Report reveals stalled housing projects in KwaZulu-Natal

Report reveals stalled housing projects in KwaZulu-Natal

IOL News5 days ago
A report on blocked and stalled projects was presented to the KwaZulu-Natal Legislature Human Settlements Portfolio Committee, highlighting the nature of the challenges, proposed interventions, and progress on houses
Image: KwaZulu-Natal Human Settlements
A 62-page summarised report by the Department of Human Settlements (DHS) in KwaZulu-Natal depicted the dire straits of housing projects in the province.
The report on blocked and stalled projects was presented to the KZN Legislature's Human Settlements Portfolio Committee recently. It highlighted the nature of the challenges, proposed interventions, and progress to date on the implementation of the development interventions.
There are several blocked projects in the report, with the most being eight in the Ilembe District Municipality.
Charlestown Housing, a R62 million project with a contract date from December 20, 2019, to April 30, 2025; sites approved 1,200, with houses delivered 295. The project is blocked due to the lack of a bulk water supply. Initially, the project area was connected to Pixley ka Seme Municipality (Mpumalanga Province) for bulk water supply, which was later cut off due to high demand. The Newcastle Municipality is currently acquiring funds for the provision of bulk water supply.
The Mbazwana Rectification 426 unit housing scheme has not broken soil as yet. The department cannot proceed with the Supply Chain Management processes to appoint a service provider before beneficiary verification has been concluded.
Video Player is loading.
Play Video
Play
Unmute
Current Time
0:00
/
Duration
-:-
Loaded :
0%
Stream Type LIVE
Seek to live, currently behind live
LIVE
Remaining Time
-
0:00
This is a modal window.
Beginning of dialog window. Escape will cancel and close the window.
Text Color White Black Red Green Blue Yellow Magenta Cyan
Transparency Opaque Semi-Transparent Background Color Black White Red Green Blue Yellow Magenta Cyan
Transparency Opaque Semi-Transparent Transparent Window Color Black White Red Green Blue Yellow Magenta Cyan
Transparency Transparent Semi-Transparent Opaque
Font Size 50% 75% 100% 125% 150% 175% 200% 300% 400% Text Edge Style None Raised Depressed Uniform Dropshadow Font Family Proportional Sans-Serif Monospace Sans-Serif Proportional Serif Monospace Serif Casual Script Small Caps
Reset
restore all settings to the default values Done
Close Modal Dialog
End of dialog window.
Advertisement
Video Player is loading.
Play Video
Play
Unmute
Current Time
0:00
/
Duration
-:-
Loaded :
0%
Stream Type LIVE
Seek to live, currently behind live
LIVE
Remaining Time
-
0:00
This is a modal window.
Beginning of dialog window. Escape will cancel and close the window.
Text Color White Black Red Green Blue Yellow Magenta Cyan
Transparency Opaque Semi-Transparent Background Color Black White Red Green Blue Yellow Magenta Cyan
Transparency Opaque Semi-Transparent Transparent Window Color Black White Red Green Blue Yellow Magenta Cyan
Transparency Transparent Semi-Transparent Opaque
Font Size 50% 75% 100% 125% 150% 175% 200% 300% 400% Text Edge Style None Raised Depressed Uniform Dropshadow Font Family Proportional Sans-Serif Monospace Sans-Serif Proportional Serif Monospace Serif Casual Script Small Caps
Reset
restore all settings to the default values Done
Close Modal Dialog
End of dialog window.
Next
Stay
Close ✕
Cedera Housing project, worth R44 million, started in July 2016 with a contract end date of March 2018. However, only 100 units were built out of 623. The targeted beneficiaries are residents at Khanye Village, which is the staff accommodation for the workers of Cedara College. However, over the years, these families have grown, and some workers have retired but remained in the village. The project was stalled because of insufficient bulk services and the school site encroaching. The Umgungundlovu District has no funds to complete the bulk services.
No funding in the Umgungundlovu Municipality for bulk services led to the stalling of 500 homes for the Kheyalisha Housing Project from December 2007.
The Chief Albert Luthuli Housing Project, a R43 million project for 1,000 homes, was contracted between February 2005 to October 2010. Only 394 houses were built. The implementing agent abandoned the project due to financial challenges and left units incomplete. There was also poor workmanship and non-performance noted before the municipality terminated the service provider. The department has repackaged the project as a rectification and rehabilitation project to address the assessment's findings.
Umzinto Slum Clearance Housing Project worth R269 million contracted from April 1, 2012, to December 2017. Of the 1,925 sites, only 500 units were built. The project was identified by uMdoni Municipality to clear six informal settlements, but due to the non-availability of bulk sanitation infrastructure, it was stalled.
Riona Gokool, MPL and DA KZN spokesperson on Human Settlements, said the 4th Quarter performance reports have revealed a litany of issues.
Gokool stated that the DHS failed to resolve dozens of blocked projects, many of which have been stagnant for more than a decade.
'These projects represent billions of rand in public funds and affect thousands of intended beneficiaries, yet the department has provided no clear roadmap for completion. There should be a comprehensive action plan for all blocked projects, with district-specific timeframes. A moratorium should be placed on new projects until current backlogs are resolved,' Gokool said.
Two weeks ago, during a discussion over his 400 days in office as the MEC for Transport and Human Settlements, Siboniso Duma expressed his commitment to tackling delays in housing construction.
He stated that his department had reduced blocked housing projects from 68 to 15.
zainul.dawood@inl.co.za
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Search for missing pilot after tragic crash at Durban North airshow
Search for missing pilot after tragic crash at Durban North airshow

IOL News

time3 days ago

  • IOL News

Search for missing pilot after tragic crash at Durban North airshow

Authorities are on the scene where a plane crashed into the sea on Thursday afternoon Image: ALS Paramedics A light aircraft participating in an airshow at Durban North crashed into the ocean on Thursday afternoon, prompting a large-scale search for the missing pilot. The Accident and Incident Investigations Division (AIID) confirmed the incident, which occurred near Suncoast Casino at approximately 13:45. 'The accident occurred at approximately 13:45 when the ZS-AEC Extra 300 aircraft that was performing its final display crashed into the sea,' the AIID said in a media statement. 'The Emergency Medical Services and law enforcement immediately attended to the scene. The AIID will provide updates as soon as further information is available.' ALS Paramedics reported that emergency personnel, including SAPS, Symmetry Police Search and Rescue Units, the T25 department, and the National Sea Rescue Institute (NSRI), were deployed. 'NSRI and lifeguards are currently at the site, and paramedics are standing by on the shoreline for medical assistance; further updates to follow,' ALS Paramedics stated. 'The SAPS helicopter, together with lifesavers and NSRI boats, is on the water trying to locate the missing pilot. Lifesavers are also on the water. All necessary authorities are in attendance; however, the pilot has not been found as yet. Further updates to follow,' ALS Paramedics said. Video Player is loading. Play Video Play Unmute Current Time 0:00 / Duration -:- Loaded : 0% Stream Type LIVE Seek to live, currently behind live LIVE Remaining Time - 0:00 This is a modal window. Beginning of dialog window. Escape will cancel and close the window. Text Color White Black Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Background Color Black White Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Transparent Window Color Black White Red Green Blue Yellow Magenta Cyan Transparency Transparent Semi-Transparent Opaque Font Size 50% 75% 100% 125% 150% 175% 200% 300% 400% Text Edge Style None Raised Depressed Uniform Dropshadow Font Family Proportional Sans-Serif Monospace Sans-Serif Proportional Serif Monospace Serif Casual Script Small Caps Reset restore all settings to the default values Done Close Modal Dialog End of dialog window. Advertisement Video Player is loading. Play Video Play Unmute Current Time 0:00 / Duration -:- Loaded : 0% Stream Type LIVE Seek to live, currently behind live LIVE Remaining Time - 0:00 This is a modal window. Beginning of dialog window. Escape will cancel and close the window. Text Color White Black Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Background Color Black White Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Transparent Window Color Black White Red Green Blue Yellow Magenta Cyan Transparency Transparent Semi-Transparent Opaque Font Size 50% 75% 100% 125% 150% 175% 200% 300% 400% Text Edge Style None Raised Depressed Uniform Dropshadow Font Family Proportional Sans-Serif Monospace Sans-Serif Proportional Serif Monospace Serif Casual Script Small Caps Reset restore all settings to the default values Done Close Modal Dialog End of dialog window. Next Stay Close ✕ The crash happened during the airshow segment of the Next Generation of Aviation Professionals Summit, hosted at the Durban International Convention Centre this week. The summit, which began earlier in the week, is the third annual global meeting organised by the International Civil Aviation Organisation (ICAO) and the South African Civil Aviation Authority (SACAA). Authorities have not yet released details on the cause of the crash or the identity of the pilot. THE MERCURY

KwaZulu-Natal to close emergency accommodations for flood victims by January 2027
KwaZulu-Natal to close emergency accommodations for flood victims by January 2027

IOL News

time5 days ago

  • IOL News

KwaZulu-Natal to close emergency accommodations for flood victims by January 2027

The KwaZulu-Natal Legislature Human Settlements Portfolio Committee was briefed on plans to provide houses for flood victims. Image: Shan Pillay All Transitional Emergency Accommodations (TEA) will be closed by January 2027, stated the KwaZulu-Natal Human Settlements Department (DHS) on Wednesday. In a report to the KZN Legislature Human Settlements Portfolio Committee, the department recorded that it had spent R185 million on TEA rental for flood victims from December 2022 to December 2024, and an additional R128 million for every 12 months thereafter. The DHS is projecting that 837 houses will be completed by December 2026, and that 375 flood victims will be housed at Montclair Lodge and Cornubia Temporary Residential Units (TRUs) while building their permanent houses, targeted for completion by June 2027. According to the DHS flood victim status report, there are 1,195 families in TEU as of June 2025. Video Player is loading. Play Video Play Unmute Current Time 0:00 / Duration -:- Loaded : 0% Stream Type LIVE Seek to live, currently behind live LIVE Remaining Time - 0:00 This is a modal window. Beginning of dialog window. Escape will cancel and close the window. Text Color White Black Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Background Color Black White Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Transparent Window Color Black White Red Green Blue Yellow Magenta Cyan Transparency Transparent Semi-Transparent Opaque Font Size 50% 75% 100% 125% 150% 175% 200% 300% 400% Text Edge Style None Raised Depressed Uniform Dropshadow Font Family Proportional Sans-Serif Monospace Sans-Serif Proportional Serif Monospace Serif Casual Script Small Caps Reset restore all settings to the default values Done Close Modal Dialog End of dialog window. Advertisement Next Stay Close ✕ In an updated report before the committee on the resettlement of 2022 and 2025 flood victims, the DHS identified seven problems. They were: Land parcels rezoning/statutory compliance for the 2022 disaster victims' permanent shelter solution was completed after two years, against the expectation of a shorter period. There is no additional funding for bulk infrastructure services and top structures estimated at R 1.7 billion if building on six identified land parcels, and R681 million if building at Cornubia. Communities already living near the rezoned identified land parcels do not want flood victims to be settled in these land parcels. There is no funding for TEA rent, and it depletes departmental resources, which would have been spent on service delivery. The department has spent R185 million on TEA rent from December 2022 to December 2024, and an additional R128 million for every 12 months. Flood victims are inconvenienced as they do not have complete privacy where they live. They no longer enjoy the perpetual stay in TEAs. The KZN province, particularly in eThekwini, continues to suffer from disasters, as could be seen with the 2025 emergencies in Lamontville and Umlazi. The department stated that the construction of 108 houses in Cornubia, north of Durban, could commence this month. For the Cornubia area, the DHS has allocated R420 million from the Urban Settlements Development Grant (USDG) and the Informal Settlements Upgrading Programme grant (ISUPG) for bulk services from the 2025 /26 budget. The department stated that R25 million from Capital Balances had already been allocated to complete 108 houses in October 2025. The balance of the money will be made available in the 2026/27 financial year. The 692 houses are scheduled for completion by the end of December 2026, and it is anticipated that the flood victims will move in during December 2026 and January 2027. The DHS stated that 20 houses for flood victims are under construction at Illovo, costing R3.8 million. The completion of these houses will close Ilfracombe and Adams TEUs. It warned that the seven rezoned lands under eThekwini Metro will be utilised for the normal housing projects to address the backlog. The DHS stated that, together with affected municipalities, it will conduct an intensive social facilitation on communities that refuse to accept flood victims and other developments in their backyards.

Captain Hook: The Cape fur seal's inspiring rescue from fish hooks
Captain Hook: The Cape fur seal's inspiring rescue from fish hooks

IOL News

time5 days ago

  • IOL News

Captain Hook: The Cape fur seal's inspiring rescue from fish hooks

Captain Hook, a Cape fur seal, faced a life-threatening situation with fish hooks embedded in his mouth and back. Image: South African Association for Marine Biological Research (Saambr) Last month, the South African Association for Marine Biological Research (Saambr) shared a heart-wrenching and intriguing story about a young Cape fur seal, now affectionately named Captain Hook, who was admitted into their care. This two-and-a-half-year-old seal captured hearts after he was found with fish hooks lodged in his mouth and back — a rare sight in the KwaZulu-Natal coast, where only one other Cape fur seal has been documented in the past 21 years at uShaka Sea World's rehabilitation facility. Captain Hook was captured in eManzimtoti in early July, where it is believed he followed the Sardine Run up the coast. When the sardines were no longer visible, he needed a new plan. He saw what seemed like an endless supply of sardines connected to the end of the Toti fishermen's lines. Despite being hooked several times, he continued to steal the fishermen's bait, and it became increasingly apparent that he needed urgent medical attention. Video Player is loading. Play Video Play Unmute Current Time 0:00 / Duration -:- Loaded : 0% Stream Type LIVE Seek to live, currently behind live LIVE Remaining Time - 0:00 This is a modal window. Beginning of dialog window. Escape will cancel and close the window. Text Color White Black Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Background Color Black White Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Transparent Window Color Black White Red Green Blue Yellow Magenta Cyan Transparency Transparent Semi-Transparent Opaque Font Size 50% 75% 100% 125% 150% 175% 200% 300% 400% Text Edge Style None Raised Depressed Uniform Dropshadow Font Family Proportional Sans-Serif Monospace Sans-Serif Proportional Serif Monospace Serif Casual Script Small Caps Reset restore all settings to the default values Done Close Modal Dialog End of dialog window. Advertisement Video Player is loading. Play Video Play Unmute Current Time 0:00 / Duration -:- Loaded : 0% Stream Type LIVE Seek to live, currently behind live LIVE Remaining Time - 0:00 This is a modal window. Beginning of dialog window. Escape will cancel and close the window. Text Color White Black Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Background Color Black White Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Transparent Window Color Black White Red Green Blue Yellow Magenta Cyan Transparency Transparent Semi-Transparent Opaque Font Size 50% 75% 100% 125% 150% 175% 200% 300% 400% Text Edge Style None Raised Depressed Uniform Dropshadow Font Family Proportional Sans-Serif Monospace Sans-Serif Proportional Serif Monospace Serif Casual Script Small Caps Reset restore all settings to the default values Done Close Modal Dialog End of dialog window. Next Stay Close ✕ When he arrived at the rehabilitation facility, several hooks were safely removed from his mouth and back. The veterinary team gave him long-acting antibiotics to cover risks associated with the hooks and a painkiller. A radiograph showed he has a hook lodged in his oesophagus, but the uShaka Sea World veterinarian, Dr Francois Lampen, wanted the seal to settle and regain its strength before further intervention. Fortunately, Captain Hook's recovery journey is progressing positively, thanks to the right medical care and affection from seal experts at the rehabilitation centre. One of his caregivers, Hayley Tennant, said: 'As he is still in the young, playful stage of his life, we have given him some basketballs to wrestle with, both in the water and out of the water. I think I enjoy watching him play with the balls as much as he loves throwing and drowning them.' Saambr spokesperson Ann Kunz said that once Captain Hook settled down, and his blood results showed enough improvement to safely undergo anaesthesia, he was taken to the Village Veterinary Clinic in Kloof, where he underwent a gastroscope, which showed the hook previously seen in his oesophagus had moved into the muscle layer. Captain Hook was in a life-threatening situation with fish hooks embedded in his mouth and back. Image: South African Association for Marine Biological Research (Saambr) 'As the position of the hook is not impacting his health or movement in any way, the decision was made not to operate to remove the hook at this stage,' Kunz said. She said that Captain Hook's love for food and strong appetite, which had previously caused him trouble by boldly stealing bait from fishermen, is now working in his favour as he is gaining weight at a healthy rate. 'He loves his food and is fed a rich diet of pilchards, hake, sprats and squid, with squid being his least favourite (he believes squid is just like broccoli),' Kunz said. 'He still has a long way to go before he reaches his goal weight, but it is safe to say that he is now out of the woods and on the road to recovery.' Kunz added that Captain Hook remains under quarantine as a rabies precaution, but he has received his vaccination, and the team currently has no reason to believe he has been exposed to the virus before arriving at uShaka Sea World. Kunz reminded the public that in South Africa and Namibia, Cape fur seals have tested positive for rabies.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store