the case.
When the delays to the school project were raised in the Seanad a few years ago, it emerged the department attributed some of the 'slippage' to staff now working from home. This is something that demands further inquiry from government.
Remote working is now, since the pandemic, part of the culture, and it has many positive attributes. But is it, as currently constituted, in any way delaying the convening of meetings between outside bodies such as construction firms and State bodies?
It has emerged differences between the department and the contractor were insurmountable, and the contract has been terminated. This will necessitate a half-built school going out to tender again.
Last year, the department decided the best way forward would be to appoint a project manager to liaise between department, the design team and the contractor. This project manager, according to the department, got off to a good start, 'identifying the key issues critical to the success of the project, developing various proposals and strategies to remedy any issues impacting programme, realigning the full project team roles and ageing the project delivery timelines and goals".
All of that is good stuff, but really why was it necessary at this stage of the game? A school is being built, not a city.
Despite the recharged run at things, more trouble lay ahead. Issues arose over the length of time it was taking for requests for information, a routine exercise in most projects. All of that culminated in May with the contractor and department in dispute, culminating with 'a temporary pause on works for now, under the suspension of works provisions of the contract', according to the department.
This 'provides an opportunity to consider outcomes from the conciliation process and the best way forward'. Make of that what you will.
Now it has emerged differences between the department and the contractor were insurmountable, and the contract has been terminated. This will necessitate a half-built school going out to tender again. There is also the possibility the contractor may seek legal recourse over what has happened, which could delay things further. All of that is apart from the ballooning costs since the job first went out to tender.
If this were an isolated case, there might be mitigation. But it comes in the wake of various delays, associated with the planning system, interdepartmental disputes over funding, and even the cancellation at a late stage of a proposal for social housing based on cost.
These issues all concern the State apparatus building much-needed infrastructure. Yet increasingly, for various reasons, almost all associated with how the State is operating, things are simply not getting done.
In statement, the Department of Education said "a temporary pause on works, under the suspension of works provisions of the contract, provided an opportunity to consider outcomes from the conciliation process".
A spokesperson said: "A notice of suspension of works was communicated to the contractor on May 23, 2025 in accordance with the provisions of the contract. During the suspension, the department carefully considered the best way to deliver a school building while also respecting its statutory obligations. The department issued a notice of termination under the contract on July 1, 2025 following careful consideration of the need to ensure compliance with those statutory obligations.
"Department officials will continue to work closely with the school principal and board of management. As an interim measure, the department is providing accommodation more suitable to the current needs of the school nearby in Cathal Brugha Street. The department is assessing all options open to it to expedite the delivery of a new school building, and as set out above, is in very regular contact with the school authorities."

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Irish Independent
10 hours ago
- Irish Independent
NatWest exits Irish market as it sells remaining shares in PTSB
The sale of the 63.6 million shares to institutional investors was completed by way of an accelerated book build following the close of the markets yesterday. The sales price was €1.98, which would have been a 5.4pc discount on the closing price of €2.09. NatWest, which raised €126m from the sale, originally acquired a 16.66pc stake of PTSB in November 2022 as part of the Irish bank's complicated acquisition of the retail business of Ulster Bank. The State still holds a 57.4pc stake in the bank. The British banking giant and the Minister for Finance entered into a shareholder co-operation agreement in late 2022. The following June, the State and NatWest disposed of a cumulative 10pc stake in the bank, a legacy from the financial crash when it bailed out the Irish banking sector. As part of the co-operation agreement, the Minister for Finance was offered an opportunity to participate in last night's sale, but chose not to do so. The minister also committed to a 90-day lock-up period on the State's shareholding. After the recent sale of the State's remaining stake in AIB, the Department of Finance said it would assess opportunities for the disposal of shares in PTSB as they arose. Paschal Donohoe, the finance minister, also removed the salary cap that had been in place in both AIB and PTSB. Denis McGoldrick, an analyst with Goodbody, said: 'We had flagged in early May that it was likely NatWest would look to reduce its holding in PTSB in the near future given the return of its Ulster Bank licence to the Central Bank of Ireland was imminent, that PTSB's share price had recovered to above the 'break even' point for NatWest, and that an exit would close out its last remaining interest in the Irish banking market. 'From a PTSB perspective, we view the news as a positive development which should also see a positive share price reaction. The exit of a material holder will significantly improve liquidity in the stock which currently has an average daily trading volume, over the last 30 days, of just 300,000 shares.' Ulster Bank returned its licence to the Central Bank at the end of June, ending a 165-year history of banking in Ireland. Davy also said that the sale by NatWest removes and overhang on the stock, and should improve its liquidity. 'PTSB is well positioned due to a range of initiatives, including operational and capital efficiency measures currently underway, to increase profitability and return and resume distributions to shareholders,' it said. PTSB's share price was down almost 2pc in early trading on the Irish stock exchange. Yesterday it emerged that staff at the Eamonn Crowley-led bank will be getting a 4pc pay increase, after an agreement was reached between management and trade unions following lengthy negotiations.


Irish Times
13 hours ago
- Irish Times
Rein in spending to cut reliance on ‘volatile' corporation tax, Ibec says
Business lobbying group Ibec has called on the Government to reduce the growth of public expenditure in an effort to reduce the State's reliance on 'volatile' corporate profit tax receipts. The lobbying group said the positive status of the State's headline economic markers are largely funded by corporate tax, which its chief economist Gerard Brady said could be 'volatile' over the coming years. Ibec suggested a maximum net spend on budget day of €3 billion, with increased exchequer spending offset by fiscal drag and €1.3 billion made up of commitments under the National Development Plan. [ Ireland's corporate tax receipts hit €156bn Opens in new window ] Ibec pointed to figures showing that, should Ireland collect a level of corporate profit tax comparable to similar economies, every worker in the country would have to pay an additional €4,000 in taxes to make up the State's current tax revenue. In light of the reliance of the State's balance sheet on corporation tax, Ibec called for the Government to rein in spending increases in the coming budgets to 'return to a balance of income over expenditure, were our corporate tax receipts to be realigned with other mid-sized globalised economies'. The lobbying group said the gap stands at around €5 billion, and Mr Brady noted that recent US policy is adding to the economy's exposure to volatility with the State at risk of being left 'very short' on tax receipts should that risk materialise. Mr Brady said the Government could 'correct, fairly painlessly, the underlying budget deficit' over a number of years and would avoid 'more painful' measures in the future. He said the business community's biggest concern is of a 'sharp correction' in Government policy should that 'volatility be materialised'. Asked whether it supported Government indications that cost-of-living measures would not be needed in the Budget, Fergal O'Brien, Ibec's head of lobbying and influence, said the group was against 'universal supports'. 'We shouldn't be doing across-the-board, universal supports – it is just really bad economic policy,' Mr O'Brien said, urging the State to target distressed households and reduce the cost of business. [ The EU/US tariff deal: The good, the bad and the potentially ugly for Ireland Opens in new window ] Ibec also called for 'targeted supports' for industries hardest hit by US import tariffs, such as the the spirits industry, where Ibec noted more than 90 per cent of distilleries had paused or cut back production. Mr Brady said that some sectors would be placed under 'existential pressure' should the level of tariffs rest at 20 or 30 per cent. The lobbying group noted that their members have been 'very vocal' in raising 'a lot of concerns' about the EU's countermeasures in response to US tariffs. One measure Ibec suggested to reduce costs to businesses and households is reducing the fixed cost component on Irish energy bills through a 'strategic annual subvention'. The group also suggested indexing the top tax band and income tax credits to wage growth at a cost of €440 million and €240 million respectively. Amid economic turmoil, Ibec called on the Government not to reduce infrastructural spending, and to introduce a set of spending targets in the upcoming 2026-2029 medium-term fiscal plan. These include a fiscal investment target of 5 per cent of gross national income (GNI), and working towards increasing public investment in research and innovation to 1 per cent of GNI by 2035. To encourage homebuilding, Ibec called for the reduction of VAT to 5 per cent and the removal of Government levies on new-build apartments – which it said would 'improve the viability of apartment building'.

Irish Times
14 hours ago
- Irish Times
Redevelopment of Dublin's Victorian fruit and vegetable market begins
The €44 million redevelopment of Dublin 's Victorian fruit and vegetable market has started, a decade after planning permission was granted for the work. The project, which is expected to take just over two years, involves the conservation and restoration of the 127-year-old market building on Mary's Lane close to Capel Street, along with new buildings to the southside of the market facing the Luas line on Chancery Street. Once completed, the revamped market will house at least 80 stalls along with a 'restaurant and food demonstration space' as well as an outdoor 'farmers' market' under canopies at the Chancery Street Yard, Dublin City Council said. Archaeological investigations have been undertaken and some asbestos removal completed. The main contractors Purcell Construction have moved on site to begin internal works to the protected structure, councillors were told on Monday. READ MORE [ 'Coming back to life' - Inside Dublin's 127-year-old fruit and vegetable market as major revamp gets under way Opens in new window ] The work includes: roof upgrades, refurbishment of the cast iron posts and wrought iron structures; repair of original brickwork and tiles and 15 large-scale doors; demolition of some 20th-century additions; and building of new structures including two toilet blocks. The redevelopment of the market was first proposed in 2002. In 2007 a consortium was selected for what was then a €425 million project involving apartments and offices as well as a retail food market. Michelin-starred restaurateur Patrick Guilbaud was reported to be 'in talks' as an anchor tenant, but contracts were never signed before the financial crash hit. Dublin City Council agreed to borrow €30 million to ensure the redevelopment of the Victorian market goes ahead. Photograph: Chris Maddaloni/The Irish Times In 2011, the council announced more modest plans to redevelop the market as a retail and wholesale food facility. The following year it began repairs to the roof and in 2013 it drafted redevelopment plans to open the new market in mid-2015. The development again stalled when it emerged vacant possession of the hall was required for the work to take place. At that point, about a dozen wholesalers were still using the building. In March 2015 the council secured planning permission for a retail-only market, and following several more years of negotiation with the traders, secured vacant possession of the building in August 2019. The council immediately closed the market and said it would begin the tender process for the new retail market which it hoped to have operational by 2021. It has remained closed since, apart from its rental to a construction company for storage, occasional one-off events, and its use by film companies. Since its closure, the historic building has been subject to repeated vandalism with several of its old wooden doors badly damaged by fire. Councillors last March approved borrowing of up to €30 million as part of the overall €44 million estimated cost of the project, and ministerial approval was subsequently sought and granted for work to begin. The new facility will be a 'quintessentially Irish food market' operating seven days a week to 'support the city's north retail core and highlight the food offer to locals and visitors alike', the council said. Shoppers will be able to 'do their weekly food shop, or dine on-site at the restaurant or traders stalls'. Facilities will be provided for 'community growers and start-up food business' and more established local producers who will have a 'direct route to market with some producing on-site' the council said. 'The new market will act as a catalyst for regeneration and new uses in the area while providing for food education and associated events,' it said.