Maha power regulator puts controversial order on hold after solar cos move court
The move comes after a consortium of renewable energy developers challenged the decision, saying it would cripple their ability to provide round-the-clock low-cost power, rendering them uncompetitive.
The court was hearing a plea filed by the National Solar Energy Federation of India (NSEFI), JSW Neo Energy Ltd, and nine other solar developers including Sunsure Solar Park MH One Pvt. Ltd and Solenco Solar Park MH-V Pvt. Ltd.
The developers have called MERC's decision arbitrary, unlawful, and detrimental to the commercial viability of clean energy projects in the state.
MERC, along with the Maharashtra State Electricity Distribution Company Ltd (MSEDCL), submitted that it would not enforce the contested provisions until mid-July.
'The aforesaid statement is accepted as an undertaking given to this court. In light of the aforesaid statement, we find that at this stage, the petitioners are adequately protected and hence, no further ad-interim relief is passed in the above petitions,' the court said on 1 July.
In addition to MERC's 25 June order, the developers have challenged Regulation 115 of the Multi-Year Tariff (MYT) Regulations, 2024, which empowers distribution companies to propose new Time-of-Day (ToD) slots and tariffs.
The core issue before the court stems from MERC's reversal of its March 2024 decision that allowed consumers to draw banked solar power across different ToD slots—enabling both operational flexibility and financial efficiency. Under the revised rules, solar energy banked during, say, 9 am to 5 pm, must be consumed strictly within that window, significantly diminishing the value of banking.
This makes the supply of renewable power to commercial and industrial (C&I) customers more expensive for solar companies. This is because solar power is generated in excess during the morning and afternoon hours when the sun shines the brightest. The excess power during this period is supplied to the grid and drawn by MSEDCL. Later, when the C&I customer needs power when the sun sets, it tends to draw it back from the grid at a nominal fee, usually about 8-10% of the power banked.
Solar producers fear that a change to the banking structure would jeopardize their long-term power supply agreements with C&I consumers as the cost increases.
MSEDCL proposed to change the banking structure as it was getting more expensive for it to supply the power back during non-solar hours from other sources. India suffers from insufficient capacity to store its solar power.
In the court, developers argued that MERC enacted the change without public consultation, a legal requirement in tariff matters, thereby breaching principles of natural justice.
'The review petition (filed before MERC) was neither made available to the stakeholders nor were the stakeholders permitted to address any arguments,' the petition reads, calling the process a 'complete go-by to the established principles of law.'
They also contend that their intervention applications, which sought a hearing in the review proceedings, were dismissed without explanation.
The petition states that nearly 600 MW of solar capacity in Maharashtra is affected by the order.
The developers are seeking to quash both the 25 June directive and Regulation 115, arguing that the latter unlawfully delegates tariff-setting authority to distribution companies.
Legal experts say the case raises broader questions around regulatory accountability and administrative fairness.
'The failure of MERC to provide due process, such as adequate hearing or consultation, before issuing a significantly impactful review order constitutes a direct infringement of the petitioners' fundamental legal right to fair administrative action,' said Kunal Sharma, founder and managing partner at Taraksh Lawyers & Consultants.
He noted that while the petition does not directly challenge Regulation 115, the court could still strike down the order on procedural or jurisdictional grounds.
'The petition derives substantial force from the argument that the revised banking provisions are inconsistent with the existing DOA Regulations and that MERC acted beyond the scope of its limited review jurisdiction,' Sharma said.
Sachit Mathur, managing partner at Emerald Law, offered a different view, suggesting the review order could hold if MERC's rationale is sound.
'With respect to the ToD tariff and banking provisions, the Commission's reliance on review jurisdiction may withstand scrutiny. In particular, the omission of Regulation 20.3 could plausibly qualify as an error apparent on the face of the record,' Mathur said.
MERC maintains that the review order is a clarification, aligning the tariff framework with earlier regulatory processes. It insists that stakeholder input had been taken during the original MYT proceedings and that repeat consultation during the review is not mandatory. It also warned that granting relief solely on procedural grounds could set a sweeping precedent.

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Time of India
an hour ago
- Time of India
Start Kusum C scheme by Aug 20 or face contract cancellation: CESC
Mysuru: Chamundeshwari Electricity Supply Corporation (CESC) managing director KM Munigopal Raju on Friday issued a directive to cancel tenders and re-invite bids if agencies that signed power purchase agreements (PPAs) under the PM Kusum-C scheme failed to commence work by the stipulated deadline. Presiding over a progress review meeting at the CESC headquarters, Raju assessed the status of the scheme's implementation across the five districts under CESC's jurisdiction and reviewed the performance of all executing agencies. "The energy minister, in a recent meeting, expressed serious concern over the delayed implementation of Kusum-C. All agencies must begin work by Aug 20. If not, notices should be issued, tenders cancelled, and fresh bids floated," Raju asserted. He emphasised that the identification of suitable land and the immediate commencement of work were critical. Agencies delaying land acquisition or groundwork would face contract termination, he warned. Under the Kusum-C scheme, CESC targeted the generation of at least 5 MW of solar power within the next three months. However, despite signing PPAs months ago, several agencies failed to take the first step. "If these firms do not treat the matter with urgency and continue to cite unresolved land issues, we will be left with no choice but to cancel their contracts," he cautioned. by Taboola by Taboola Sponsored Links Sponsored Links Promoted Links Promoted Links You May Like This Could Be the Best Time to Trade Gold in 5 Years IC Markets Learn More Undo Raju also directed that work should begin wherever land is currently available—be it govt or private. In areas where land acquisition is difficult, engineers must identify alternative options on priority. "Executive engineers must instruct junior engineers to locate available land locally and move ahead without delay. Govt land may not be available everywhere, but that cannot be an excuse to stall the project," he added. CESC director (technical) DJ Divakar, Mysuru zone chief engineer Mrutyunjaya, Hassan zone chief engineer Harish, and general manager (IT & MIS) Ramaswamy were present.


Time of India
an hour ago
- Time of India
City's Multi-Modal Transport Hub Gets Green Light, State Clears Land-Use Change Near Station
Nagpur: Maharashtra govt formally sanctioned changes to Nagpur's city development plan, clearing the decks for the much-delayed Multi-Modal Transport Hub (MMTH) near railway station. The project, intended to integrate bus, Metro, rail, and commercial services, now gained traction with the official conversion of key land parcels from public and institutional use into commercial zone. The decision was notified by the urban development department on July 28 and disclosed to the Nagpur bench of the Bombay high court on Thursday. During the hearing, Justices Mukulika Jawalkar and Praveen Patil were informed that the land earmarked for the Maharashtra and Madhya Pradesh state road transport corporations, along with a portion occupied by Nehru Model High School in Mouza Sitabuldi, would now be part of the MMTH layout. The court was also told that these lands were reclassified for commercial use in line with the revised development plan. The move follows the civic body's earlier failure to reserve space for vendors displaced by the demolition of an old flyover near the station, prompting the court to question the govt's "contradictory stance" on rehabilitation. Advocate Mahesh Dhatrak, appearing for the petitioners, reminded the bench that the court had previously directed the Nagpur Municipal Corporation (NMC) to provide alternative space to displaced vendors. by Taboola by Taboola Sponsored Links Sponsored Links Promoted Links Promoted Links You May Like 5 Books Warren Buffett Wants You to Read In 2025 Blinkist: Warren Buffett's Reading List Undo The new plan now includes vendor resettlement within a proposed multi-storey parking facility on the MMTH site. The sanctioned notification imposes three conditions before execution: A no objection certificate (NOC) from the defence department for overlapping land; legal compliance with pending litigation regarding MPSRTC land (Writ Petition No. 609/2019); and NOCs from the Maharashtra State Road Transport Corporation and Railways. MahaMetro was directed to respond within three weeks on acquisition procedures, and the state govt must also clarify funding provisions. The govt stated, "Lands so released are shown as 'Multi-Modal Transport Hub' as per the sanctioned plan." The updated zoning map is open for public inspection at the NMC commissioner's office for one month.


Economic Times
an hour ago
- Economic Times
Food businesses must display license, QR code of mobile app to register consumer complaints: FSSAI
Food regulator FSSAI has directed all food business operators (FBOs) to display licences at an appropriate place in their premises. They have also been told to display QR code of a mobile app meant for registering consumer complaints. The move is aimed at empowering consumers and ensuring food safety. "Food Safety and Standards Authority of India (FSSAI) has asked all FBOs, including restaurants, dhabas, cafes, and eateries, to display their FSSAI License/ registration certificate with the QR code of Food Safety Connect App in customer-visible areas, such as entrances, billing counters, or seating areas," according to a statement. FSSAI said it has made the QR code of the app available on the front page of the FSSAI Licence and Registration. All FBOs have been asked to display this in their premises. This is in compliance with Condition of License number 1 of the FSS (Licensing and Registration of Food Businesses) Regulations, 2011. The operators have also been asked to feature the QR code or a direct download link for the 'Food Safety Connect' app on their websites and online ordering platforms, wherever applicable. Consumers can register their complaints regarding food safety and hygiene issues. They can also report misleading claims on food products besides accessing basic information about licensed and registered FBOs, the statement said. PTI