
PSEG to file court order seeking temporary access to properties along MPRP to review land
PSEG needs to access properties in order to conduct field studies along the route of the Maryland Piedmont Reliability Project (MPRP), a 500,000-volt line that will extend for almost 70 miles across Frederick, Baltimore and Carroll counties.
In Frederick County, the MPRP would run through the southeastern and southern parts of the county near New Market and Ijamsville, continue toward Buckeystown and Adamstown, and end at the Doubs substation.
Maryland is requiring that PSEG conduct these studies, which will help illustrate the full environmental effects of the MPRP, to move the project forward.
Thousands of residents and many elected officials from around Maryland have mobilized against the project and have expressed fear, anger and frustration about the MPRP cutting through properties or possibly hurting the environment.
PSEG has a contract with PJM Interconnection, the company that coordinates electricity movement in 13 states and Washington, D.C., to build the MPRP to address anticipated increases in power demand.
Part of this increased demand is due to new data centers to be sited in Maryland and Virginia, which are estimated to require up to 7,500 megawatts of electricity.
Additionally, PJM has said that 11,000 megawatts of power generation across the grid have recently been deactivated while power demand continues growing.
PSEG sent out about 800 letters in the fall to the owners of about 600 tracts of property who will be impacted by the MPRP route. Some of the land parcels have multiple owners.
For months, land agents on behalf of PSEG have been reaching out to affected property owners to discuss the company temporarily accessing properties to conduct environmental surveys and field studies.
Some owners have been offered compensation of $1,000 for a temporary right-of-entry. Most people have either not responded or denied PSEG's requests.
Jason Kalwa, the project's director, said field data is used for most permits to confirm environmental conditions. He emphasized that gaining temporary access to properties through this court order would not be the same as PSEG using eminent domain.
Eminent domain is a governmental power to seize private property for public use with just compensation.
PSEG will not have access to the properties anymore after completing the field surveys.
A judge would decide how much time to grant.
'The property owners are not giving up any other rights. This is temporary access. This is effectively to allow our experts, environmental and otherwise, to walk on the property, take an assessment of what they see there,' Kalwa said in an interview.
'... It's not eminent domain. It gives us no permanent rights to the property. It merely gives us access to the property to conduct surveys, which are necessary for many types of permits out there.'
PSEG is asking for a Certificate of Public Convenience and Necessity from the Maryland Public Service Commission as part of developing the MPRP.
This certificate authorizes the construction or modification of a new generating station or high-voltage transmission lines and is necessary for the MPRP to move forward.
'The MPRP will prevent extensive, severe, and widespread thermal overloads and voltage collapse conditions (reliability violations) from occurring on the bulk transmission system that serves Maryland electric customers and the surrounding region,' PSEG said in its application.
On March 26, the Power Plant Research Program, which is part of the Maryland Department of Natural Resources, said PSEG's certificate application is incomplete — it doesn't have enough information on alternative project routes or specific environmental and socioeconomic impacts.
The Maryland Public Service Commission said on Jan. 10 that it would start making a procedural schedule to move the application forward once the Power Plant Research Program deemed the application as complete.
The program said PSEG didn't provide 'any discussion detailing why each of the alternative routes other than the proposed route ... were rejected and instead, focuses on why the proposed route was selected.'
The program also said the application doesn't adequately show the environmental and socioeconomic consequences of the MPRP's construction and operation.
Specifically, the application doesn't include field studies, which are necessary to verify that the MPRP's impacts are correctly documented and appropriate mitigation actions are taken.
The program said the application lacked these field-based surveys:
* Wetland delineations
* Forest stand delineations
* Geotechnical surveys
* Surveys on sensitive species project review areas
* Maryland Historical Trust-required field surveys
'Without field-based information, [the program] cannot fully evaluate the Project's impacts to Maryland's socioeconomic and natural resources,' the program said in a letter to the Public Service Commission dated March 26.
The Power Plant Research Program said it isn't opposed to scheduling a prehearing conference for PSEG's application to set a limited procedural schedule, but it still needs more information outlined in its letter to finish assessing PSEG's application.
Once it's determined that the application is complete, further procedural dates can be scheduled.
Need to seek judicial support
The same day the program gave its letter to the commission, PSEG filed a response asking for a prehearing conference to be held to create a procedural schedule so the MPRP can be built by June 1, 2027 — the date that PJM said the MPRP has to start operating.
To meet this deadline, PSEG has to start constructing the transmission line by January and therefore needs a Certificate of Public Convenience and Necessity by then.
PSEG also wants the conference to be held to rule on more than 170 petitions to intervene, most of which were filed by people with properties on or near the MPRP route.
A petition to intervene is a request to become a formal party in a case and be able to actively participate in the legal process and influence the outcome of a project.
PSEG also asked the Public Service Commission to determine its application is complete for the purpose of setting a procedural schedule.
The company said the information the Power Plant Research Program wants 'go to issues that [the program] would like to better understand and not as required information that is missing' under Maryland law.
Still, PSEG anticipated that the Power Plant Research Program would ask for field studies, which is why the company has been trying to access properties. Its response says that where 'necessary and appropriate, the Company may also need to seek judicial support to conduct the surveys.'
Bill Smith, a PSEG spokesperson, said the court filing PSEG plans to submit on April 15 will involve getting temporary access to about 90 properties.
There will be multiple filings requesting temporary access if PSEG can't negotiate with the remaining property owners for voluntary rights-of-entry.
The company is still willing to have discussions with landowners regarding compensation for rights-of-entry to avoid taking court action.
Kalwa said PSEG is aware that some property owners are extremely hostile to the company and won't welcome the idea of company representatives walking on their land.
'The safety and security of our team, the contractors that work for us, members of the public are of utmost importance. ... We just ask for folks' patience throughout all of this. We understand it's difficult,' he said.
'For the folks that don't want to talk to us, if they could, if they'd be willing to have a conversation with us, I think they'll find us to be reasonable, and hopefully, that'll calm some of their fears.'
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles
Yahoo
2 days ago
- Yahoo
Data Centers Need Own Power Supply, US Grid Watchdog Says
(Bloomberg) -- Data centers looking to connect to the largest US grid must bring their power supply, the system's independent watchdog said. The US-Canadian Road Safety Gap Is Getting Wider Sunseeking Germans Face Swiss Backlash Over Alpine Holiday Congestion To Head Off Severe Storm Surges, Nova Scotia Invests in 'Living Shorelines' Five Years After Black Lives Matter, Brussels' Colonial Statues Remain Festivals and Parades Are Canceled Amid US Immigration Anxiety The warning escalates the watchdog's position from just a month ago when it said the grid operated by PJM Interconnection LLC, stretching across 13 states from Virginia to Illinois, has no spare supply for new data centers and suggested developers build their own power plants. However, in its quarterly report released Thursday, watchdog Monitoring Analytics LLC said it 'recommends that large data centers be required to bring their own generation.' The grid is home to the highest concentration of data centers whose soaring power demand has strained and aging infrastructure, driven up costs for consumers and become a political flashpoint. 'The current supply of capacity in PJM is not adequate to meet the demand from large data center loads and will not be adequate in the foreseeable future,' the report said. 'There is still time to address the issue but failure to do so will result in very high costs for other PJM customers.' PJM said in a statement that it's working with all of its stakeholders, including the market monitor, to address the imbalance of supply and demand, which it said was primarily driven by unprecedented growth in electricity use. --With assistance from Mark Chediak. (Updates with comment from PJM in last paragraph) Americans Are Getting Priced Out of Homeownership at Record Rates What Declining Cardboard Box Sales Tell Us About the US Economy Dubai's Housing Boom Is Stoking Fears of Another Crash Bessent on Tariffs, Deficits and Embracing Trump's Economic Plan Why It's Actually a Good Time to Buy a House, According to a Zillow Economist ©2025 Bloomberg L.P. Error while retrieving data Sign in to access your portfolio Error while retrieving data Error while retrieving data Error while retrieving data Error while retrieving data


Bloomberg
2 days ago
- Bloomberg
Data Centers Need to Bring Own Power Supply, Grid Watchdog Says
Data centers looking to connect to the largest US grid must bring their power supply, the system's independent watchdog says. The warning escalates the watchdog's position from just a month ago when it said the grid operated by PJM Interconnection LLC, stretching across 13 states from Virginia to Illinois, has no spare supply for new data centers and suggested developers build their own power plants.

Epoch Times
4 days ago
- Epoch Times
Grid on the Brink: PJM's Record Auction Proves We Must Keep—and Build—More Coal Plants
There comes a point when even the most willfully blind must acknowledge what is plain to see. That point arrived quietly—but thunderously—on July 22, 2025, when PJM Interconnection, the grid operator for 65 million Americans across 13 states and the District of Columbia, released the results of its latest capacity auction.