Do you dread driving on I-4? See improvements coming this month and more projects ahead
Nobody likes sitting in traffic.
And ranking right up there is the frustration of road work that seems to drag on forever.
So mark this on your calendar: construction of "congestion relief lanes" on one of the busiest sections of Interstate 4 has finished ahead of schedule.
Gov. Ron DeSantis announced this week that 6 miles of added lanes on I-4 will be completed eight months ahead of schedule.
Here's what is going on.
The new lanes, one additional lane in each direction of I-4 from U.S. 27 in Polk County to World Drive in Osceola County, will be open for use beginning the week of April 28, DeSantis said.
"The new lanes will be located on the inside of the existing I-4 mainline to provide motorists with congestion relief," FDOT said.
The project is being completed eight months ahead of schedule.
After DeSantis directed the Florida Department of Transportation to deliver immediate congestion relief along I-4, the department "used an innovative construction approach to open new lanes early."
FDOT launched the Moving I-4 Forward program and introduced a new streamlined method called Modified Phased Design-Build, a news release said.
"Benefits of using this pioneering process include reduced project timelines, travelers spending less time in traffic, fewer taxpayer dollars being spent, and a continued focus on innovation," FDOT said.
In practical application, on the section intended to open the week of April 28, construction crews paved the inner breakdown lanes, converting them to traffic lanes.
The approach allowed new lanes to open "without waiting for full project completion. These lanes will remain open through all future construction," FDOT said.
Yes. The Moving Florida Forward program includes nearly 700 projects across Florida, with $75 billion in infrastructure investment committed since 2019, a news release said.
FDOT listed these projects after the new lanes open the week of April 28:
Segment A: I-4 from east of U.S. 27 to west of S.R. 429. 4.1 miles. Segment B: I-4 from west of S.R. 429 to east of World Drive. 3.4 miles. Highlights include:
Expand I-4 to accommodate up to 12 total lanes at the ChampionsGate Boulevard (C.R. 532) and World Drive interchanges. These additional lanes will consist of up to eight general use lanes and four express lanes (for future use).
East of World Drive to east of U.S. 192. 2.6 miles. Highlights include:
Three general-use lanes and two new express lanes in each direction.
Maintain existing access to State Road (S.R.) 417 from the general-use lanes onI-4. A
New ramps will connect the S.R. 417 toll to the I-4 express lanes.
Replace toll plazas on S.R. 417.
East of C.R. 532 to west of World Drive. 3.1 miles. Highlights include:
Improvements to the State Road (S.R.) 429 interchange, which currently ends at I-4.
Four general-use lanes and two express lanes in each direction.
New ramps will be built to connect the express lanes on I-4 to S.R. 429 and from the I-4 general-use lanes to S.R. 429.
Old Lake Wilson Road will be widened from Sinclair Road to Assembly Court and over I-4 from two to four lanes with sidewalks and bicycle lanes on both sides, including building a second bridge.
West of U.S. 27 to west of ChampionsGate Boulevard (C.R. 532). 3.4 miles. Highlights include:
Adding two express lanes in each direction along I-4.
Adding ramps to connect I-4 express lanes and U.S. 27.
West of Osceola Parkway to east of World Center Drive (S.R. 536). 2.1 miles. Highlights include:
Adding two express lanes in each direction along I-4.
Adding ramps to connect the express lanes and S.R. 536.
Existing I-4 bridges at the Osceola Parkway interchange over Bonnet Creek will be reconstructed.
Poinciana Connector from C.R. 532 to S.R. 429. 3.5 miles. Highlights include:
Extending the Poinciana Connector from where it ends near U.S. 17 to Osceola Polk Line Road, County Road (C.R.) 532.
The I-4 project will continue and connect south of the interchange with S.R. 429.
Final configuration of the new road includes three lanes in each direction with the ability to expand to four lanes in each direction.
Ramps connecting to Osceola Polk Line Road (C.R. 532) will be included.
DeSantis announced the Moving Florida Forward initiative last year at a news conference in Polk County. The program includes nearly 700 projects across Florida.
These projects will "deliver much-needed congestion relief 10 to 20 years ahead of the original schedule," according to FDOT's website. The projects are intended to:
Strengthen resilient infrastructure for future growth.
Improve travel times by reducing congestion.
Increase safety and connectivity.
Enhance the quality of life for the community.
'We launched the Moving Florida Forward initiative to accelerate major transportation projects that reduce congestion and improve connectivity,' DeSantis said.
'With nearly 700 projects underway and $75 billion in infrastructure investment since 2019, we're delivering real results for Floridians and keeping Florida moving.'
This article originally appeared on The Daytona Beach News-Journal: Florida Interstate 4 congestion relief. New lanes opening April 28
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles
Yahoo
an hour ago
- Yahoo
U.S. 231 Road Improvement Project to begin in Bay County
BAY COUNTY, Fla. (WMBB) – The Florida Department of Transportation will begin an intersection improvement project later this summer at U.S. 231 at Pipeline Road in Bay County. According to a news release, the project will cost $2.6 million and will cause lane closures and traffic shifts. Lane closures will not occur during peak travel times of 7 a.m. to 9 a.m. or 3:30 p.m. to 7:30 p.m.; until Labor Day, lane closures will be limited to Sunday through Thursday between 8 p.m. and 6 a.m. Bay County OKs FDOT grant for road resurfacing and other improvements The project includes the installation of new mast arm traffic signals, as well as new signing and pavement markings. Pipeline Road will be widened to include new left turn lanes for accessing U.S. 231, and crews will be removing the median and realigning the intersection; they will also be milling and resurfacing the pavement. Enhancements will be made to stormwater management to include the installation of concrete curbs and gutters as well as a closed pipe drainage system. Completion of the construction is scheduled for mid-2026. Copyright 2025 Nexstar Media, Inc. All rights reserved. This material may not be published, broadcast, rewritten, or redistributed.
Yahoo
a day ago
- Yahoo
S.R. 408 ramps will close overnight at Conway
According to the Florida Department of Transportation (FDOT), drivers should use caution due to overnight closures of the eastbound State Road (S.R.) 408 off-ramp to Conway Road (S.R. 15) (Exit 13) and the westbound S.R. 408 on-ramp from Conway Road from Sunday, June 8, to Thursday, June 12. This work is part of FDOT's resurfacing project on Conway Road from Devonshire Lane to Lake Underhill Road. Work on the ramps will start as early as 11 p.m. nightly and is expected to wrap up by 6 a.m. the next morning, with the final closure ending on Friday, June 13. Detour Information: Motorists traveling north on Conway Road who wish to access westbound S.R. 408 should turn left on Lake Underhill Road and continue west to South Street. Drivers should head west on South Street to access westbound S.R. 408. Alternatively, motorists can head east on Lake Underhill Road, then turn left onto northbound Andes Avenue to access the westbound S.R. 408 entrance ramp. Motorists traveling east on S.R. 408 who wish to access Conway Road should exit early at Bumby Avenue (Exit 12A), continue east on Anderson Street, then turn right onto Lake Underhill Road, continuing east to Conway Road. Please see the attached detour maps for detailed information. In addition to the detours, periodic single-lane closures will occur during daytime and nighttime hours. Click here to download our free news, weather and smart TV apps. And click here to stream Channel 9 Eyewitness News live.
Yahoo
a day ago
- Yahoo
Traffic Advisory: Overnight closures begin for Kirkman expansion project
The Florida Department of Transportation (FDOT) advises drivers of overnight closures on Interstate 4 (I-4) between Kirkman Road (S.R. 435) and S.R. 528 (Beachline Expressway) from Sunday, June 8, to Thursday, June 12. Closures start at 10 p.m. each night and reopen by 6 a.m. the next morning, with the final closure on Friday, June 13. Detour Information for June 8 to 10 Overnight Closures Motorists traveling west on I-4 who wish to access S.R. 528 will be directed to exit early at Exit 75B to southbound Kirkman Road, then continue to the Sand Lake Road (S.R. 482) ramp, staying in the left lane and turning left onto Sand Lake Road at the traffic signal, heading east to John Young Parkway (S.R. 423). Motorists will then turn right onto John Young Parkway, proceeding south to S.R. 528. Detour Information for June 11 and 12 Overnight Closures Motorists traveling west on I-4 will be directed to take Exit 75B to southbound Kirkman Road, then continue to the Sand Lake Road ramp, staying in the left lane and turning left onto Sand Lake Road at the traffic signal, heading east to John Young Parkway. Motorists will then turn right onto John Young Parkway, proceeding south to S.R. 528. From there, drivers who wish to return to I-4 will continue west to the end of S.R. 528 and take the ramp to westbound I-4. Motorists traveling east on Sand Lake Road who wish to access westbound I-4 will turn right onto southbound Turkey Lake Road and proceed to Central Florida Parkway. From there, motorists will turn left onto eastbound Central Florida Parkway and take the first right onto the westbound I-4 entrance ramp. FDOT recommends that drivers follow all posted detour signs. Please note that construction schedules may change due to weather or unexpected circumstances. Click here to download our free news, weather and smart TV apps. And click here to stream Channel 9 Eyewitness News live.