
Five possible locations for new bridge which will form part of the highly-anticipated Enniscorthy Flood Relief Scheme are revealed
Frustration has festered over the long wait for the scheme to be approved and for work to finally begin on a plan that hopes to address the frequent flooding experienced by the town's residents.
Enniscorthy has experienced significant flooding over the years, the latest incident being in 2021, with many homeowners and businessowners struggling to get insurance and having to throw out damaged furniture repeatedly.
Following a recent visit by Minister for the Office of Public Works Kevin Moran to Enniscorthy to reiterate the government's commitment to seeing the deliverance of the current Flood Relief Scheme, the project has entered the consultation stage.
The scheme is to be delivered in two phases. Phase One of the scheme will involve the removal of the Seamus Rafter Bridge, which poses a significant obstruction to river flow through the town centre during flood events, and the construction of a new road bridge and new pedestrian bridge to replace the Seamus Rafter Bridge.
Phase Two of the scheme will involve the construction of the remaining flood relief works required for the town.
The spokesperson for the council emphasised the need for public consultation and support: 'Flooding represents a risk to the health and safety of the community, causes significant property damage, and disruption to commercial activity and traffic in the town. The flood relief scheme will protect over 300 homes and businesses in the area from the ongoing risk of flooding.'
"The bridge will be removed and replaced by a road bridge and pedestrian bridge that will accommodate for future flood levels and provide segregated pedestrian and cyclist facilities.'
In preparation, a constraints study was carried out to identify all factors that will influence the design of Phase One of the scheme. This was the first step in the option selection process and outlines the key environmental constraints, including physical (topography, river and built environment) and environmental constraints ( River Slaney SAC, biodiversity, landscape and visual, and cultural heritage), that have the potential to affect the design and location of the scheme.
On Tuesday, May 13, locals were presented with multiple options that they could give their feedback on. The first option was not considered feasible following a preliminary assessment, so options 2 to 5B were presented to the public.
Option 2 is located approximately 890m downstream of the Seamus Rafter Bridge, connecting between the R772 Wexford Road just north of Killagoley Lane to the R774 St John's Road north of the River Urrin.
Option 3 is located approximately 600m downstream of the Seamus Rafter Bridge (or c.100m south of the Riverside Hotel), connecting between the R772 Wexford Road the R774 St John's Road north of the Arnolds Cross (Parnell Road).
Option 4 is located approximately 570m downstream of the Seamus Rafter Bridge (or c.75m south of the Riverside Hotel), connecting between the R772 Wexford Road the R774 St John's Road north of the Arnolds Cross (Parnell Road).
Option 5A is located approximately 120m downstream of the Seamus Rafter Bridge, connecting between the R772 Wexford Road and The Promenade. The bridge is set at a level of c7.8m OD, which is up to five metres above the existing quay / road level and allows for the design flood level plus 600mm freeboard.
Option 5B is the same bridge location as Option 5A, however the southwest ramp connecting to The Promenade is omitted. While the connection from Quay Street to The Promenade would still be severed, access to The Promenade is maintained via Mill Yard Land and Salthouse Lane.
However, it was noted that Options 2, 3 and 4 would require the provision of a pedestrian / cycle bridge in proximity of the existing Seamus Rafter Bridge, given that the diversion distance of 1.4 – 2.2km via the replacement road bridge would be an excessive diversion for walking or cycling.
Following initial feedback, public opinion is currently leaning towards the fifth options. Residents can access a feedback form online and can submit their response by the cut off date of Tuesday, June 10.
In attendance on the day was Cllr Jackser Owens, who despite welcoming public participation on the plan, has thrown doubts over the expected timeline of the project.
"It is unlikely it was start in 2026 as planned – there is too much red tape. When I asked the consultants on the day they said that this and that needed to be done had to be done first. I am 70 years of age and I doubt I will see this done in my lifetime.'
He added that himself and others were left with more questions than answers on the day as well.
"They said that despite the feedback, the scheme could be denied based on environmental factors again in the future. People also asked how the plan would affect the people on Island Rd and they couldn't answer. People are sick of listening to this over the years. So I am calling on all Oireachtas representatives in the county to come out and do something.'

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


RTÉ News
03-06-2025
- RTÉ News
Judge to decide on suspension of Sceilg Mhichíl permits
A High Court judge will decide this week whether to lift a suspension on boating permits for ferries to and from the UNESCO heritage island Sceilg Mhichíl, saying the case requires top priority as "people's livelihoods are at risk". The permits have not been issued while legal proceedings are before the courts in the form of a judicial review of the tendering process. At the High Court, Mr Justice Garret Simons said he was "staggered" by the assertion made by lawyers for the Office of Public Works that it would need six months to prepare the case. He ordered it to be heard next month. Two companies, which were unsuccessful in their applications for the 2025 season, have made a judicial review application, resulting in a delay to the granting of permits. The season runs from May to the end of September. The OPW ran a competition in late 2024 to award 15 boating permits for summer 2025 serving the monastic island, which was chosen as a film location for the Star Wars movies, The Force Awakens and The Last Jedi. However, in April 2025, two unsuccessful participants in the competition brought High Court proceedings challenging the outcome. The OPW said that under Irish and EU law, it was then precluded from issuing permits for the 2025 summer season until legal proceedings were resolved. Skellig Michael Boat Trips and Atlantic Endeavour Limited both dispute the process underpinning the granting of the licences, alleging it to be "deficient" and "without transparency" and have been granted permission for the challenge. At the High Court, David Dodd BL, for the plaintiffs, told Mr Justice Simons that nobody wanted to prevent boats from visiting the island. He said permits could be granted by the court in an interim fashion, as the issuing of a one-season permit was not a "contract", as contended by the OPW. He said his clients are happy for the suspension to be lifted. Mr Justice Simons asked Andrew Beck SC, for the OPW, why it would take six months to prepare for what the judge described as "the most straightforward case of competition for licences". Mr Beck said there was discovery of documents needed, amendments to make and a possible issue around cross-examination. Mr Justice Simons said he was "staggered" that the case would take up to six months to get on and that there were "livelihoods" at stake. The judge said the court would give the case "top priority", adding that the court had "gone out of its way" to facilitate an early trial. Mr Justice Simons said he would rule on Thursday of this week on whether to lift the suspension of the permits. He adjourned the substantive hearing of the judicial review to 21 July.


Irish Examiner
03-06-2025
- Irish Examiner
Skellig Michael delayed boat permits row to be decided this week
A High Court judge has given "top priority" for a case involving the granting of boat permits to ferry people to Skellig Michael. Mr Justice Garrett Simons will decide this week whether or not to lift a suspension on boating permits needed to bring tourists to and from the UNESCO heritage island Skellig Michael, saying "people's livelihoods are at stake". The permits have not been issued while legal proceedings are before the courts in the form of a judicial review of the tendering process. At the High Court on Tuesday, Mr Justice Simons said he was "staggered" by the assertion made by lawyers for the Office of Public Works (OPW) claiming it would need six months to prepare the case and ordered it to be heard next month, giving it "top priority". The granting of permits to successful applicants was delayed as two companies who were unsuccessful in their applications for the 2025 season, which runs from May to the end of September, launched a legal challenge. The OPW ran a competition in late 2024 to award 15 boating permits for summer 2025 and serving the monastic island, which was chosen as a film location for the Star Wars movies The Force Awakens and The Last Jedi. However, in April 2025, two unsuccessful participants in the competition brought High Court proceedings challenging the outcome of the competition. The OPW has said that under Irish and EU law, the OPW was then precluded from issuing permits for the 2025 summer season until legal proceedings were resolved. Skellig Michael Boat Trips and Atlantic Endeavour Limited both dispute the process underpinning the granting of the licences, alleging it to be "deficient" and "without transparency" and have been granted permission for the challenge. At the High Court, David Dodd, counsel for the plaintiffs, told Mr Justice Simons that nobody wanted the boats to not visit the island and that permits could be granted by the court in an interim fashion, as the issuing of a one-season permit was not a "contract", as contended by the OPW. Mr Dodd said he was resisting a suggested "five-year framework" on the OPW's granting of the permits as part of a contract but that the plaintiffs also wanted to see the boats out. Mr Dodd said the OPW, in applying to the court to have the suspension lifted, had referred to a "contract" having to be in place for the boats to take to sea. Mr Dodd said there should be no such "contract" and that permits issued were akin to planning permission or a gun permit being granted, neither or which, he claimed, were "contracts" nor necessitated frameworks. Mr Dodd said that a permit is a statutory permit without an offer or an acceptance as found in a contract. Whether or not this granting amounted to a "contract", was a matter for the full hearing of the substantive case, he said. "We are happy, however, for the suspension to be lifted," he said. Mr Justice Simons asked Andrew Beck, counsel for the OPW, how it was possible that the OPW was looking for six months to prepare the case in what the judge described as "the most straightforward case of competition for licences". Mr Beck said there was discovery of documents needed, amendments to make and a possible issue around cross examination. Mr Justice Simons said he was "staggered" that the case would take up to six months to get on and that there were "livelihoods" at stake. The judge said the court would give the case "top priority", adding the court had "gone out of its way" to facilitate an early trial. Mr Justice Simons said he would rule on Thursday of this week on whether or not he would lift the suspension of the permits and adjourned the substantive hearing of the judicial review to July 21.


Irish Independent
30-05-2025
- Irish Independent
New Garda Station for County Sligo town replacing existing premises dating from the 1960s
The Office of Public Works has confirmed that refurbishment works at a state-owned building will accommodate a new Garda Station building for Tubbercurry, that will be fully refurbished right next door to the current one. The news has been welcomed by local FF TD Eamon Scanlon 'I am delighted to receive this confirmation from the Office of Public Works. Their plans for the Garda station are exciting, and this is a long-standing issue which will now be addressed. 'I have worked on this issue for many years. I had the now Minister of State, Kevin Boxer Moran visit the current station back in 2016,' he said. 'The current station dates back all the way to 1960 and is now completely unfit for purpose." The work will consist of a deep retrofit to include a fabric/energy upgrade, new windows, solar water heating, PV panel installation and a fire escape, confirmed Scanlon. He said: 'Tubbercurry is the third busiest station in the Sligo-Leitrim division and this building no longer meets the needs of a functioning Garda Station. After the Statutory Submissions such as Part IX Planning submission, together with Fire Certification and Disability Access applications are granted, the project will progress to tender preparation. Deputy Scanlon said that the benefits of the provision of a new station for the people of Tubbercurry, the Gardaí based in the station, and the broader communities will be clear to see. 'This has been a long time coming, and the establishment of a new station will allow the enhancement of new facilities for staff, and in essence, that will be a great support for the local community.'