After the completion of the Udhampur-Srinagar-Baramulla Rail Link (USBRL), the 125-km Rishikesh-Karnaprayag line is another 'Himalayan project' of the Indian Railways. On April 16, it completed a major breakthrough of a 14.57 km long tunnel, also called T-8, on the line, which is slated to be India's longest transportation tunnel, marking the first instance of the Indian Railways successfully using Tunnel Boring Machine (TBM) for excavation in the Himalayan geology. Navratna PSU (RVNL) is tasked with implementing the Rishikesh-Karnaprayag project to ensure its timely completion. In an interview with The Indian Express, PRADEEP GAUR, chairperson and MD of RVNL tells DHEERAJ MISHRA the the Rishikesh-Karnaprayag project is of paramount significance as it is a gateway to the China border.
Edited Excerpts:
What is the importance of the Rishikesh-Karnaprayag line?
The Rishikesh-Karnaprayag Railway line is important mainly for two reasons. First, it is rail connectivity to the people in the remote areas of the hills. Out of 125 km of the project, a total of 105 km is going through the tunnels and then bridges. So, virtually except for yards, it is a completely underground train. It will provide safe travel in all weather as roads built alongside the hills are always vulnerable to landslides.
Secondly, it is a movement towards the China border. This is declared a strategically important project. So far, it is up to Karnaprayag, but it has been planned to take it beyond. All this will help to move the heavy Army machinery to the border in a camouflage condition because almost all the movement will be done under the tunnel.
The line will be extended to Joshimath, Gangotri, Yamunotri for Char Dham. We have already submitted the Final Location Survey and detailed cost to the Railway Board. The extension project is yet to be sanctioned. The Army wants to extend it to Mana, which is located at a very high level, almost 3,500 m above sea level. It will be taken as far as we can take this line.
Why did you use the Tunnel Boring Machine (TBM) in T-8?
We got this project in 2012 and after a detailed survey, we submitted the estimates to the government in 2016. From 2016 to 2019, we did a detailed investigation, completed land acquisition and forest clearance. We started working on the project in 2020.
T-8 is going to be the longest tunnel in India. Beside these two openings, there was not any possibility to have any other opening on this stretch. If we would have excavated this tunnel through the conventional method, it would have taken nine years to complete it. So, because of uniform geological conditions, we decided that we will use the Tunnel Boring Machine (TBM). Usually, people are not confident in using TBM in the Himalayas, and rightly so, because there are many cases of failure. In addition to the geology, the movement of tectonic plates also makes tunneling difficult. The geology of the Alps mountain range is similar to ours, but the movement of tectonic plates make it more challenging.
The geology of the rock in the tunnel can be understood as the average MPa (a unit of pressure commonly used to measure the compressive strength of rocks) of the rock is around 35. While the granite has more than 200 MPa. So the mountain is very fragile and as we move ahead excavating, there is always a risk of squeezing or shrinking of the opening, which can also lead to a collapse.
How did you overcome these challenges?
Look, given the geology of the area, it was obvious that we will face a number of challenges. But we anticipated all these things in advance and planned accordingly. The important thing about tunneling is what you can predict. To ensure safe and efficient excavation, one has to predict all the possible things that may occur during the work. Once you do this, you will be fully prepared.
So, we did an extensive investigation with Airborne Electromagnetic testing. Under this technique, there is a big frame which is carried by the helicopter over the alignment. The machine bombards the electromagnetic radiation, which strikes on the alignment. Using this technology, we got to know about the mountain strata.
Second, the machinery used in the tunnel is the latest state of art machinery in the world like jumbo dills, loaders, shotcrete machine, multi-service vehicles, etc.
For instance, in drill and blast, first we drill a hole and then fit it with explosives for the blast. Now the alignment of the hole is very important. If you drill the hole correctly, it will blast exactly as much as you designed. If you drill it crookedly, it will overbreak the rock. Using these latest machines, we have never had any problem with overbreaking.
Along with this, we streamline the tendering system. We took the geological risk on our head so that the contractor does not feel overburdened with the concerns of mishappening. We owned up the investigation that if anything goes wrong, RVNL will compensate the contractors. It was one of the biggest factors which gave them confidence.
How was the alignment of the line decided?
Tunneling does not mean to call a tender and ask the contractor to excavate the mountain. We should spend on 'Sharpening the axe', like other developed countries do. We did around six years of investigation and if we had not done this, we would not have been able to achieve all this. If you are making an alignment, which avoids the dangerous pitfalls, half of work is done.
From which countries were the machines procured and how were they transported to the site?
The machinery used in the tunnel was bought from two companies, Swedish company Epiroc, a Finnish company Sandvik. We bought almost 40 fully automatic machines for the tunnel. TBM was bought from the German company Herrenknecht. The important thing is that the machine was manufactured in Germany, brought to Mundra port after dismantling it and then brought to the site. We faced challenges in transportation after Rishikesh as it lies in the hilly area.
There is a small bridge spanning almost 100 m at the Ganga. We did not know the load carrying capacity. Because, without knowing the capacity, it was not possible to transport such heavy machinery. So we did a load test.
The heaviest part of the machine was 168 tonnes. That was a huge challenge. We wanted to carry it in one single piece. We could have dismantled it and transported it part by part, but we could not have achieved finishing while assembling at the site as compared to the factory finishing.
Another reason is that the most critical part of the TBM, which is called main drive, had the chances of shields being damaged. You can not drive the TBM if the shield is damaged and the replacement of these parts inside the tunnel was almost impossible. So we did not take any chances on this.
Along with this, there were chances of dust accumulation and ingression at the site during assembling the TBM, which had a very bad impact on its working and dust particles could cut the shield. So it was decided to transport it in one part.
It is a Rs 250 crore machine. Its dimension was also large, almost 6.8 m. So, in the narrow area, we had to lift it and stand it vertically using the crane. After crossing the narrow road, we again made it horizontal. It took 2.5 months for the complete assembling of the TBM.
What is the reason for using two tunneling methods?
From ordering a TBM to the commissioning, it takes almost 16 months. So in this tunnel, as it is 14.57 km long, we did not wait for the starting of the TBM and began excavation through New Austrian Tunnelling Method (NATM) from the other side. The actual TBM excavation started in March 2023. Out of the 14.57 km, 10.47 was excavated through by TBM and 4.11 km by NATM. It took 760 days to excavate 10,470 m by TBM. So the average progress was 415 m per month.
It is the world's second fastest excavation in the category of 9-10 m tunneling. The fastest is 423 m per month in Spain's cabrera tunnel. But they had good geology of limestone. Our geology is of phyllite rocks. Stronger the mountain, the easier it is to tunnel in it.
Kashmir Rail Link is also a similar project. Were there any learnings drawn from it for the Rishikesh-Karnaprayag Line?
Yes, the most important learning was the alignment to avoid any additional expenditure. In the Kashmir rail line, accessibility was a major issue. The alignment was deep into the area which was remote, where there was no connectivity by the road. So we had to build a road for transportation of machinery. We built approach roads of 215 km.
In this alignment, we took care of these things that let's not make big roads and let's have tunnel portals near the highways or where there is an accessibility. So we made only 11-12 km road in this project. Thus the additional work can be avoided.
There are big bridges like Chenab and Anji Khad in the Srinagar line. In this, we took an alignment in such a matter that we do not have to build big bridges. In this project, the bridges are a maximum of 50 m high. It saved us a lot of money, time and resources.
What is the completion target for Rishikesh-Karnaprayag line?
Our target is to start the operation of the train by December 2026. The total tunneling on the line is 213 km, which includes main tunnel, escape tunnel, out of this, 195 km is complete. All this has been done in just three years and nine months. Our aim is to complete the excavation by the end of this year.
What is the next major project of RVNL?
Our next major project is 63-km long Bhanupli (Punjab) to Bilaspur (Himachal Pradesh) line, which will further go up to Leh, Ladakh.
Dheeraj Mishra is a Principal correspondent with The Indian Express, Business Bureau. He covers India's two key ministries- Ministry of Railways and Ministry of Road Transport & Highways. He frequently uses the Right to Information (RTI) Act for his stories, which have resulted in many impactful reports. ... Read More

Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Aviation Watchdog To Probe Highway Landing Of Chopper Headed To Kedarnath
Aviation Watchdog To Probe Highway Landing Of Chopper Headed To Kedarnath

NDTV

time2 hours ago

  • NDTV

Aviation Watchdog To Probe Highway Landing Of Chopper Headed To Kedarnath

The Directorate General of Civil Aviation will carry out an investigation into the emergency landing made by a private helicopter carrying pilgrims to Kedarnath. The chopper landed on a highway near the Bharasu helipad in Uttarakhand's Rudraprayag district on Saturday afternoon due to a suspected technical fault, and all passengers on board are safe, said officials. The Directorate General of Civil Aviation (DGCA) was informed of the incident. A team from the Directorate of Air Safety (North Region) is being dispatched to the site for an on-ground assessment of the aircraft and the cause of the malfunction. Officials said the helicopter has been secured at the site and further investigation will reveal the exact cause of the suspected control malfunction. Soon after take-off, the pilot, Captain RPS Sodhi, detected a suspected malfunction in the helicopter's collective control - a critical component that manages the aircraft's lift. In response, he executed a precautionary hard landing on a road just below the Bharasu helipad. According to Uttarakhand ADG (Law and Order) Dr V Murugesan, all passengers on board are safe. The pilot reported a backache after the landing and was taken to a hospital for evaluation. "There is no report of any casualties. The situation was handled efficiently, and the pilot made a safe landing," he said. The CEO of the Uttarakhand Civil Aviation Development Authority (UCADA) confirmed that the helicopter, while flying from Sirsi with passengers, opted to land on a road near the helipad instead of returning to or landing on the designated helipad itself. The helicopter, an AW119 operated by Kestrel Aviation Private Limited (registration VT-RNK), is a single-engine model designed for high-altitude operations. It is part of the fleet used for shuttle services to Kedarnath during the annual Char Dham Yatra. These services are especially vital during peak pilgrimage season, allowing devotees to access the Himalayan shrine with relative ease and speed. The UCADA CEO confirmed that all other helicopter operations to Kedarnath are proceeding as per schedule and there has been no disruption.

A journey to remember and big boost to connectivity: PM Modi after inaugurating Chenab rail bridge
A journey to remember and big boost to connectivity: PM Modi after inaugurating Chenab rail bridge

India Gazette

time18 hours ago

  • India Gazette

A journey to remember and big boost to connectivity: PM Modi after inaugurating Chenab rail bridge

New Delhi [India], June 7 (ANI): After inaugurating much-awaited and world's highest railway arch bridge over the river Chenab during his day-long visit to Jammu and Kashmir on Friday, Prime Minister Narendra Modi said that today's development works will enhance the development journey of Jammu and Kashmir. In a post on social media platform, X, PM Modi said, ' A journey to remember and a big boost to connectivity! Travelled from the Chenab Rail Bridge to Anji Bridge and thereon to Katra for the public meeting. Today's development works will enhance the development journey of Jammu and Kashmir' The architectural marvel Chenab Rail Bridge, situated 359 metres above the river, is the world's highest railway arch bridge. It is a 1,315-metre-long steel arch bridge engineered to withstand seismic and wind conditions. A key impact of the bridge will be in enhancing connectivity between Jammu and Srinagar. The Vande Bharat train moving on the bridge will take just about three hours to travel between Katra and Srinagar, reducing the existing travel time by two to three hours. Prime Minister Narendra Modi on Friday flagged off two Vande Bharat Express trains from Katra Railway Station, directly connecting the Jammu division with marks a major milestone in Jammu and Kashmir's railway connectivity. Before flagging off the trains, Prime Minister Modi interacted with school children onboard and also spoke with railway staff members present on the train. The new Vande Bharat Express service will reduce the travel time between Katra and Srinagar from the current 6-7 hours by road to just about 3 hours. The trains aim to provide a fast, comfortable, and reliable travel option for residents, tourists, and pilgrims. The train will run through the Anji Khad Bridge, which is India's first cable-stayed railway bridge, and the Chenab Bridge, which is the highest railway bridge in the world. These trains have been specially designed to operate in the cold climatic conditions of the Kashmir Minister Modi inaugurated the world's highest railway arch bridge - 'Chenab Railway Bridge' and India's first cable-stayed 'Anji Bridge' in Jammu and Kashmir's Reasi and Kashmir Lieutenant Governor Manoj Sinha, Chief Minister Omar Abdullah and Union Railways Minister Ashwini Vaishnaw were present during the inauguration. Before the inauguration of the bridge on the Chenab, the Prime Minister inspected the railway arch bridges are part of the ambitious Udhampur-Srinagar-Baramulla Railway Link (USBRL) project in Jammu and Kashmir. The iconic Chenab Railway Bridge, the world's highest railway arch bridge, is part of the Katra-to-Sangaldan stretch, connecting New Delhi directly with Kashmir via Katra. Situated in the Reasi district of Jammu and Kashmir, the Chenab Bridge is an engineering marvel standing at a height of 359 meters above the riverbed. It will officially connect the Kashmir Valley with the rest of India via rail for the first time in history. The project faced numerous engineering and logistical challenges due to the region's difficult terrain and seismic sensitivity. Yet, after years of meticulous work, the bridge now stands as a testament to India's technological prowess and commitment to inclusive marks a transformative chapter in India's infrastructural landscape, promising greater connectivity, economic growth, and social integration in the region. The Udhampur-Srinagar-Baramulla Rail Link (USBRL) project is 272 km long USBRL project, constructed worth around Rs 43,780 crore, includes 36 tunnels (spanning 119 km) and 943 bridges. The project establishes all-weather, seamless rail connectivity between the Kashmir Valley and the rest of the country, aiming to transform regional mobility and drive socio-economic integration. (ANI)

Modi inaugurates world's highest rail bridge in Kashmir (VIDEO)
Modi inaugurates world's highest rail bridge in Kashmir (VIDEO)

India Gazette

timea day ago

  • India Gazette

Modi inaugurates world's highest rail bridge in Kashmir (VIDEO)

The crossing is part of a new train line connecting the region to the rest of India for the first time Indian Prime Minister Narendra Modi on Friday inaugurated two railway bridges that are a part of a new link connecting the Union Territory of Jammu and Kashmir with the rest of the country. It is the first time he has been to the region since the deadly Pahalgam attack on tourists, which triggered a diplomatic and military clash between New Delhi and Islamabad. During his speech on Friday, Modi highlighted the importance of developing Kashmir's infrastructure. The region has been a point of contention between India and Pakistan for decades. The prime minister opened the Chenab bridge - labeled by Indian authorities the world's highest railway bridge - and Anji bridge, India's first cable-stayed rail bridge. Both are parts of the Udhampur-Srinagar-Baramulla Rail Line project, a 272-kilometer long railway link that Modi hailed as Jammu and Kashmir's "new strength" and a "testament to India's growing capabilities." The Chenab bridge, built over the river of the same name, towers 359 meters above the riverbed and rises 35 meters higher than the Eiffel Tower. It was constructed at an estimated cost of approximately $173 million, according to the official statement. The Anji bridge, a cable-stayed railway bridge constructed in a difficult Himalayan terrain, is 331 meters high and is anchored by 96 high tensile cables. The total length of the cables used in the bridge is 653 kilometers, the statement noted. Modi also announced new trains would run between Jammu's capital Srinagar, and Katra, where Vaishno Devi temple, one of the most visited and revered Hindu pilgrimage sites in India, is located. It marks the completion of a 42-year-old project to link Kashmir with the rest of the country via railway. A test run on his route was carried out by the railway authorities in December last year.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into the world of global news and events? Download our app today from your preferred app store and start exploring.
app-storeplay-store