Access road to KIA southern zone expected completion within this month, says Kota Sentosa rep
KUCHING (July 3): The access road to the southern zone of Kuching International Airport (KIA) is almost completed, said Kota Sentosa assemblyman Wilfred Yap.
When updating the public on the status of its work progress, Yap said the physical progress of the project was at 95 per cent as of June 25.
Having been briefed by Public Works Department (JKR) Kuching Divisional Engineer Wang Say Kwang during a meeting yesterday, Yap in a statement highlighted the remaining works and their targeted completion dates.
'Road A/D Junction: 300 metres of road widening works are in progress and are targeted for completion by July 7; Road A (Sungai Kuap Bridge Approaches): 750 metres of road base construction from CH3+200 to CH3+950 is ongoing and targeted for completion by July 21; and Street Lighting, Substation and Traffic Light: Following verification of the substation platform by Sarawak Energy Berhad (SEB) this week, all electrical systems will be energised, with all related works scheduled for completion by July 31,' he said.
A critical component of this project involves the Underpass Airfield Ground Lighting (AGL) system, which requires relocation of the existing AGL to a new vertical profile that complies fully with stringent aviation safety standards and, this includes raising 13 rows of AGL poles along the aircraft approach flight path, Yap said.
He added that due to the high level of technical complexity and safety considerations, this work required approvals from the Malaysia Airports Sdn Bhd (MASB); Civil Aviation Authority of Malaysia (CAAM) Kuching Office and; CAAM Division of Air Navigation Services and Aerodrome (ANSA) Kuala Lumpur.
'I am pleased to inform that the final approval from the CAAM Division of ANSA Kuala Lumpur was officially granted via email on July 1, 2025.
'This approval marks a significant milestone, enabling the contractor to proceed with the remaining AGL works and, the contractor has indicated that they will require approximately one month to complete these activities,' said Yap.
In line with the highest safety precautions, he said the road can only be opened to public use after the completion of the scheduled Flight Testing Window from this Sept 21 to 26, which is necessary to ensure that all airfield safety systems are fully operational and certified.
Yap said he has requested JKR to supervise and monitor the project contractor closely, now that all regulatory approvals have been secured, to ensure that all outstanding works are completed in a timely manner.
'I would like to ask for the patience and understanding of all road users and residents, as these final steps are critical to uphold aviation safety and public safety. It is our shared priority to ensure the road is opened safely for public use by the end of September 2025.
'I wish to extend my appreciation to JKR, all relevant agencies, the contractor, and stakeholders for their cooperation and commitment to the successful delivery of this important infrastructure project that will benefit the people of Kuching and Sarawak,' he concluded. access road Kuching International Airport Wilfred Yap
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


New Straits Times
a day ago
- New Straits Times
257 accidents, 22 fatalities recorded on Gerik–Jeli highway as of June 2025
KOTA BARU: From January to June this year, 257 accidents involving 442 vehicles were reported along the East-West Highway (JRTB) Gerik-Jeli. According to Gerik police chief Superintendent Abdul Samad Othman, the accidents included eight fatal cases, resulting in 22 deaths. Among the fatalities were 15 students from Universiti Pendidikan Sultan Idris (UPSI), who were killed in a horrific accident on June 9. "The number of deaths reflects the total number of victims who died, as fatal accidents often involve more than one casualty. "For example, a fatal bus crash on June 9 alone claimed 15 lives, all of whom were students from UPSI," he said when contacted today. Abdul Samad added that the 442 vehicles involved in the accidents included 287 cars, followed by 55 multi-purpose vehicles (MPVs) or vans, 42 motorcycles, 38 pickup trucks, 17 lorries, and three buses. On July 22, Bernama reported that, according to the 2024 traffic census by the Public Works Department, the JRTB route remains at a good level of service, with its current configuration able to accommodate the present traffic volume. Works Minister Datuk Seri Alexander Nanta Linggi reportedly said that a total daily traffic volume of 2,409 vehicles was observed on the JRTB route, with heavy vehicles accounting for 751 vehicles, or 31.2 per cent of the total. "The JRTB route is categorised as hilly terrain, with its alignment designed to follow the contours and topography of the Titiwangsa mountain range. "Its geometric design as the two-lane single carriageway has met the required technical and functional standards for its construction," he said. To improve road safety, Public Works Department director-general Datuk Roslan Ismail said the department has implemented a blackspot treatment programme under its Road Safety Infrastructure Upgrade initiative. Since 2018, 16 accident-prone locations along the route have been identified. "The approach is based on the principle of 'Low Cost, High Impact.' If the treatment method applied is appropriate to the type of accident occurring, the accident rate at those blackspot locations can be reduced at relatively low cost," he said.


The Star
a day ago
- The Star
25 scholars on global track
Set to soar: The scholarship recipients with (centre row, from left) Kim Yee, Prof Zhang, Wang, Prof Sze Wei and Tee. THE opportunity to pursue tertiary education both locally and abroad is now within reach for 25 scholarship recipients. Thanks to the Malaysia-China Talent Development Programme, 10 Tunku Abdul Rahman University of Management and Technology (TAR UMT) students will pursue a Bachelor of Metallurgical Engineering micro-credential programme, spending the first two years here, followed by another two years at the University of Science and Technology Beijing (USTB). The other recipients will take up bachelor's degrees in accountancy, finance, investment, electrical and electronics engineering, mechanical engineering, and mechatronics, including four students from Universiti Tunku Abdul Rahman (UTAR). Now in its second year, the initiative is a collaboration between TAR UMT, USTB and Eastern Steel Sdn Bhd (ESSB). The cross-border integrated programme aims to bridge the gap between academia and industry at a global level. The scholarship award presentation ceremony was held recently at the TAR UMT main campus in Kuala Lumpur, attended by its president Prof Datuk Dr Lee Sze Wei, USTB International Students Centre deputy director Prof Zhang Hu, ESSB chief executive officer Wang Shenghua, ESSB executive director Datuk Tee Choon Hock, and UTAR Lee Kong Chian Faculty of Engineering and Science deputy dean Dr Lee Kim Yee. In his speech, Prof Lee said the programme offers a clear and future-focused pathway for developing talent by bridging education and career in a seamless and purposeful way. 'This helps to close the academia-industry gap and meet the growing demand for graduates who are well-educated and workforce-ready,' he said. His counterpart Prof Zhang, meanwhile, said both sides have worked diligently to improve the programme's structure, enhance coordination, and support participating students more effectively, following the pioneer initiative in July last year. 'This reflects our commitment to strengthening collaboration with industries, integrating academic learning with practical experience, and ensuring the growth of both education and the workforce,' he said. Separately, Wang said the first batch under the programme has shown results, with two of the students joining the company and contributing their expertise. 'The success is not only a concrete action towards empowering local talent and investing in the future, but also a vital step in fostering deeper integration between education and industry in both Malaysia and China.' Scholarship recipient Mei Jian Hao expressed his gratitude for the opportunity to further his studies at both TAR UMT and USTB. 'This will help deepen our technical knowledge and abilities, broaden our horizons, and lay a strong foundation for our future careers.' Another recipient Heng Jen Yi said he was selected after going through interviews, based on his academic results and active participation in extracurricular activities in school. 'The scholarship and the opportunity to study overseas will inspire us to strive harder in pursuit of our dreams,' he said.


The Sun
a day ago
- The Sun
Northern Coastal Highway to boost Sarawak connectivity by 2030
LIMBANG: The Northern Coastal Highway (NCH) project is set to transform connectivity and development in northern Sarawak, according to Works Minister Datuk Seri Alexander Nanta Linggi. The initiative, covering Lawas and Limbang, aims to integrate regions currently separated by Brunei Darussalam. Nanta highlighted the project's significance during a technical meeting in Limbang, involving teams from the Sarawak and Federal Public Works Departments (JKR), the Ministry of Works, and RECODA. 'This reflects strong collaboration between the Federal and Sarawak state governments,' he said. The NCH will provide a domestic route linking Miri, Limbang, and Lawas without passing through Brunei, reducing reliance on the Miri–Temburong–Limbang route, which currently requires four immigration checks. 'This will enhance mobility, ease daily life, and unlock economic opportunities for rural communities,' Nanta added. Key components include an 87.96 km new road, 10.16 km of access roads, 27 main structures (including 13 bridges), 44 bus stops, and four Rest & Service Areas. Five sections under Phase 1 are underway, with completion expected by 2030. Nanta emphasized the broader impact: 'This project supports the economy, tourism, logistics, and improves well-being.' The NCH will also complement the Pan Borneo Highway, linking Sarawak's central and southern regions with Brunei and Sabah via the Merapok border. - Bernama