‘No land, no home, no future': Himalayan Lepchas fear new dam
'It felt like an earthquake,' the 51-year-old mother of five says of the events of October 4, 2023. 'The whole house was shaking. It was raining heavily, there was no electricity, and we couldn't see anything.'
In the pitch dark and amid the heavy downpour that night, Lepcha roused her three children, aged 13, 10 and five, and rushed out of the house with her husband, panicking. Together with a few neighbours, they searched for a safe space on higher ground. That's when they noticed a distinct smell of mud and something like gunpowder.
Moments later, an enormous, tsunami-like wave surged down with terrifying force. Lepcha didn't know it at the time, but it was a glacial lake outburst flood (GLOF), which had been triggered by the sudden avalanche of ice and rock into the South Lhonak Lake – a glacial lake high up in the Teesta basin in North Sikkim.
The impact breached the lake's moraine wall, releasing more than 50 million cubic metres of water. The flood destroyed the 1,200-megawatt Teesta III dam – Sikkim's largest hydropower plant, located at Chungthang on the River Teesta, the largest river in Sikkim, which originates in the eastern Himalayas. The dam's collapse released an additional five million cubic metres (equivalent to 2,000 Olympic swimming pools) of reservoir water.
The high-velocity flood in the Teesta River valley carried about 270 million cubic metres of sediment and debris along with it, causing widespread devastation across Sikkim, parts of West Bengal and Bangladesh through which the Teesta flows.
At least 55 people were killed, 74 went missing, and more than 7,025 were displaced. The flood damaged nearly 26,000 buildings, destroyed 31 bridges and flooded more than 270 square kilometres of farmland. It also triggered 45 landslides, damaged four dams and destroyed long stretches of National Highway 10.
Both Teesta III and Teesta V, another hydroelectric dam near Dikchu in Balutar, have remained shut since they were severely damaged during the flood. Repair work is continuing, but neither of the dams has generated electricity for almost two years.
Scientists say the scale of the destruction makes it one of the most devastating flooding disasters recorded in the Himalayas in recent decades.
Rebuilding amid ruin
Today, Naga village, located about 73 kilometres from Sikkim's capital, Gangtok, is deserted due to continuous land subsidence. Houses are cracked, have collapsed or are still standing but leaning towards the river flowing below. The main NH10 road passing through the village has been destroyed with long, deep cracks.
In all, about 150 families lost their homes and land in the flood and now face an uncertain future. Lepcha's family lost both their houses, which collapsed in the landslides. They, along with 19 other families, are now living temporarily in a government tourist lodge in Singhik, about 10km from their home.
As the region struggles to recover, and communities along the Teesta remain displaced and vulnerable, the Ministry of Environment, Forest and Climate Change (MoEF&CC) has approved plans to rebuild the Teesta III dam without any public consultation, despite concerns about the risk of future glacial lake outburst floods and the fact that the Himalayan range running across Sikkim is seismically sensitive.
With the ongoing monsoon season, the Teesta's water levels have risen significantly. This has already caused several landslides in North Sikkim, washing away the under-construction Sankalang bridge and cutting off large parts of the region.
Long stretches of roads across North Sikkim are still unpaved, muddy and full of rubble. Several bridges damaged during the 2023 flood and the monsoon next year are yet to be rebuilt.
The quality control lab at the Chungthang dam site has also been swept away, halting construction work. 'It looks like a war-torn area. How will they rebuild Teesta III?' asks Gyatso Lepcha, a climate activist with Affected Citizens of Teesta (ACT), a group of Lepchas campaigning against large hydropower projects and environmental conservation in the region.
'A detailed risk assessment considering future climate scenarios, glacial behaviour, hydrological changes, and sedimentation rates is essential before deciding to rebuild the dam in the same location,' says Farooq Azam, senior cryosphere specialist at the International Centre for Integrated Mountain Development (ICIMOD).
In the absence of such an assessment, the region's Lepcha communities, who fear further disaster, are protesting against the construction.
A controversial dam
Sikkim is home to 40 of India's 189 potentially dangerous glacial lakes across the Himalayan region, many of which are at risk due to rising temperatures and glacial melt driven by climate change.
Built on a river already lined with dams constructed by the National Hydroelectric Power Corporation (NHPC), the Teesta III dam was originally pitched as a renewable energy project.
Approved in 2005 with a budget of Rs 5,705 crore (about $667m), the dam actually cost more than Rs 14,000 crore ($1.6bn) to build by the time it became operational in 2017. Delays were caused by the 2011 earthquake, which destroyed major infrastructure, and also repeated flash floods and landslides.
The dam faced criticism from environmentalists and the All India Power Engineers Federation (AIPEF), which described it as a 'failed example of public-private partnership' for the massive cost overruns, years of delay, ecological damage and disregard for Indigenous rights and livelihoods.
The operator, Sikkim Urja Limited (formerly Teesta Urja Ltd or TUL), was forced to sell electricity at half the agreed rate as buyers, including the states of Punjab, Haryana, Uttar Pradesh and Rajasthan, refused to pay higher prices. In 2017, transmission delays caused yet more losses of about Rs 6 crore ($701,000) per day from June to September 2017.
Following the devastating flooding of 2023, the estimated reconstruction cost for the dam is now Rs 4,189 crore ($490m), but experts question how such a large-scale reconstruction could be completed at less than a third of its original building cost.
An investigation in May this year renewed concerns about the project. The Sikkim Vigilance Police, a special police force, found irregularities in the process used to select the independent power producer, who, according to the findings of the police investigation, lacked the qualifications for a project of this scale. It was alleged that critical dam design parameters had been compromised as a result.
Other reports have found that environmental assessments also overlooked key risks. A 2006 biodiversity report [PDF] from Delhi University had identified the Chungthang region as a highly sensitive ecological zone. Yet the project received swift environmental clearance from the environment ministry based on a report which claimed that little to no significant wildlife existed in the area. The clearance procedure also bypassed the ministry's own directive that no dams could be approved in Sikkim until a full 'carrying capacity study' (a study of an area's capacity for supporting human life and industry) of the Teesta basin had been completed.
'What was the hurry to give clearance for rebuilding even before the Central Water Commission and Central Electricity Authority cleared the design?' asks Himanshu Thakkar, coordinator of South Asia Network on Dams, Rivers and People (SANDRP), an advocacy group working on the water sector. 'The Environmental Impact Report (EIA) used was done before 2006, which didn't consider the risk of a GLOF. It contributed to the disaster, and now the same flawed EIA is being used again. Even the dam safety report prepared after the collapse hasn't been made public or considered for this decision.'
While a 'concrete faced rockfill dam' is planned this time – supposedly more resilient to flooding than the old 'concrete gravity dam' design – experts and local communities still worry this won't be enough because, they say, key impact studies are incomplete.
Al Jazeera reached out to MoEF&CC with questions about why the Teesta III reconstruction had been approved without a new EIA, despite concerns over safety and ecological impacts. Questions were also sent to Sikkim Urja Ltd regarding reconstruction plans and structural safety and to NHPC about the cumulative impacts of multiple dams along the Teesta. Emails and calls to all these offices remained unanswered by the time of publication.
Tunnelling and blasting during the original construction of Teesta III, before it opened in 2017, led to landslides, erosion and damage to homes. Yet, no comprehensive assessment has been conducted on seismic risks, reduced river flow or long-term ecological impacts.
'Our soil is fragile,' says Sangdup Lepcha, president of ACT. 'We are seeing more landslides every year. During the GLOF, the soil was completely washed away. If tunnels are dug again under our villages, the area could collapse.'
Sangdup, who lives in Sanggong village in Lower Dzongu, says the 10km stretch from Namprikdang to Dikchu is the only remaining stretch of the Teesta without any dams.
Many worry that if the rebuilding of Teesta III continues without safeguards, it will put villages at risk. 'We have already seen what happened in Naga,' says Sangdup. 'Why is the project getting emergency clearance while affected families are still waiting for rehabilitation?'
Sacred land
Dzongu, a region bordering the Kanchenjunga Biosphere Reserve in North Sikkim, is a protected reserve for the Indigenous Lepcha community. Known for their spiritual ties to the rivers and mountains, the Lepchas from Dzongu have long resisted large-scale hydropower projects in the region to protect their identity, livelihoods and the biodiversity of the region.
When multiple dams were proposed in the early 2000s along the Teesta basin – a river the Lepchas revere as a living deity – ACT spearheaded protests against dam construction. Their hunger strikes and protests led to the cancellation of four major hydropower projects in Dzongu and four outside.
'We are animists,' says Mayalmit Lepcha, ACT's general secretary. 'Our traditions, culture, identity, and everything else are tied to Mount Kanchenjunga, Teesta, Rangeet and Rongyong rivers here.'
Despite their long history of activism, the communities say they were ignored during the public consultation process, even though their land and rivers would be used for the proposed 520 MW Teesta IV hydroelectric project.
At least 16 villages lie near the potential construction site, across the agricultural belt of North Sikkim. The project would include building tunnels underneath Hee Gyathang and Sanggong villages in Dzongu to carry water to the power station. The siltation tunnel, which will divert sediment-laden water away from the main reservoir, is supposed to run beneath the Tung Kyong Dho, a sacred lake known for its rich biodiversity.
Songmit Lepcha, from Dzongu's Hee Gyathang village, told Al Jazeera that she lost her livestock and plantation during flash floods in June last year. 'We are scared of rebuilding our homes,' Songmit said, her voice filled with worry.
Opposition Citizen Action Party (CAP) leader Ganesh Rai told Al Jazeera that he is particularly worried about the new plans to rebuild the dam to a height of 118.64 metres, twice as high as the original. 'With climate change intensifying, any future breach could submerge all of Chungthang,' he said. 'It won't just affect Dzongu but everyone downstream.'
That could include settlements in Dikchu, Rangpo, Singtam and Kalimpong, and Darjeeling and Jalpaiguri districts in West Bengal, which were severely affected by the 2023 flood. In places like Bhalukhola near Melli, families have been living in makeshift relief camps since the 2023 floods. Conditions are difficult, with limited access to clean water, sanitation and medical care.
Struggles downstream
The 2023 flood did not just destroy 22-year-old Leboon Thapa's family home in Bhalukhola in north Bengal, about 100km downstream from the site of the old Teesta III dam. It also disrupted his dreams of a professional football career.
Leboon is now living with his parents in a single, cramped room inside a relief camp along the Teesta highway, which is situated above Bhalukhola. They are sandwiched between works being done to widen the highway in front of their site, and the ongoing tunnel construction work for the Sevoke-Rangpo railway project behind them. The exposed location leaves them at risk of landslides and flooding.
'If they are rebuilding the dam, they must build protection walls here for our safety,' says the lanky, athletic young man, looking around at what's left of his village. The fields he played football in as a child, as well as the playground he once ran about in, are now buried under silt and debris. 'We only have this land. If we lose it, where do we go?'
About 10km further downstream in Teesta Bazar, 68-year-old Tikaram Karki lost his house and motorcycle repair shop to the 2023 flooding. His home, built above the riverbank, began cracking and sliding just a few days after the flood.
'We were hiding in the mountains in the rain. When we came back at 6am, there were no houses, roads, or electricity,' he says, as he stands next to what remains of his house and shop, both of which are leaning steeply towards the Teesta. He smiles even as he talks about his losses since that dreadful night.
Tikaram now lives in a rented house with his family of four. He is paying Rs 8,000 ($93) monthly rent while struggling with financial losses as he has no way to run his business.
He received some compensation from the West Bengal state government, but it does not cover all he has lost. 'I have been living here for 30 years and spent Rs 30 lakh ($35,000) building my house. I only got Rs 75,000 ($876) in compensation. What will happen with that?'
Like others here, Tikaram says he believes the destruction was made worse by years of poor planning and unchecked silt buildup caused by the dam, which raised the riverbed of the Teesta.
'If they had cleared the silt during the dry months, we wouldn't be so vulnerable now,' he says.
'I cannot tell the government not to build the dam, but they should build proper protection for all the people still living along Teesta,' adds Tikaram.
Rising risk
In a January 2025 study by an international team of scientists and NGOs published in the Science journal, researchers warned that South Lhonak Lake is one of the more rapidly expanding and hazardous glacial lakes in Sikkim. The lake expanded from 0.15 square kilometres in 1975 to 1.68sq km by 2023, posing a danger of flooding to the communities downstream.
'The Teesta-III dam played a significant role in amplifying the downstream impact of the South Lhonak GLOF disaster,' Azam, at the International Centre for Integrated Mountain Development (ICIMOD), tells Al Jazeera.
Azam explains that while the disastrous flood could not have been prevented, its impact could have been significantly reduced through better infrastructure planning and active monitoring of the lake. 'Reinforced spillways, sediment handling systems, and early warning systems linked to upstream sensors could have provided critical response time,' he says.
The night the flood hit, the dam's power station was still operating. According to Thakkar, authorities had received alerts well in advance, but there were no standard operating procedures or emergency protocols in place about opening spillway gates during such situations. 'And there has been no accountability since,' he added.
Thakkar says he is deeply concerned that the dam is being rebuilt without taking into account the flood potential based on current rainfall patterns.
'And what happens to the other downstream dams when this one releases excess water during the next flood?' he asked. 'None of them are being redesigned to withstand that kind of excess flow.'
At the end of May, there was a landslide at the Teesta VI dam site in Singtam. 'This is happening every monsoon,' said Gyatso.
Rai criticises the state's priorities, saying the government was 'pushing for more dams instead of strengthening disaster preparedness' at a time when the frequency of extreme weather events is expected to increase.
'No Future Here'
Nearly two years after the October 2023 flood, Tashi Choden Lepcha still has no home. Her voice chokes up as she speaks about her houses in Naga village.
'We were born there, raised children there. Now we have nothing,' she says of herself and her husband, wiping her tears. Her brother used to live next door: he lost everything as well.
After the disaster, she, her husband and children stayed in a school building in Naga. But when cracks appeared in the school walls, they were shifted to Singhik. The lodge, too, is beginning to show cracks in the kitchen and bathroom.
Her husband and children have since relocated to Siliguri, about 150km away, for work and education, while she stayed behind alone because she teaches at Naga Secondary School.
The government gave them Rs 1.3 lakh ($1,520) in compensation, but most of it went on the cost of moving their belongings to different locations.
There have been discussions about allocating land higher up in the mountains for the displaced families. But many of them fear it could take years before they are rehoused. 'If the government gives us land in a safe location, we can build a house. How long can we live like this? We have no future here,' she says now.
Most people in the surrounding villages share her fears. They want the dam project scrapped or moved to a safer location.
Mayalmit echoes this call for caution. 'We're going to have more GLOFs, there's no doubt,' she says.
'People will have confidence only if decisions are based on proper impact assessments, considering all factors, and done in a transparent way,' Thakkar adds. 'But that's not happening now, which is why there's scepticism about hydro projects among locals.'
He says that Indigenous communities must be part of the decision-making process. 'They're the ones most at risk, and also the most knowledgeable.'
Praful Rao of Save The Hills, an NGO working in disaster management in North Bengal and Sikkim, has called for joint disaster planning between the two states. 'What happens upstream affects us downstream. It is time we work together for science-based disaster planning, not blindly push dam projects for revenue.'
While hydroelectricity is important for India's energy future, Rao warns against unchecked expansion. 'You can't build dams every few kilometres. We need to study how many this fragile region can safely support.'
Mayalmit urges central and state authorities to reconsider the approval. 'Don't act against Indigenous rights, the environment. I speak for the rivers, the birds and the animals here.'
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Al Jazeera
2 days ago
- Al Jazeera
Indian village swallowed by mudslide: What happened – and why?
More than 100 people are missing and at least four people have died after flash floods swept through the village of Dharali, in the north Indian state of Uttarakhand. Teams from the army and disaster response forces are operating in the area to rescue people trapped under debris, local authorities have said. 'A massive mudslide struck Dharali village in the Kheer Gad area near Harsil, triggering a sudden flow of debris and water through the settlement,' the Central Command of the Indian Army said in a post on X. Flash floods in Uttarkashi, where Dharali is situated, were triggered by intense rainfall known as a 'cloudburst', which caused the Kheerganga river to swell, at around 1:30pm local time (08:00 GMT) on Tuesday. The India Meteorological Department (IMD) warned that heavy rainfall will continue for the next few days. What is a cloudburst? A cloudburst is an intense downpour that delivers a large volume of rain in a short time. It is often accompanied by thunder and hail and can cause flash floods. At any given time, clouds blanket about 70 percent of the Earth's surface. Cloudbursts are often associated with cumulonimbus clouds, which contain large amounts of water. The IMD said that over the past 24 hours, extreme rainfall of 21cm (8.3 inches) or more had been recorded in parts of northwest India, including Uttarakhand, where the flash floods happened – more than the 10cm (3.9 inches) of rain per hour required to be classed as a cloudburst, according to the IMD. Cloudbursts tend to occur over a small geographical region of 20 to 30 square kilometres (7.7 to 11.6 square miles) Is this caused by climate change? Uttarakhand, which has a large amount of mountainous and often unstable terrain, is prone to monsoon-related flooding. Dharali village is nestled in the Himalayas between the villages of Harsil and Gangotri. Uttarakhand is particularly vulnerable to climate change given the fragility of the Himalayan region. In particular, it is exposed to excessive precipitation, cloudbursts, flood events and periods of very cold weather (cold waves), according to a study published in the International Journal of Disaster Risk Reduction. That study found that districts in higher regions are more exposed to these effects because of their inability to adjust to weather-related and climate changes and because the ecosystems in these areas are more sensitive to such changes. Experts say global warming will cause mountain temperatures to rise faster than the global average. Catastrophic flooding that has historically affected Uttarakhand will become more common as rising temperatures lead to hastening glacier melting, such as the Gangotri, the glacier that is closest to Dharali. According to the United Nations Environment Programme, rising temperatures in the Himalayas will ultimately reduce the size of glaciers, resulting in a reduction in the long-term availability of water for agriculture, people and power systems. It will also cause more solar energy absorption – accelerating the effects of global warming – because areas of glacial melting will be replaced by water or land, and the amount of light currently reflected by existing glaciers will decrease.


Al Jazeera
2 days ago
- Al Jazeera
India's flood rescue efforts hampered by landslides, blocked roads
Rescue workers are battling heavy rain and blocked roads after at least four people were killed and dozens reported missing after flash floods and landslides swept through parts of India's northern Himalayan state of Uttarakhand. The flood struck Dharali, a village in Uttarkashi district and a popular stop on the way to the Hindu pilgrimage town of Gangotri, after a sudden surge of muddy water mixed with debris engulfed the valley on Tuesday. The flooding was triggered by intense monsoon rains, which continued to lash the region into Wednesday, complicating rescue efforts. Al Jazeera understands that among the missing are at least eight soldiers from a nearby army base, while more than 190 people have been rescued. Telephone lines remain damaged, and communication with the affected area is limited. Roads leading to the village have either collapsed or been blocked by large boulders, according to local official Prashant Arya. 'A large part of the village is engulfed in mud,' he told the news agency Reuters. 'Some areas are covered up to 15 metres deep – enough to bury entire buildings.' The Indian army said it is leading efforts to find approximately 50 people still unaccounted for. Mohsen Shahedi of the National Disaster Response Force said 'the search for the missing is continuing'. The army's central command confirmed that 'additional military columns' have been deployed, along with tracker dogs, drones and heavy earthmoving equipment. Military helicopters are delivering supplies, including medical aid, and evacuating those stranded. Mobile and electricity towers were swept away by the floodwaters, forcing authorities to issue satellite phones to rescue teams. Television footage showed torrents of dark, debris-filled water crashing through Dharali, sweeping away buildings and roads as residents fled for their lives. A video shared by the office of Uttarakhand's chief minister showed parts of the village buried under mud. Chief Minister Pushkar Singh Dhami confirmed that about 130 people had been rescued by Tuesday night, and that helicopters were ready to deliver relief supplies to remote areas cut off by the flooding. 'People didn't understand what was happening. The floodwaters hit them in 15 seconds,' Suman Semwal told The Indian Express, recounting how her father, watching from a neighbouring village upstream, saw the flood hit with a 'thud' and 'unimaginable magnitude'. The Indian Meteorological Department said that water levels in all major rivers in Uttarakhand had risen above the danger mark. 'Residents have been relocated to higher ground due to rising water levels caused by the incessant rains,' the Indian Army said in a statement. Hydrologist Manish Shrestha said 270mm of rainfall recorded in 24 hours qualifies as an 'extreme event', particularly dangerous in mountainous regions where such rainfall has a 'more concentrated' impact. Shrestha, from the International Centre for Integrated Mountain Development in Nepal, added that such intense rainfall events are becoming more frequent and could be linked to the climate crisis.


Al Jazeera
3 days ago
- Al Jazeera
At least four dead, dozens missing as flash floods hit north India village
Flash floods have swept through a Himalayan village in northern India, killing at least four people and leaving more than 50 missing, according to officials, who warned that the toll could rise further. Videos broadcast on Indian media on Tuesday showed a terrifying surge of muddy water sweeping away buildings in Uttarakhand state's Dharali village. Several people could be seen running before being engulfed by the dark waves of debris that uprooted entire multistorey buildings. A wide swath of the village was swamped by deep debris. In places, the mud lapped at the rooftops of houses. Four people were killed and many more have been rescued so far, Uttarkashi district administrator Prashant Arya told local media. 'A massive mudslide struck Dharali village in the Kheer Gad area near Harsil, triggering a sudden flow of debris and water through the settlement,' the Indian Army said in a post on X. Rescue teams were deployed 'on a war footing' to the Himalayan state of Uttarakhand, said state Chief Minister Pushkar Singh Dhami in a statement on Tuesday, adding: 'We are doing everything possible to save lives and provide relief.' Teams from the army and disaster response forces reached the area, local authorities said, with workers trying to rescue people trapped under debris and sludge. India's National Disaster Management Authority said it requested three helicopters from the federal government to assist in the rescue and relief operations, as rescuers struggled to access the remote terrain. 'Luckily, most of the people were at a fair in a safe location,' said a disaster official who asked not to be named, since he was not authorised to speak to the media. Images released by the army, taken from the site after the main torrent of water had gone, showed a river of slow-moving mud. Red warning issued Prime Minister Narendra Modi expressed condolences to those 'affected by this tragedy… No stone is being left unturned in providing assistance to the people,' he said in a statement posted on social media. The India Meteorological Department issued a red alert warning for the area, and recorded 'extremely heavy' rainfall of about 21cm (8in) in isolated parts of Uttarakhand. It also forecast more heavy rains in the region in the coming days. Authorities have asked schools to remain closed in several districts, including Dehradun and Haridwar cities. Sudden, intense downpours over small areas known as cloudbursts have become increasingly common in Uttarakhand, a region prone to flash floods and landslides during the monsoon season from June to September. Cloudbursts have the potential to wreak havoc by causing intense flooding and landslides, affecting thousands of people in the mountainous regions. Experts say cloudbursts have increased in recent years partly due to climate change, while damage from the storms also has increased because of unplanned development in mountain regions. More than 6,000 people died and 4,500 villages were affected when a similar cloudburst devastated Uttarakhand state in 2013. A 2023 report by Nepal-based International Centre for Integrated Mountain Development found that glaciers are melting at unprecedented rates across the Hindu Kush and Himalayan Mountain ranges. The study found that at least 200 of the more than 2,000 glacial lakes in the region are at risk of overflowing, which can cause catastrophic damage downstream. The UN's World Meteorological Organization said last year that increasingly intense floods and droughts are a 'distress signal' of what is to come, as climate change makes the planet's water cycle ever more unpredictable.