Salim Water Treatment Plant upgrading works ahead of schedule, expect completion in June 2027, says Julaihi

Salim Water Treatment Plant upgrading works ahead of schedule, expect completion in June 2027, says Julaihi

Borneo Post25-04-2025
Julaihi (third left) reviews the progress of the water treatment plant upgrade during the site visit today.
SIBU (April 25): The upgrading project of the Salim Water Treatment Plant in Sibu has reached 17.96 per cent completion, ahead of the initial target of 6.45 per cent, said Sarawak Minister of Utility and Telecommunication, Dato Sri Julaihi Narawi.
He said the upgrade will double the plant's capacity from 150 million litres per day (MLD) to 300 MLD, enabling a 30 per cent water reserve margin for Sibu and its surrounding areas once completed.
'We've seen steady progress since the project started in May 2024.
'This project is not only progressing smoothly but is also ahead of schedule. We expect it to be completed as planned and capable of supplying clean water to 350,000 residents in the Sibu area,' he told reporters after a working visit to the site at Muka Sauk, Sibu Water Board (SWB), Jalan Stabau today.
Julaihi said the RM291 million project, funded entirely by the Sarawak government, carries a contract value of RM269 million.
It is part of the Sarawak Water Supply Master Plan and supports the implementation of the state's water grid system aimed at interconnecting water treatment plants across the state.
At present, Julaihi said Sibu is served by two main plants — Salim (150 MLD) and Bukit Lima (45 MLD) — with a combined capacity of 195 MLD.
However, daily demand has already surpassed this, reaching 200 MLD, resulting in both plants operating beyond capacity.
'As a long-term solution, the Sarawak government has also approved RM1.1 billion for the replacement and upgrade of old pipes across the state, covering 2,740 km of pipelines, to be implemented over five years.
'For the Sibu Division alone, RM170 million has been allocated,' he said.
He also noted that a new water supply system at Sungai Sadit has been completed and will help boost Sibu's water reserve margin.
'This isn't an overnight solution. It's a long-term plan we're executing through the water master plan and the Sarawak water grid system,' said the Sebuyau assemblyman.
Meanwhile, SWB clarified that the total project cost of RM291.4 million includes construction, land acquisition for the raw water pipeline, site supervision, and professional fees.
Key components of the project include the Phase 2 upgrade of the raw water intake from 150 MLD to 300 MLD; construction of an 8 km new raw water pipeline using 1.4m diameter mild steel pipes; upgrading of the Salim Treatment Plant from 150 MLD to 300 MLD; modification of existing components in Salim Treatment Plant Phases 1 and 2 (sludge bridge, generator set, filters); and construction of a 4km treated water pipeline (2km with 1.6m diameter and 2km with 1.2m diameter).
'The project was awarded to contractor Perbena Emas Sdn Bhd through an open tender and granted on April 18, 2024, with a contract value of RM269,099,341.13.
'Construction works began on May 20, 2024, and are expected to be completed by June 25, 2027,' the board stated.
Upon completion, the upgraded plant will be capable of meeting the water supply needs of 350,000 residents in Sibu, Kanowit, Selangau, Maradong, and Rassau through to 2036.
Accompanying Julaihi during the site visit were the Permanent Secretary of the State Ministry of Utility and Telecommunication, Datu Jafri Lias; Rural Water Supply Department (JBALB) director, Ir Ts Awg Mohammad Fadillah Awg Redzuan; and SWB general manager Abdul Malik Abdullah. julaihi narawi Salim Water Treatment Plant Sibu
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

RM1.1 million for village, school projects in Kampung Kiau
RM1.1 million for village, school projects in Kampung Kiau

Daily Express

time3 days ago

  • Daily Express

RM1.1 million for village, school projects in Kampung Kiau

Published on: Monday, August 11, 2025 Published on: Mon, Aug 11, 2025 By: Bernama Text Size: KOTA BELUD: The government has allocated RM1.1 million for development projects in Kampung Kiau under the Madani Adopted Village and School programme. The funding was announced by Minister of Entrepreneur Development and Cooperatives Datuk Ewon Benedick. Advertisement Of the total, RM1 million will fund seven small-scale infrastructure projects in the village. Another RM100,000 was granted to the Parent-Teacher Association of Sekolah Kebangsaan Kiau. The village projects include road upgrades, agricultural pathways, and public amenities across Kampung Kiau Nuluh, Kampung Kiau Taburi, and Kampung Kiau Bersatu. Specific works involve improving field roads, halls, clinics, and drainage systems in multiple zones. Advertisement Ewon shared these details during the launch of the Tourism Development Programme at SK Kiau. He highlighted that SK Kiau is his alma mater, having studied there from Year One to Year Six. The minister expressed hope that the allocation would address key development needs in the village and school. He also urged villagers to leverage natural resources in agriculture, tourism, and cooperatives for socio-economic growth. The event marked the official handover of funds under the Madani Adopted Village initiative. * Follow us on our official WhatsApp channel and Telegram for breaking news alerts and key updates! * Do you have access to the Daily Express e-paper and online exclusive news? Check out subscription plans available. Stay up-to-date by following Daily Express's Telegram channel. Daily Express Malaysia

RM1.1m allocated for Madani village, school projects in Kg Kiau
RM1.1m allocated for Madani village, school projects in Kg Kiau

The Sun

time5 days ago

  • The Sun

RM1.1m allocated for Madani village, school projects in Kg Kiau

KOTA BELUD: The government has allocated RM1.1 million for development projects in Kampung Kiau under the Madani Adopted Village and School programme. The funding was announced by Minister of Entrepreneur Development and Cooperatives Datuk Ewon Benedick. Of the total, RM1 million will fund seven small-scale infrastructure projects in the village. Another RM100,000 was granted to the Parent-Teacher Association of Sekolah Kebangsaan Kiau. The village projects include road upgrades, agricultural pathways, and public amenities across Kampung Kiau Nuluh, Kampung Kiau Taburi, and Kampung Kiau Bersatu. Specific works involve improving field roads, halls, clinics, and drainage systems in multiple zones. Ewon shared these details during the launch of the Tourism Development Programme at SK Kiau. He highlighted that SK Kiau is his alma mater, having studied there from Year One to Year Six. The minister expressed hope that the allocation would address key development needs in the village and school. He also urged villagers to leverage natural resources in agriculture, tourism, and cooperatives for socio-economic growth. The event marked the official handover of funds under the Madani Adopted Village initiative. - Bernama

RM1.1 million for Kampung Kiau development, SK Kiau adopted under Madani Programme
RM1.1 million for Kampung Kiau development, SK Kiau adopted under Madani Programme

Borneo Post

time5 days ago

  • Borneo Post

RM1.1 million for Kampung Kiau development, SK Kiau adopted under Madani Programme

Ewon launches the Sir Hugh Low Heritage Trail, developed by Koperasi Minitinduk Kiau Kota Belud, as one of Kg Kiau's tourism products. KOTA BELUD (Aug 9): The government, through the Ministry of Entrepreneur Development and Cooperatives (KUSKOP), has allocated RM1.1 million for the Kampung Angkat Madani and Sekolah Angkat Madani development projects in Kampung Kiau here. Minister Datuk Ewon Benedick said RM1 million would go towards seven small-scale infrastructure projects in the village, while RM100,000 has been channelled to the Parent-Teacher Association (PIBG) of Sekolah Kebangsaan (SK) Kiau. The Kampung Angkat Madani projects include road upgrades, improved drainage, and enhancements to public facilities in Kampung Kiau Nuluh, Kampung Kiau Taburi, and Kampung Kiau Bersatu. 'Among the projects implemented are upgrading the field road, community hall, clinic and village hall in Kampung Kiau Nuluh; constructing drains in Zones Tebobon and Hongkung; building a road and culvert to the cemetery in Kampung Kiau Taburi; and constructing a community road and drainage system in Zone Tomoduh, Kampung Kiau Bersatu,' Ewon said. He was speaking after officiating the Tourism Development Programme Through the Cooperative Movement and the handover ceremony for the Kampung Angkat Madani and Sekolah Angkat Madani projects at Dewan Tamu Desa Kg Kiau on Saturday. For the Sekolah Angkat Madani initiative, RM100,000 was allocated to SK Kiau's PIBG for school development needs. 'SK Kiau is my adopted school, where I studied from Year 1 to Year 6. I hope that with this allocation, part of the development needs in my village, including those at SK Kiau, can be met,' he said. Ewon also encouraged villagers to harness the area's natural resources — particularly in agriculture, tourism and cooperatives — to further boost socio-economic growth. Also present were KUSKOP Secretary-General Datuk Sri Khairul Dzaimee Daud, Malaysian Cooperative Commission (SKM) Chief Executive Officer Noor Affifah Abdul Razak, as well as KUSKOP agency heads and village leaders. As part of the event, Ewon launched the Sir Hugh Low Heritage Trail, developed by Koperasi Minitinduk Kiau Kota Belud, as one of Kampung Kiau's tourism products.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store